Professional Documents
Culture Documents
Rebar, 16mm dia, GR-40 282.00 m 75.00 21,150.00 26.25 7,402.50 28,552.50
Rebar, 20mm dia, GR-40 805.00 m 75.00 60,375.00 26.25 21,131.25 81,506.25
Rebar, 10mm dia, GR-33 6,793.00 m 29.30 199,013.67 10.25 69,654.79 268,668.46
G.I. Tie wire, Ga-16 337.00 kgs 70.00 23,590.00 21.00 7,077.00 30,667.00
Formwork Area 380.00 sq.m. 400.00 152,000.00 120.00 45,600.00 197,600.00
Finishing: 380.00 sq.m. - - -
Screened Sand 10.00 cu.m. 1,000.00 10,000.00 350.00 3,500.00 13,500.00
Portland Cement 1:2 cement-sand r 176.00 bags 260.00 45,760.00 91.00 16,016.00 61,776.00
Painting Works 380.00 sq.m. 96.00 36,480.00 96.00 36,480.00 72,960.00
Rebar, 20mm dia, GR-40 main bars 1,567.00 m 75.00 117,525.00 26.25 41,133.75 158,658.75
Finishing 809.60
Screened Sand 22.30 cu.m. 1,000.00 22,300.00 350.00 7,805.00 30,105.00
Portland Cement 393.00 bags 260.00 102,180.00 91.00 35,763.00 137,943.00
Painting Works 809.60 sq.m. 96.00 77,721.60 96.00 77,721.60 155,443.20
2.0 CHB Wall - 2nd
CHB, 100mm thick 4,508.90 pcs 18.00 81,160.20 6.30 28,406.07 109,566.27
Gravel 13.50 cu.m. 1,350.00 18,225.00 472.50 6,378.75 24,603.75
Sand 11.30 cu.m. 1,000.00 11,300.00 350.00 3,955.00 15,255.00
Cement 159.10 bags 260.00 41,366.00 91.00 14,478.10 55,844.10
Rebar, 10mm dia, GR-40 1,551.70 m 29.30 45,459.96 10.25 15,910.99 61,370.95
G.I. Tie wire, Ga-16 9.10 kgs 70.00 637.00 21.00 191.10 828.10
Finishing Area 655.80 sq.m. - - -
Finishing 809.60
Screened Sand 22.30 cu.m. 1,000.00 22,300.00 350.00 7,805.00 30,105.00
Portland Cement 318.00 bags 260.00 82,680.00 91.00 28,938.00 111,618.00
Painting Works 809.60 sq.m. 96.00 77,721.60 96.00 77,721.60 155,443.20
Rough Lumber 2x2; 400x400 spa 2,727.00 bd.ft. 62.00 169,074.00 18.60 50,722.20 219,796.20
1.0 Doors
D01: Tanguile Panel Door 2.4x1 16.0 unit 11,208.00 179,328.00 1,681.20 26,899.20 206,227.20
D02: Hollow Core Flush Type Door 2.054x0.9 2.0 unit 1,663.74 3,327.48 249.56 499.12 3,826.60
D03: Louver Type Double Swing Door 2.1x0.7 2.0 unit 1,029.00 2,058.00 154.35 308.70 2,366.70
SUMMARY
TOTAL DIRECT COST 13,047,348.09
Prepared by: CONTINGENCIES AND PROFIT(20%) 2,609,469.62
TAXES (12%) 1,565,681.77
TOTAL CONSTRUCTION COST 17,222,499.48
SEVENTEEN MILLION TWO HUNDRED NINETEEN THOUSAND SIX HUNDRED SIXTEEN AND SIXTY CENTAVOS
Approved By:
DR. NORDY D. SIASON JR.
Owner
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
0
1
2
3
4
5
6
7
8
9
B Construction of field office A Tue 2/01/22 Mon 2/07/22 7 Electrical, plumbing and
water pipe connections= 8
Plastering and tile works= 7
C Delivery of materials B Tue 2/08/22 Mon 2/14/22 7
11 18 Installation of
D Stalking and batter boards A Tue 2/01/22 Mon 2/07/22 7 plumbing fixtures
=5
E Excavation D Tue 2/08/22 Wed 2/16/22 9 =8 Stalking and
Back filling and
compaction, slab
Pouring of Beams and slabs forms &
Pouring of 2F beams
Installation of Painting and
installation of writing Final work and
Positioning of steel Pouring of columns= 9 reinforcing and various 2F CHB laying, column, roof Roof framing and roofing electrical wiring cleaning = 8
F Cutting and assembling of reinforcements D Tue 2/08/22 Thu 2/17/22 10 Clearing the site = 8 batter boards= 7 Excavation= 9 reinforcements= 14 footing= 7 on fill= 7 piping installations= 10 and slabs= 7 beam= 14 sheet= 9 and fixtures =12 boards = 14
GF CHB Laying= 14
1 2 5 8 9 10 12 13 14 15 16 17 19 22 23 24 25
G Positioning steel reinforcements E Fri 2/18/22 Wed 3/02/22 13
Construction of stairways and
H Form works for footing-column F Fri 2/18/22 Sat 2/26/22 9 installation of corridor
Cutting and assembling of Formwork for footing-
reinforcements = 10 column= 9 railings= 7
I Pouring of footing G Thu 3/03/22 Wed 3/09/22 7
6 7 21
J Back filling and compaction, slab on fill I Thu 3/10/22 Wed 3/16/22 7
K Electrical, plumbing and water pipe connections G Thu 3/03/22 Thu 3/10/22 8 Plumbing and drainage
system =5
L Pouring of columns J Thu 3/17/22 Fri 3/25/22 9
Construction of field Delivery of materials = 20
M GF CHB laying L Sat 3/26/22 Fri 4/08/22 14 office= 7 7 1
Beams and slabs forms & reinforcing and various 3 4 8
N piping installations M Sat 4/09/22 Mon 4/18/22 10
O Pouring of 2F beams and slabs N Tue 4/19/22 Mon 4/25/22 7
P 2F CHB laying, column, roof beam O Tue 4/26/22 Mon 5/09/22 14
Q Roof framing and roofing sheet P Tue 5/10/22 Wed 5/18/22 9
Construction of stairways and installation of
R corridor railings Q Thu 5/19/22 Wed 5/25/22 7
S Plastering and tile works P Tue 5/10/22 Tue 5/24/22 15
T Plumbing and drainage system Q Thu 5/19/22 Mon 5/23/22 5
U Installation of electrical wiring and fixtures Q Tue 5/24/22 Sat 6/04/22 12
V Installation of plumbing fixtures U Tue 5/31/22 Sat 6/04/22 5
W Painting and installation of writing boards V Sun 6/05/22 Sat 6/18/22 14
X Final work and cleaning W Sun 6/19/22 Sun 6/26/22 8
TOTAL COST 153
2 Storey 8 Classroom School Building
[JJP Construction]
Construction of
B
field office
Wooden Works 2.37 mh/m^2
Delivery of
C
materials
Stalking and batter
D
boards
E Excavation
Machine Excavation 0.5 mh/m^3
Cutting and
F assembling of
reinforcements
16mm 0.08 mh/kg
10mm 0.08 mh/kg
G Positioning steel
reinforcements
16mm 0.08 mh/kg
10mm 0.08 mh/kg
16mm 0.07 mh/kg
10mm 0.07 mh/kg
I Pouring of footing
Concrete Works 8.54 mh/m^3
Back filling and
J compaction, slab
on fill
Machine back fill 2 mh/m^3
Slab on Fill 5 mh/m^3
Electrical, plumbing
K and water pipe
connections
Quantity Unit Man-Hour Req T hours Manpower Req
1000 cu.m. 50
1000 cu.m. 30
500 sqm 845
500 sqm 500
1425 64 23
10
22519.66 kg 1801.5728
1539.2 kg 123.136
2424.7088 80 31
22519.66 kg 1801.5728
1539.2 kg 123.136
22519.66 kg 1576.3762
1539.2 kg 107.744
3608.829 104 35
37 cu.m. 315.98 56 6