Professional Documents
Culture Documents
BILL OF MATERIALS
1.0 Building & Occupancy permits to complete Owner Supplied 1.0 lot - - -
2.0 Documents Facilitations 1.0 lot - 10,000.00 10,000.00 10,000.00
3.0 Surety bond
a. Contractors all risk insurance 1.0 lot 25,000.00 25,000.00 6,250.00 6,250.00 31,250.00
b. Performance/guarantee bond 1.0 lot - - - -
c. Payment Bond 1.0 lot - - - -
d. Construction Bond 1.0 lot - - -
4.0 Mobilization/demobilization 1.0 lot - 15,000.00 15,000.00 15,000.00
5.0 Temporary facilities(including office) 1.0 lot 50,000.00 50,000.00 12,500.00 12,500.00 62,500.00
6.0 Light & Water bill
Temporary Electric Consumption Owner Supplied months
Concrete mix, 3000 psi 34.90 cu.m. 4,600.00 160,540.00 2,000.00 69,800.00 230,340.00
Rebar, 16mm dia, GR-40 282.00 m 75.00 21,150.00 26.25 7,402.50 28,552.50
Rebar, 20mm dia, GR-40 805.00 m 75.00 60,375.00 26.25 21,131.25 81,506.25
Rebar, 10mm dia, GR-33 6,793.00 m 29.30 199,013.67 10.25 69,654.79 268,668.46
G.I. Tie wire, Ga-16 337.00 kgs 70.00 23,590.00 21.00 7,077.00 30,667.00
Formwork Area 380.00 sq.m. 400.00 152,000.00 120.00 45,600.00 197,600.00
Concrete mix, 3000 psi 29.00 cu.m. 4,600.00 133,400.00 2,000.00 58,000.00 191,400.00
Rebar, 20mm dia, GR-40 main bars 1,567.00 m 75.00 117,525.00 26.25 41,133.75 158,658.75
Rebar, 16mm dia, GR-40 main bars 285.00 m 75.00 21,375.00 26.25 7,481.25 28,856.25
Rebar, 12mm dia, GR-40 side bars 70.00 m 42.19 2,953.13 14.77 1,033.59 3,986.72
Rebar, 10mm dia, GR-40 stirrups 769.00 m 29.30 22,529.30 10.25 7,885.25 30,414.55
G.I. Tie wire, Ga-16 33.00 kgs 70.00 2,310.00 21.00 693.00 3,003.00
Formwork Area 318.00 sq.m. 400.00 127,200.00 120.00 38,160.00 165,360.00
Finishing: 318.00 sq.m. - - -
Screened Sand 8.80 cu.m. 1,000.00 8,800.00 350.00 3,080.00 11,880.00
Portland Cement 1:2 cement-sand ratio 154.00 bags 260.00 40,040.00 91.00 14,014.00 54,054.00
Painting Works 318.00 sq.m. 96.00 30,528.00 96.00 30,528.00 61,056.00
2.0 Steeldeck Slab
Concrete mix, 3000 psi 39.90 cu.m. 4,600.00 183,540.00 2,000.00 79,800.00 263,340.00
Rebar, 10mm dia, GR-40 8,870.00 m 29.30 259,863.28 10.25 90,952.15 350,815.43
G.I. Tie wire, Ga-16 374.00 kgs 70.00 26,180.00 21.00 7,854.00 34,034.00
Portland Cement 1:2 cement-sand ratio 124.00 bags 260.00 32,240.00 91.00 11,284.00 43,524.00
Painting Works 254.90 sq.m. 96.00 24,470.40 96.00 24,470.40 48,940.80
Sag Rods
Tie Rods
ROOF, RIB; 0.5mm Thickness - sq.m. 486.00 - 145.80 - -
Bended Items - m 363.64 - 109.09 - -
C-Purlins, LC-120x40x20x2 130.00 pcs 700.00 91,000.00 405.60 52,728.00 143,728.00
Truss L-2x2x1/4 80.00 pcs 5,300.00 424,000.00 1,590.00 127,200.00 551,200.00
Truss L-2x2x3/16 46.00 pcs 5,300.00 - 1,590.00 - -
Fascia frame 126.90 m 1,000.00 126,900.00 300.00 38,070.00 164,970.00
1.0 RC Staircase
Concrete mix, 3000 psi 13.20 cu.m. 4,600.00 60,720.00 2,000.00 26,400.00 87,120.00
Rebar, 16mm dia, GR-40 main bars 99.70 m 75.00 7,477.50 26.25 2,617.13 10,094.63
Rebar, 10mm dia, GR-40 temperature bars 49.50 m 29.30 1,450.20 10.25 507.57 1,957.76
Rebar, 10mm dia, GR-40 nosing bars 99.00 m 29.30 2,900.39 10.25 1,015.14 3,915.53
G.I. Tie wire, Ga-16 5.20 kgs 70.00 364.00 21.00 109.20 473.20
Formwork Area 11.00 sq.m. 400.00 4,400.00 120.00 1,320.00 5,720.00
Floor Finishing
Portland Cement 1:4 Cement-Sand Ratio 119.00 bags 260.00 30,940.00 91.00 10,829.00 41,769.00
Painting Works 67.50 sq.m. 96.00 6,480.00 96.00 6,480.00 12,960.00
Finishing 809.60
1.0 Ground floor ceiling 855.0 sq.m. 300.00 256,500.00 250.00 213,750.00 470,250.00
HARDFLEX; 4ft x 8ft, 3.5mm thikness 1,232.00 pcs 455.00 560,560.00 136.50 168,168.00 728,728.00
S4S Lumber 2x2; 400x400 spacing 2,727.00 bd.ft. 62.00 169,074.00 18.60 50,722.20 219,796.20
Assorted Nails 28.50 kgs 70.00 1,995.00 21.00 598.50 2,593.50
Painting Works 427.50 sq.m. 96.00 41,040.00 96.00 41,040.00 82,080.00
2.0 2nd floor ceiling
HARDFLEX; 4ft x 8ft, 3.5mm thikness 1,232.00 pcs 455.00 560,560.00 136.50 168,168.00 728,728.00
Rough Lumber 2x2; 400x400 spacing 2,727.00 bd.ft. 62.00 169,074.00 18.60 50,722.20 219,796.20
1.0 Doors
D01: Tanguile Panel Door 2.4x1 16.0 unit 11,208.00 179,328.00 1,681.20 26,899.20 206,227.20
D02: Hollow Core Flush Type Door 2.054x0.9 2.0 unit 1,663.74 3,327.48 249.56 499.12 3,826.60
D03: Louver Type Double Swing Door 2.1x0.7 2.0 unit 1,029.00 2,058.00 154.35 308.70 2,366.70
D04: Hollow Core Flush Type Door Varitaion 2 1.2x0.6 3.0 unit 648.00 1,944.00 97.20 291.60 2,235.60
2.0 Windows - - - -
W01: Jalousie Windows w/ Clear Glass Blades
on Standard Aluminum Casing & fixed Clear 1.2x2.5 18.0 unit 12,000.00 216,000.00 1,200.00 21,600.00 237,600.00
Glass Transom on Top (4 Columns)
W02: Jalousie Windows w/ Clear Glass Blades
on Standard Aluminum Casing & Fixed Clear 1.2x1.4 16.0 unit 3,360.00 53,760.00 336.00 5,376.00 59,136.00
Glass Transom on Top( Columns)
W03: Jalousie Windows w/ Clear Glass Blades 0.635x2.5 2.0 unit 2,381.25 4,762.50 238.13 476.25 5,238.75
on Standard Aluminum Casing
1.0 Landscape - - -
Landscape 1.0 lot 150,000.00 150,000.00 75,000.00 75,000.00 225,000.00
Lavatory Faucet, Angle Valve and Flex. Hose 5.0 pcs 2,500.00 12,500.00 750.00 3,750.00 16,250.00
Bath tub set, with valves and accessories 1.0 set 65,000.00 65,000.00 19,500.00 19,500.00 84,500.00
Shower head set with valves and accessories 5.0 set 4,000.00 20,000.00 1,200.00 6,000.00 26,000.00
Tissue Holder 5.0 pcs 500.00 2,500.00 150.00 750.00 3,250.00
Stainless Steel Soap Holder 5.0 pcs 500.00 2,500.00 150.00 750.00 3,250.00
Towel holder 5.0 pcs 1,200.00 6,000.00 360.00 1,800.00 7,800.00
Floor drain, T&B 5.0 pcs 300.00 1,500.00 90.00 450.00 1,950.00
Kitchen Sink set 2.0 set 4,000.00 8,000.00 1,200.00 2,400.00 10,400.00
Elecric water heater, wall mount type, multipoint 5.0 set 10,000.00 50,000.00 3,000.00 15,000.00 65,000.00
Water pump, booster, easybox 1 pcs 15,000.00 15,000.00 4,500.00 4,500.00 19,500.00
Water heater outlet 6.0 units 280.00 1,680.00 140.00 840.00 2,520.00
1-Gang Switch 16.0 sets 150.00 2,400.00 37.50 600.00 3,000.00
2-Gang Switch 10.0 sets 230.00 2,300.00 57.50 575.00 2,875.00
3-Gang Switch 8.0 sets 330.00 2,640.00 82.50 660.00 3,300.00
3.0 Wires, Cables & Conductors
150 mm2 THHN Copper wire 100.0 mtrs 831.00 83,100.00 207.75 20,775.00 103,875.00
22 mm2 THHN Copper wire 50.0 mtrs 151.00 7,550.00 37.75 1,887.50 9,437.50
50 mm2 THHN Copper wire 10.0 mtrs 347.00 3,470.00 86.75 867.50 4,337.50
16 mm2 THHN Copper wire 5.0 mtrs 98.00 490.00 24.50 122.50 612.50
8.0 mm2 THHN Copper wire 100.0 mtrs 60.00 6,000.00 15.00 1,500.00 7,500.00
5.5mm2 THHN Copper wire 300.0 mtrs 40.00 12,000.00 10.00 3,000.00 15,000.00
3.5mm2 THHN Copper wire 500.0 mtrs 26.00 13,000.00 6.50 3,250.00 16,250.00
3.35mm2 THHN Copper wire
3.0 Conduits, fittings
20mmØ x 3.00m PVC Pipes 50.0 length 70.00 3,500.00 17.50 875.00 4,375.00
25mmØ x 3.00m PVC Pipes 30.0 length 70.00 2,100.00 17.50 525.00 2,625.00
Moldflex uPVC Electrical conduit 20mm 6.0 roll 800.00 4,800.00 200.00 1,200.00 6,000.00
Misc. PVC adoptors and fittings 264.0 pcs 15.00 3,960.00 3.75 990.00 4,950.00
SUMMARY
TOTAL DIRECT COST 11,236,444.26
Prepared by: CONTINGENCIES AND PROFIT(20%) 2,247,288.85
Approved By:
DR. NORDY D. SIASON JR.
Owner
I Pouring of footing G
F=10 H=9 FF=4
7
6 7 R= 7 FF=8
J Back filling and compaction, slab on fill I 7
19
K Electrical, plumbing and water pipe connections I 7
PREDECESSO
TASK DESCRIPTION AMOUNT R START
A Clearing the site START Mon 1/24/22
B Construction of field office A Tue 2/01/22
C Delivery of materials B Tue 2/08/22
D Stalking and batter boards A Tue 2/01/22
E Excavation D Tue 2/08/22
F Cutting and assembling of reinforcements D Tue 2/08/22
G Positioning steel reinforcements E Thu 2/17/22
H Form works for footing-column F Fri 2/18/22
I Pouring of footing G Thu 3/03/22
J Back filling and compaction, slab on fill I Thu 3/10/22
K Electrical, plumbing and water pipe connections G Thu 3/03/22
L Pouring of columns J Thu 3/17/22
M GF CHB laying L Sat 3/26/22
N Beams and slabs forms & reinforcing and various piping installations M Sat 4/09/22
O Pouring of 2F beams and slabs N Tue 4/19/22
P 2F CHB laying, column, roof beam O Mon 4/25/22
Q Roof framing and roofing sheet P Sun 5/08/22
R Construction of stairways and installation of corridor railings P Sun 5/08/22
S Plastering and tile works P Sun 5/08/22
T Plumbing and drainage system Q Tue 5/17/22
U Installation of electrical wiring and fixtures S Sun 5/22/22
V Installation of plumbing fixtures U Sun 5/29/22
W Painting and installation of writing boards S Sun 5/22/22
X Final work and cleaning W Sun 6/05/22
TOTAL COST
END DAYS M T W T F S S M T W T F S S M T W T F S S M T W T F
Mon 1/31/22 8 1 1 1 1 1 1 1 1
Mon 2/07/22 7 1 1 1 1 1 1 1
Mon 2/14/22 7 1 1 1 1 1 1 1
Mon 2/07/22 7 1 1 1 1 1 1 1
Wed 2/16/22 9 1 1 1 1 1 1 1 1 1
Thu 2/17/22 10 1 1 1 1 1 1 1 1 1 1
Wed 3/02/22 14 1 1
Sat 2/26/22 9 1
Wed 3/09/22 7
Wed 3/16/22 7
Wed 3/09/22 7
Fri 3/25/22 9
Fri 4/08/22 14
Mon 4/18/22 10
Mon 4/25/22 7
Sun 5/08/22 14
Mon 5/16/22 9
Sat 5/14/22 7
Sat 5/21/22 14
Fri 5/20/22 4
Sat 5/28/22 7
Thu 6/02/22 5
Sat 6/04/22 14
Tue 6/14/22 10
1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 3 3 3 3 3 3 3 2 2 2 2
1 2 3 4 5 6 7 8 10 12 14 16 18 20 22 25 28 31 34 37 40 43 45 47 49 51
Week 4 Week 5 Week 6 Week 7 Week 8 Week 9
14 Feb 2022 21 Feb 2022 28 Feb 2022 7 Mar 2022 14 Mar 2022 21 Mar 2022
19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1
1 1 1 1 1 1 1
1 1 1 1 1 1 1
1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1
1 1
2 2 2 2 2 2 2 2 1 1 1 1 2 2 2 2 2 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
53 55 57 59 61 63 65 67 68 69 70 71 73 75 77 79 81 83 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99############
Week 10 Week 11 Week 12 Week 13 Week 14 Week 15
28 Mar 2022 4 Apr 2022 11 Apr 2022 18 Apr 2022 25 Apr 2022 2 May 2022
28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 1 1 1 1 1 1 1 1
###############################################################################################################
Week 15 Week 16 Week 17 Week 18 Week 19 Week 20
2 May 2022 9 May 2022 16 May 2022 23 May 2022 30 May 2022 6 Jun 2022
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
1 1 1 1 1
1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1
1 1 1 1 1 1 1
1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1
1 1 1 1 4 3 3 3 3 3 3 2 2 2 2 2 2 1 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 1 1 1
###############################################################################################################
Week 20 Week 21
6 Jun 2022 13 Jun 2022
10 11 12 13 14 15 16 17 18 19
F S S M T W T F S S
1 1 1 1 1
1 1 1 1 1
###############