This document is a checklist for conducting a pile maintained load test. It outlines the standard procedures that must be followed which include: 1) conducting a desk top study and gaining approval for the test methodology; 2) properly preparing the site and installing necessary equipment; 3) performing an initial cycle test by incrementally increasing and decreasing the load; and 4) performing a secondary full test cycle by further increasing the load and taking settlement readings over a 24 hour period before removing the load. The checklist must be completed and certified by both the site supervisor and oversight inspector.
This document is a checklist for conducting a pile maintained load test. It outlines the standard procedures that must be followed which include: 1) conducting a desk top study and gaining approval for the test methodology; 2) properly preparing the site and installing necessary equipment; 3) performing an initial cycle test by incrementally increasing and decreasing the load; and 4) performing a secondary full test cycle by further increasing the load and taking settlement readings over a 24 hour period before removing the load. The checklist must be completed and certified by both the site supervisor and oversight inspector.
This document is a checklist for conducting a pile maintained load test. It outlines the standard procedures that must be followed which include: 1) conducting a desk top study and gaining approval for the test methodology; 2) properly preparing the site and installing necessary equipment; 3) performing an initial cycle test by incrementally increasing and decreasing the load; and 4) performing a secondary full test cycle by further increasing the load and taking settlement readings over a 24 hour period before removing the load. The checklist must be completed and certified by both the site supervisor and oversight inspector.
A DESK TOP STUDY 1 Methodology by jacking method (including the support system) Y N NA submitted to and approved by OIC 2 Submitted catalogue & calibration certificates of the jack and Y N NA settlement gauges to OIC's approval. (Jack measured to ±2% accuracy, Gauge measured to ±0.25mm accuracy) 3 Checked the counter weight (kentledge) to be a minimum of 2.2 Y N NA times the pile's working capacity 4 OIC confirmed the test pile position Y N NA B SITE PREPARATION 1 Support System is properly installed on firm ground Y N NA 2 Settlement Gauges installed at a datum that will not be affected Y N NA by any movement of the ground due to any cause 3 Independent checks on the level of the datum by an accurate Y N NA levelling instrument conducted by surveyor C FIRST CYCLE TEST 1 The gauges are reset by applying a load of 10 tons, removing of Y N NA load and setting recording instruments to zero 2 Increased jacking load to the working load with a min. 4 equal Y N NA increments with 1 hour holding time for each or to OIC's direction 3 Held the full working load for 2 hours or to OIC's direction Y N NA 4 Reduced the load to zero with a min. of 4 equal decrements with Y N NA a min. of 30 minutes holding time each tor o OIC's direction 5 Held zero load for 2 hours or to OIC's direction for full recovery Y N NA before proceeding with 2nd cycle test D SECOND CYCLE TEST 1 Increased jacking load to FULL TEST LOAD with a min. of 8 equal Y N NA increments with 1 hour holding time each or to OIC's direction 2 Held the FULL TEST LOAD for 24 hours or to OIC's direction Y N NA 3 Reduced the load to zero with a min. of 8 equal decrements with Y N NA min. 30 minutes holding time each or to OIC's direction 4 Held zero load for 2 hours or to OIC's direction for full recovery Y N NA before removing the jack E RECORDING 1 At constant load, recorded time and settlement/recovery Y N NA immediately on reaching the load and at 15 minutes intervals for 1st hour, at 30 minute intervals for the next 3 hours and then at hourly intervals 2 Submitted Test Record to OIC within 24 hours, use Form 404 Y N NA 3 Submitted Test Report with settlement/recovery plotted vertically Y N NA against a base line of load 4 OIC certified the acceptance of the test result Y N NA