Professional Documents
Culture Documents
FOR
FOR
M/S ALSTOM SYSTEM INDIA PVT. LTD.
BY
ESSCON ENGINEERING SERVICES PVT. LTD.
343, L.I.G FLAT, PKT-B, HASTSAL,
OPP. CENTREL SCHOOL VIKAS PURI
NEW DELHI – 110059
TELE:- 011-25377348, 9810899977
E-MAIL: eesindia@yahoo.co.in
essconengineering@gmail.com
(AN ISO -9001:2008 CERTIFIED COMPANY)
ACKNOWLEDGEMENT
Test Results ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
3.0 15
Recommendation and conclusion ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ 16
4.0
‐
ANNEXURE ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ 17- 28
Esscon Engineering Services Pvt Ltd.
1.0 INTRODUCTION
The report presented herein deals with Pile load Test for PROTOTYPE
PILE LOAD TEST AT TUNDLA DETOUR . The work of Pile load
The scope of this document is to test and validate the estimated design
capacity of the cylindrical foundation ,The following are the scope of
work for conducting various types of load test including Lateral &
Vertical load test. According to is code of practice. IS: 2911(Part IV)
1.2 REFERENCES
IS CODE
IS 2911(part 4) :2013
DESIGN AND CONSTRUCTION OF PILE FOUNDATION-
CODE OF PRACTICE (Part 4 load Test on Pile)
Page 1
Esscon Engineering Services Pvt Ltd.
Load Test shall be performed when concrete has reached its required
strength i.e. 28 days strength. The axial compressive loads test
should be done as per IS code 2911 part IV (latest revision).
Page 2
Esscon Engineering Services Pvt Ltd.
Page 3
Esscon Engineering Services Pvt Ltd.
Load Test shall be performed when concrete has reached its required
strength i.e. 28 days strength. The lateral loads test should be done as
per IS2911 Part IV 2013 . The test may be carried out by introducing a
hydraulic jack with gauge between two piles or reaction may be
suitably obtained. The full load imposed by the jack shall be taken as
the lateral resistance of the pile. The loading shall be applied in
increments of about 20 percent of estimated safe load.
Page 4
Esscon Engineering Services Pvt Ltd.
Page 5
2.3 GRAPH & TABLE
Page 6
PILE TESTING DETAILS
PILE ID P-1
PILE TYPE BORED CAST IN SITU
PILE DIAMETER 900 mm
LENGTH OF PILE 3.020m
DATE OF PILE TESTING 9‐Mar‐2017
Page 7
Table‐1 Vertical LOAD TEST DATA SHEET
REBOUNDING
40 185.9 183.04 190 40.9 5.62 5.64 5.75 5.68 5.67
38.4 178.5 175.71 180 38.7 5.61 5.62 5.74 5.66 5.66
35.2 163.6 161.07 170 36.6 5.60 5.62 5.74 5.65 5.65
32 148.8 146.43 150 32.3 5.59 5.61 5.72 5.65 5.64
28.8 133.9 131.78 140 30.1 5.59 5.60 5.70 5.63 5.63
25.6 119.0 117.14 120 25.8 5.55 5.60 5.68 5.60 5.61
22.4 104.1 102.50 110 23.7 5.55 5.60 5.66 5.59 5.60
19.2 89.3 87.86 90 19.4 5.53 5.58 5.64 5.57 5.58
16 74.4 73.21 80 17.2 5.50 5.56 5.60 5.55 5.55
12.8 59.5 58.57 60 12.9 5.47 5.51 5.60 5.53 5.53
9.6 44.6 43.93 50 10.8 5.45 5.48 5.57 5.53 5.51
6.4 29.8 29.29 30 6.5 5.42 5.43 5.55 5.50 5.48
3.2 14.9 14.64 20 4.3 5.37 5.41 5.47 5.40 5.41
0 0 0.00 0 0.0 5.18 5.26 5.20 5.31 5.24
Page 8
FIG NO-1:
2
mm
3
Settlement -m
Page 9
Page 10
Page 11
PILE TESTING DETAILS
PILE ID P-2
PILE TYPE BORED CAST IN SITU
PILE DIAMETER 900 mm
LENGTH OF PILE 3.020 m
DATE OF PILE TESTING 05‐April‐2017
Page 12
Table‐2 LATERAL LOAD TEST DATA SHEET
Page 13
FIG NO-2:
Applied Load in Kg
0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000
0
ection-mm
1
Defle
Page 14
Esscon Engineering Services Pvt Ltd.
PERMISSIBLE
SAFE LOAD TEST LOAD SETTLEMENT
PILE ID SETTLEMENT
(TONNE) (TONNE) (mm)
(mm)
3.2 The lateral load test on pile were conducted on 1 piles and the results
as obtained are given below.
PERMISSIBLE
VERTICAL
SAFE LOAD TEST LOAD VERTICAL
PILE ID DISPLACEMENT
(TONNE) (TONNE) DISPLACEMENT
(mm)
(mm)
Page 15
Esscon Engineering Services Pvt Ltd.
PERMISSIBLE
SAFE LOAD TEST LOAD SETTLEMENT
PILE ID SETTLEMENT
(TONNE) (TONNE) (mm)
(mm)
4.2 The lateral deflection were calculated on the basis of design lateral
load test on pile, The results are given below:-
PERMISSIBLE
SAFE LOAD TEST LOAD DEFLECTION
PILE ID DEFLECTION
(TONNE) (TONNE) (mm)
(mm)
P‐2 1.60 4.0 1.57 12.0
4.3 Reviewing the above pile load test results, As the gross Settlement and
deflection are observed within the permissible limits, hence design &
construction are recommended to adopt accordingly.
Page 16
ANNEXURE
Page 17
ANNEXURE-A
Page 18
Page 19
Page 20
Page 21
Page 22
Page 23
Page 24
Page 25
Page 26
Page 27