COMPLETION REVISED Manpower Mateial Mateial CONTRACTOR
S.No. STRUCTURE ACTION BY STATUS Manpower REMARKS
DATE DATE Available Avialble Required NAME
Required
Cable trench seepage
1 arresting and cleaning 11/25/2023 Mr.Bubendar Cleaning work in progress 10
work at Unit -3
RR Wall:
Sushila
Quarters 4th Priorty - bharadwaj,MK
7/30/2023 10/30/2023 Sup-24,25: Internal and external plastering work is in progress. 48 nil
( Sup-24 ,25) Const, pushpa
jaiswal
Guest House - 46 11/30/2023 First floor Block work in progress 16 nil SB Construction
Mr.Joel
Deputy Manager
30-02-2024 Plinth beam completed. Ground floor column in progress 15 nil Karim
Quarters - 44
Deputy Manager
30-02-2024 Backfilling completed. Brickwork started for plinth beam. 8 Karim
Quarters - 40
2
SUPERVISOR Tejas
3/5/2024 Footing completed. Pedestal column work in progress 13
QUARTERS - 21 construction
COMPLETION
STRUCTURE NO'S START DATE
DATE
DEPUTY MANAGER 1 10/1/2023 2/28/2024
SUPERVISOR
Balance Quarters -Schedule
QUARTERS - 17 No's
Total 314
COAL SHED - RR BALANCE WORK SCHEDULE
S.No Description of work Duration Start Date Finish Date Remarks
Page 3 of 100
CIVIL DEPARTMENT - INCHARGE OF WORKS
7 Roads at Residential Quartes Dhaneshwar Prasad Yadav 7566801100 Brajesh Kumar Pandey
(9575303376)
8 Inplant Road
Sudipta Kumar Banerjee 7770997728
9 Storm water Drain
Marirajan
10 Coal Shed Pradyumna Kumar Prusty 8435000368
(9698126123)
11 Coal Shed Tail Pully Room
P K Sinha
12 Stacker Reclaimer Niranjan Kumar 7008258229
(9406035816)
13 Coal Pile Run off Pit
8171928012 Marirajan
14 TG Pending works Kishore Kumar Bahuguna
(9698126123)
P K Sinha
15 Wagon Tippler Mantu Gorai
(9406035816)
185
152
Sunday
221
152
195
150
139
201
Sunday
153
180
213
164
154
226
Sunday
193
177
Sunday
2853 0
1203.86
ASH POND - 03 (16 Acre) Site Engineer : Ajay Kumar
Constrains Ash to be evacuated
Action by Mr.Kalaiselvan/Mr.Irfan
Qty
S.No Description of work Unit
Estimated Qty Completed Balance
ASH POND - 03
1 HDPE Laying work Sqm 7,500.00 7,500.00
2 Reinforcement Steel MT 15.75 15.75
3 Shuttering Bgl Sqm 450.00 450.00
4 RCC Tie Beam - M20 Cum 67.50 67.50
5 Brick work 115mm thk Sqm 7,500.00 7,500.00
Overall
Schedule
Status: Pond is being evacuated of ash, expected to be complete by 16-06-2022 Work to resume thereafter
Updated Schedule
S.No Description of work Unit Qty Duration Start Date End Date Remarks
ASH POND - 03
1 HDPE Laying work Sqm 7500
2 Reinforcement Steel MT 15.75 Ash evacuation is in
3 Shuttering Bgl Sqm 900 progress
4 RCC Tie Beam - M20 Cum 67.5
5 Brick work 115mm thk Sqm 7500
ASH POND - 04 Site Engineer : Rajesh Kumar
Constrains Ash to be evacuated
Action by Mr.Kalaiselvan/Mr.Irfan
Qty
S.No Description of work Unit Estimated
Completed Balance
Qty % Of Completion % of Balance
ASH POND - 04
1 HDPE Film for Ash Pond Sqm 38,298.99 - 38,298.99 0% 100%
2 Steel reinforcement MT 8.00 8.00 0% 100%
3 Shuttering - Bgl Sqm 2,919.60 2,919.60 0% 100%
4 RCC M20 Cum 657.11 657.11 0% 100%
5 Brickwork 115 mm thk Sqm 11,900.00 11,900.00 0% 100%
Overall 0% 100%
SCHEDULE
Status: Pond is using for ash deposit, expected to be complete byWork to resume thereafter
S.No Description of work Unit Balance Duration Start Date Finish Date Remarks
ASH POND - 04 0 12/30/1899 12/30/1899
185
152
Sunday
221
152
195
150
139
201
Sunday
153
180
Sunday
Sunday
1726 0
728.48
ASH POND - 03 (16 Acre) Site Engineer : Ajay Kumar
Constrains Ash to be evacuated
Action by Mr.Kalaiselvan/Mr.Irfan
Qty
S.No Description of work Unit
Estimated Qty Completed Balance
ASH POND - 03
1 HDPE Laying work Sqm 7,500.00 7,500.00
2 Reinforcement Steel MT 15.75 15.75
3 Shuttering Bgl Sqm 450.00 450.00
4 RCC Tie Beam - M20 Cum 67.50 67.50
5 Brick work 115mm thk Sqm 7,500.00 7,500.00
Overall
Schedule
Status: Pond is being evacuated of ash,
Updated Schedule
S.No Description of work Unit Qty Duration Start Date End Date Remarks
ASH POND - 03
1 HDPE Laying work Sqm 7500
2 Reinforcement Steel MT 15.75 Ash evacuation is in
3 Shuttering Bgl Sqm 900 progress
4 RCC Tie Beam - M20 Cum 67.5
5 Brick work 115mm thk Sqm 7500
RESERVOIR PUMP HOUSE SCHEDULE
Description Unit Qty Duration Start Finish
Reservoir Pump House 107 days 12/5/2022 3/21/2023
Below Ground Level 53 days 12/5/2022 1/26/2023
Column - 9 Nos of 11.3 mtr depth (380 X 750) 16 days 12/21/2022 1/5/2023
Column - 4 Nos of 9.5 mtr depth (380 X 750) 12 days 12/31/2022 1/11/2023
Lift - 01 - 2.44 mtr Depth 3 days 12/31/2022 1/2/2023
Reinforcement work MT 0.405 1 day 12/31/2022 12/31/2022
Shuttering work - BGL Sqm 1.623 1 day 1/1/2023 1/1/2023
RCC M30 Cum 2.723 1 day 1/1/2023 1/1/2023
Deshuttering Sqm 1.623 1 day 1/2/2023 1/2/2023
Lift - 02 - 2.34 mtr Depth 3 days 1/3/2023 1/5/2023
Reinforcement work MT 0.388 1 day 1/3/2023 1/3/2023
Shuttering work - BGL Sqm 1.556 1 day 1/4/2023 1/4/2023
RCC M30 Cum 2.611 1 day 1/4/2023 1/4/2023
Deshuttering Sqm 1.556 1 day 1/5/2023 1/5/2023
Lift - 03 - 2.34 mtr Depth 3 days 1/6/2023 1/8/2023
Column - 4 Nos of 6.3 mtr depth (380 X 750) 9 days 1/7/2023 1/15/2023
Lift - 01 - 2.44 mtr Depth 3 days 1/7/2023 1/9/2023
Reinforcement work MT 0.434 1 day 1/7/2023 1/7/2023
Shuttering work - BGL Sqm 22.058 1 day 1/8/2023 1/8/2023
RCC M30 Cum 2.782 1 day 1/8/2023 1/8/2023
Deshuttering Sqm 22.058 1 day 1/9/2023 1/9/2023
Lift - 02 - 2.34 mtr Depth 3 days 1/10/2023 1/12/2023
Reinforcement work MT 0.417 1 day 1/10/2023 1/10/2023
Shuttering work - BGL Sqm 21.154 1 day 1/11/2023 1/11/2023
RCC M30 Cum 2.668 1 day 1/11/2023 1/11/2023
Deshuttering Sqm 21.154 1 day 1/12/2023 1/12/2023
Lift - 03 - 1.52 mtr Depth 3 days 1/13/2023 1/15/2023
Reinforcement work MT 0.271 1 day 1/13/2023 1/13/2023
Shuttering work - BGL Sqm 13.741 1 day 1/14/2023 1/14/2023
RCC M30 Cum 1.733 1 day 1/14/2023 1/14/2023
Deshuttering Sqm 13.741 1 day 1/15/2023 1/15/2023
Column - 4 Nos of 3.3 mtr depth (380 X 750) 6 days 1/14/2023 1/19/2023
Lift - 01 - 2.44 mtr Depth 3 days 1/14/2023 1/16/2023
Reinforcement work MT 0.481 1 day 1/14/2023 1/14/2023
Shuttering work - BGL Sqm 21.274 1 day 1/15/2023 1/15/2023
RCC M30 Cum 2.782 1 day 1/15/2023 1/15/2023
Deshuttering Sqm 21.274 1 day 1/16/2023 1/16/2023
Lift - 02 - 0.86 mtr Depth 3 days 1/17/2023 1/19/2023
Reinforcement work MT 0.169 1 day 1/17/2023 1/17/2023
Available
Manpower Unit Required Qty
Qty
Page 23 of 100
Description Unit Qty Duration Start Finish
Column - 9 Nos of 11.3 mtr depth (380 X 750) 16 days 1/14/2023 1/29/2023
Lift - 01 - 2.44 mtr Depth 4 days 1/14/2023 1/17/2023
Reinforcement work MT 0.847 1 day 1/14/2023 1/14/2023
Shuttering work - BGL Sqm 38.479 1 day 1/15/2023 1/15/2023
RCC M30 Cum 3.174 1 day 1/16/2023 1/16/2023
Deshuttering Sqm 38.479 1 day 1/17/2023 1/17/2023
Lift - 02 - 2.34 mtr Depth 4 days 1/17/2023 1/20/2023
Reinforcement work MT 0.812 1 day 1/17/2023 1/17/2023
Shuttering work - BGL Sqm 36.902 1 day 1/18/2023 1/18/2023
RCC M30 Cum 3.044 1 day 1/19/2023 1/19/2023
Page 24 of 100
Description Unit Qty Duration Start Finish
Column - 4 Nos of 9.5 mtr depth (380 X 750) 12 days 1/24/2023 2/4/2023
Lift - 01 - 2.44 mtr Depth 3 days 1/24/2023 1/26/2023
Reinforcement work MT 0.405 1 day 1/24/2023 1/24/2023
Shuttering work - BGL Sqm 1.623 1 day 1/25/2023 1/25/2023
RCC M30 Cum 2.723 1 day 1/25/2023 1/25/2023
Deshuttering Sqm 1.623 1 day 1/26/2023 1/26/2023
Lift - 02 - 2.34 mtr Depth 3 days 1/27/2023 1/29/2023
Reinforcement work MT 0.388 1 day 1/27/2023 1/27/2023
Shuttering work - BGL Sqm 1.556 1 day 1/28/2023 1/28/2023
RCC M30 Cum 2.611 1 day 1/28/2023 1/28/2023
Deshuttering Sqm 1.556 1 day 1/29/2023 1/29/2023
Lift - 03 - 2.34 mtr Depth 3 days 1/30/2023 2/1/2023
Reinforcement work MT 0.388 1 day 1/30/2023 1/30/2023
Shuttering work - BGL Sqm 1.556 1 day 1/31/2023 1/31/2023
RCC M30 Cum 2.611 1 day 1/31/2023 1/31/2023
Deshuttering Sqm 1.556 1 day 2/1/2023 2/1/2023
Lift - 04 - 2.34 mtr Depth 3 days 2/2/2023 2/4/2023
Reinforcement work MT 0.388 1 day 2/2/2023 2/2/2023
Shuttering work - BGL Sqm 1.556 1 day 2/3/2023 2/3/2023
RCC M30 Cum 2.611 1 day 2/3/2023 2/3/2023
Deshuttering Sqm 1.556 1 day 2/4/2023 2/4/2023
Column - 4 Nos of 6.3 mtr depth (380 X 750) 9 days 1/31/2023 2/8/2023
Lift - 01 - 2.44 mtr Depth 3 days 1/31/2023 2/2/2023
Reinforcement work MT 0.434 1 day 1/31/2023 1/31/2023
Shuttering work - BGL Sqm 22.058 1 day 2/1/2023 2/1/2023
RCC M30 Cum 2.782 1 day 2/1/2023 2/1/2023
Deshuttering Sqm 22.058 1 day 2/2/2023 2/2/2023
Lift - 02 - 2.34 mtr Depth 3 days 2/3/2023 2/5/2023
Reinforcement work MT 0.417 1 day 2/3/2023 2/3/2023
Shuttering work - BGL Sqm 21.154 1 day 2/4/2023 2/4/2023
RCC M30 Cum 2.668 1 day 2/4/2023 2/4/2023
Deshuttering Sqm 21.154 1 day 2/5/2023 2/5/2023
Page 25 of 100
Description Unit Qty Duration Start Finish
Column - 4 Nos of 3.3 mtr depth (380 X 750) 6 days 2/7/2023 2/12/2023
Lift - 01 - 2.44 mtr Depth 3 days 2/7/2023 2/9/2023
Reinforcement work MT 0.481 1 day 2/7/2023 2/7/2023
Shuttering work - BGL Sqm 21.274 1 day 2/8/2023 2/8/2023
RCC M30 Cum 2.782 1 day 2/8/2023 2/8/2023
Deshuttering Sqm 21.274 1 day 2/9/2023 2/9/2023
Lift - 02 - 0.86 mtr Depth 3 days 2/10/2023 2/12/2023
Reinforcement work MT 0.169 1 day 2/10/2023 2/10/2023
Shuttering work - BGL Sqm 7.498 1 day 2/11/2023 2/11/2023
RCC M30 Cum 0.98 1 day 2/11/2023 2/11/2023
Deshuttering Sqm 7.498 1 day 2/12/2023 2/12/2023
Page 26 of 100
Description Unit Qty Duration Start Finish
Supervisor Nos 1 0
Page 27 of 100
Description Unit Qty Duration Start Finish
Carpenter Nos 7 3
Fitter Nos 7 3
Helper Nos 15 10
Total Manpower Nos 30 16
Page 28 of 100
Work details Qty No of days Time study Man power
Pump House Wall & Roof (Only pump house 55 55Days required to complete pump
portion) house wall& Roof
Total wall length - 110Rmt, Height - 12M
One lift ht - 2.4m
5 Lift
1st lift qty
5 1F+1 Helper done - 20F+20H done - 5MT/Day. So 5 day
Reinforcement steel 25MT 0.25MT / Day 20F+20H required to complete this job.
Page 32 of 100
SL NO DESCRIPTION LEVEL LEVEL LEVEL GRID 217 8/4/2022 3/9/2023
B' B' IN 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Column Balance Qty in Cum Duration Start Date End Date
BEAM 259.200 259.500 (+7.7TO +8.00) 0.300 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 54.000 36 2/2/2023 3/9/2023
RR Wall 258.300 259.200 0.900 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.116 6.116 6.116 6.116 6.116 6.116 6.116 6.116 6.116 6.116 6.116 4.010 157.991 66 12/9/2022 2/12/2023
RR Wall 257.400 258.300 0.900 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.116 6.116 6.116 6.116 6.116 6.116 6.116 6.116 6.116 6.116 6.116 4.010 157.991 61 11/24/2022 1/23/2023
RR Wall 256.500 257.400 0.900 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.116 6.116 6.116 6.116 6.116 6.116 6.116 6.116 6.116 6.116 6.116 4.010 157.991 56 11/9/2022 1/3/2023
BEAM 256.200 256.500 (+4.7TO +5.00) 0.300 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 54.000 21 10/25/2022 11/14/2022
RR Wall 255.300 256.200 0.900 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.116 4.010 96.836 39 9/25/2022 11/2/2022
RR Wall 254.400 255.300 0.900 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 4.010 90.720 39 9/10/2022 10/18/2022
RR Wall 253.500 254.400 0.900 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 6.480 4.010 90.720 39 8/26/2022 10/3/2022
BEAM 253.200 253.500 (+1.7TO +2.00) 0.300 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 2.160 30.240 41 8/11/2022 9/20/2022 RR wall work is stopped due to
RR Wall 252.350 253.200 0.850 6.120 6.120 6.120 6.120 6.120 6.120 6.120 6.120 6.120 6.120 6.120 6.120 6.120 79.560 31 8/4/2022 9/3/2022 coal shifting vehicle movement
RR Wall 251.500 252.350 0.850 -
RR Wall 250.500 251.500 1.000 -
BEAM 250.200 250.500 (-.7 TO -1.00) 0.300 -
RR Wall 249.350 250.200 0.850 -
RR Wall 248.600 249.350 0.750 -
RR Wall 247.700 248.600 0.900 -
P.C.C 247.600 247.700 (-3.0 TO -2.9) 0.100 -
EXVT 247.600 247.600 0
Total Qty Total Qty 24.057 831.807
Total Nos of RR Stone Total Nos of RR Stone 66,545.00
Grand Total Nos of RR Stone Grand Total Nos of RR Stone 137,034.00
Page 33 of 100
D D IN 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Column Balance Qty in Cum Duration Start Date End Date
BEAM 259.200 259.500 (+7.7TO +8.00) 0.3 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 62.100 30 2/24/2023 3/25/2023
RR Wall 258.300 259.200 0.9 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.088 7.088 7.088 7.088 7.088 7.088 7.088 7.088 7.088 7.088 7.088 4.010 182.291 55 1/24/2023 3/19/2023
RR Wall 257.400 258.300 0.9 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.088 7.088 7.088 7.088 7.088 7.088 7.088 7.088 7.088 7.088 7.088 4.010 182.291 61 1/4/2023 3/5/2023
RR Wall 256.500 257.400 0.9 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.088 7.088 7.088 7.088 7.088 7.088 7.088 7.088 7.088 7.088 7.088 4.010 182.291 56 12/15/2022 2/8/2023
BEAM 256.200 256.500 (+4.7TO +5.00) 0.3 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 2.484 62.100 27 11/25/2022 12/21/2022
RR Wall 255.300 256.200 0.9 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 7.452 4.010 104.328 47 11/10/2022 12/26/2022
RR Wall 254.400 255.300 0.9 7.452 7.452 7.452 7.452 7.452 7.452 7.452 4.010 52.164 46 10/21/2022 12/5/2022
RR Wall 253.500 254.400 0.9 7.452 7.452 7.452 7.452 7.452 7.452 7.452 4.010 52.164 45 10/1/2022 11/14/2022
BEAM 253.200 253.500 (+1.7TO +2.00) 0.3 2.484 2.484 2.484 2.484 2.484 12.420 25 9/11/2022 10/5/2022
RR Wall 252.350 253.200 0.85 7.038 2.754 7.038 43 8/22/2022 10/3/2022
RR Wall 251.500 252.350 0.85 7.038 2.754 7.038 42 8/13/2022 9/23/2022
RR Wall 250.500 251.500 1 8.280 3.240 8.280 46 8/6/2022 9/20/2022
P.BEAM 250.200 250.500 (-.7 TO -1.00) 0.3 2.484 2.484 23 8/1/2022 8/23/2022
RR Wall 249.350 250.200 0.85 -
RR Wall 248.600 249.350 0.75 -
RR Wall 247.700 248.600 0.9 -
P.C.C 247.600 247.700 (-3.0 TO -2.9) 0.1 -
EXVT 247.600 247.600 0
Total RR Qty Total RR Qty 777.884
Total Nos of RR Stone Total Nos of RR Stone 62,231.00
RR Stones - 80
Nos/Cum (230mm x
6 230mm x 200mm) Nos 586,005.00 17,500.00 568,505.00
7 JCB Nos 1.00
Excavator 1.00
Hywa 2.00
Water Tanker 1.00
Page 34 of 100
Structure : Coal shed PROCESS SHEET
Work : RR wall weekly work Sheet
Working Details for (GRID A 16 TO 20 ) (B16 TO 25)( C16 TO 25) (D 14 TO 25)
BACK FILLING
RR WORK STEEL IN SHUTTERING RCC IN BOTTOM
WORK DETAILS IN CUM KG IN SQM CUM
WITH WATER PLUM CC PCC
LEVEL
TOP LEVEL HEIGHT REMARKS
S.No Date Mason Carpenter Fitter Helper COMPACTION
NOS L B H Qty Qty Qty Qty Qty Qty
1 12/1/2022 50 5 1 120 1 150 0.45 0.9 61 0.20 25.29 2 44 22 253.500 256.150 2.65
2 12/2/2022 51 5 1 120 1 200 0.45 0.75 68 0.25 26.10 4 44 0 253.500 256.150 2.65 staging=(64cum) with shifting
3 12/3/2022 50 5 1 120 1 200 0.45 0.75 68 0.23 12.96 2 44 33 staging=(68cum) with shifting
4 12/4/2022 0 5 1 120 1 0 0.45 0.9 0 - 0 44 0
5 12/5/2022 50 5 1 120 1 145 0.45 0.9 59 - 19.44 2 44 22 253.500 254.950 1.45 staging=(96cum) with shifting
6 12/6/2022 50 5 1 120 1 130 0.45 0.9 53 0.11 0.00 4 44 0 253.500 256.150 2.65 staging=(64cum) with shifting
7 12/7/2022 51 5 1 120 1 145 0.45 0.9 59 0.15 48.61 2 44 33 253.500 256.150 2.65
8 12/8/2022 50 5 1 120 1 155 0.45 0.9 63 0.19 4 44 253.500 256.150 2.65
9 12/9/2022 53 5 1 120 1 125 0.45 0.9 51 - 2 44 22 253.500 254.950 1.45
10 12/10/2022 50 5 1 120 1 175 0.45 0.75 59 0.27 4 44 253.500 256.150 2.65 staging=(96cum) with shifting
11 12/11/2022 0 5 1 120 1 0 0.45 0.9 0 - 44
12 12/12/2022 50 5 1 120 1 130 0.45 0.9 53 0.76 2 44 33 253.500 254.950 1.45
13 12/13/2022 50 5 1 120 1 165 0.45 0.75 56 0.76 4 44 253.500 256.150 2.65 staging=(96cum) with shifting
14 12/14/2022 52 5 1 120 1 125 0.45 0.9 51 0.76 2 44 22 253.500 254.950 1.45
15 12/15/2022 50 5 1 120 1 130 0.45 0.9 53 0.76 4 44 253.500 256.150 2.65 staging=(96cum) with shifting
657 1800 750 4.44 132.40 17 655 190 0 12.05 APPROX LENGTH (100 TO 120 RMT)
work done of 2 week 551 6.53 391.24 70 1023 73 6
balance qty for 1 week -199 2 259 53 368 -117 6
ABSTARACT
# Mason utilization @ 51/ day
# Helper utilization @ 120/ day ( i/c @ 3 helper / Mason) due to height (+2 mtr to +5mtr)
# Total man power proposed to be engaged @ 170 / day
# Output RR Work @ 375 cum / Week
# Output RR Work @ 58 cum / day
# Output mason @ 1.1 cum / day
# Output shuttering @ 10 Sqm / day ( mason gang can do the shuttering )
# Output Steel @ 0.35 Mt / day
# Output concrete @ 15 Cum / day
# Output back filling @ 44 Cum / day ( Ash and soil filling)
Coal Transporation Road
Completed Qty
BOQ Qty (Rmt) 1232 (Rmt) 810 Balance Qty (Rmt) 422
Qty
S.No Description of work Unit Remarks
Estimated Qty Completed Balance
S.No Description of work Unit Qty Duration (Days) Start Date Finish Date Remarks
Work considering for 700 Rmt 27 12/8/2022 1/4/2023
1 GSB Cum 1,750.00 18 12/8/2022 12/26/2022
2 WMM Cum 1,400.00 18 12/9/2022 12/27/2022 Completed
3 CC Cum 1,575.00 27 12/8/2022 1/4/2023
4 Hard Shoulder Cum 630.00 8 1/4/2023 1/12/2023
Road from New parking yard to New weigh Bridge-532 Rmt (Part-2)
S.No Description of work Unit Qty Duration (Days) Start Date Finish Date Remarks
Work considering for 532 Rmt 38 1/6/2023 2/13/2023
1 Embankment Formation Cum 14,517.00 21 1/6/2023 1/27/2023
2 Subgrade (300mm tk) Cum 2,394.00 7 1/21/2023 1/28/2023 Embankment
formation under
3 GSB Cum 1,330.00 8 1/28/2023 2/5/2023 progress (5150 Cum
4 WMM Cum 1,064.00 7 2/2/2023 2/9/2023 completed)
5 CC M35 Cum 1,197.00 10 2/3/2023 2/13/2023
6 Hard Shoulder Cum 478.80 8 2/10/2023 2/18/2023
Page 36 of 100
Inplant Road
Budget Approval (Rmt) 2938 Completed (Rmt) 2758 Balance (Rmt) 180
Estimated Completed
S.No Description Unit Balance Qty Duration (Days) Start Date Finish Date Remarks
Qty Qty
INPLANT ROAD WORK - 2938.185 RMT 97 9/26/2022 1/18/2023
Road No. 97 (Cooling Tower
Road upto Fire & Safety Office) -
1 11 days 10/15/2022 10/26/2022 Completed
5.0 Mtr Width of length 148.147
Rmt
Carting away of surplus earth Cum 425.45 425.450 0.000 3 days 12/10/2022 12/13/2022
Hard Shoulder - Murram Laying Cum 180.341 180.341 7 days 1/7/2023 1/14/2023
Hard Shoulder - Murram Laying Cum 125.455 125.455 - 6 days 12/26/2022 12/31/2022
Carting away of surplus earth Cum 749.566 749.566 0.000 5 days 11/19/2022 11/25/2022
GSB - Ready Mix Cum 249.855 249.855 2 days 11/26/2022 11/27/2022
WMM - Ready Mix Cum 199.884 199.884 2 days 11/28/2022 11/29/2022
Shuttering Sqm 174.042 174.042 2 days 31-11-2022 12/1/2022
Dowel Bars MT 0.806 0.806 2 days 31-11-2022 12/1/2022
Joint Sheet Rmt 209.713 209.713 2 days 31-11-2022 12/1/2022
CC Road - M35 Cum 190.799 190.799 2 days 31-11-2022 12/1/2022
Groove Cutting Rmt 209.713 209.713 3 days 12/2/2022 12/4/2022
Hard Shoulder - Murram Laying Cum 109.028 109.028 5 days 12/2/2022 12/7/2022
Qty
S.No Description of work Unit Estimated
Completed Balance
Qty Remarks
TG BALANCE WORK
1 IPS Flooring - 6.3 Mtr sqm 1,355.10 1,355.10 -
2 Waterproofing - 18.9 Mtr Floor sqm 1,205.31 1,205.31 -
Cleaning sqm 1,205.31 1,205.31 -
1st coat waterproofing sqm 1,205.31 1,205.31 -
2nd coat waterproofing sqm 1,205.31 1,205.31 -
Final coat waterproofing sqm 1,205.31 1,205.31 -
7 screed concrete - 18.9 Mtr Floor sqm 1,205.31 1,205.31 -
8 Waterproofing - 25.2 Mtr Roof
Cleaning sqm 1050.55 1,050.55 -
1st coat waterproofing sqm 1050.55 1,050.55 -
2nd coat waterproofing sqm 1050.55 1,050.55 -
Final coat waterproofing sqm 1050.55 1,050.55 -
13 screed concrete - 25.2 Mtr Roof sqm 1050.55 1,050.55 -
14 External Plastering sqm 4,218.81 3,848.02 370.79 TG-03 & TG-04
15 Internal Plastering sqm 1,039.57 1,039.57 -
SCHEDULE
S.No Description of work Unit Balance Duration Start Date Finish Date Remarks
Mason-02, Helper - 08
01. Staging - (10 x 17 mtr) - 02 Days
1 External Plastering 10 11/16/2022 11/26/2022 02. Plastering - 30 Sqm/day
TG - 03 (Balance Plastering 1230.899 Sqmt) -
Plastering Grid C 18'-27 (6.00 mtr to 17.00 mtr
lvl)
Plastering Grid C 19 - 25 Sqm
TG - 04 (Balance Plastering 1200 Sqmt)
1 Supervisor Nos -
Mason Nos -
Carpenter Nos -
Fitter Nos -
Helper Nos -
WAGON TIPPLER
SCHEDULE
S.No Description of work Unit Balance Duration Start Date Finish Date Remarks
Wagon Tippler 114 days 11/17/2022 3/29/2023
A Side 62 days 11/17/2022 1/27/2023
Empty side arm charger 41 days 11/17/2022 1/3/2023
27 Rmt from Grid 14 -
8 days 11/17/2022 11/25/2022
depth 1.1 Mtr
Shuttering BGL Sqm 0 3 days 11/17/2022 11/19/2022
Bolt Fixing LS 0 2 days 11/21/2022 11/22/2022
Concrete Cum 0 1 day 11/23/2022 11/23/2022
Deshuttering Sqm 0 2 days 11/24/2022 11/25/2022
30 Rmt From Grid 4 33 days 11/26/2022 1/3/2023
Excavation 0 to 2 mtr Cum 0 1 day 11/26/2022 11/26/2022
Excavation 2 to 4 mtr Cum 0 1 day 11/28/2022 11/28/2022
Page 44 of 100
SCHEDULE
S.No Description of work Unit Balance Duration Start Date Finish Date Remarks
Concrete Cum 115.2 2 days 12/22/2022 12/23/2022
Deshuttering Sqm 72.5 2 days 12/24/2022 12/26/2022
Pedestal 30 Rmt length and
10 days 12/27/2022 1/6/2023
1.0 Mtr depth
Shuttering BGL Sqm 58 3 days 12/27/2022 12/29/2022
Bolt Fixing LS 1 3 days 12/30/2022 1/2/2023
Concrete Cum 115.2 2 days 1/3/2023 1/4/2023
Deshuttering Sqm 58 2 days 1/5/2023 1/6/2023
Page 45 of 100
SCHEDULE
S.No Description of work Unit Balance Duration Start Date Finish Date Remarks
Concrete Cum 36.888 1 day 1/20/2023 1/20/2023
Wall - 2 Nos 6 days 1/21/2023 1/27/2023
Reinforcement work MT 13.44 2 days 1/21/2023 1/23/2023
Shuttering Sqm 676.28 3 days 1/24/2023 1/26/2023
Concrete Cum 67.628 1 day 1/27/2023 1/27/2023
Page 46 of 100
SCHEDULE
S.No Description of work Unit Balance Duration Start Date Finish Date Remarks
Bottom Raft 9 days 3/13/2023 3/22/2023
Reinforcement work MT 5.76 4 days 3/13/2023 3/16/2023
Shuttering Sqm 30.74 4 days 3/17/2023 3/21/2023
Concrete Cum 36.888 1 day 3/22/2023 3/22/2023
Wall - 2 Nos 6 days 3/23/2023 3/29/2023
Reinforcement work MT 13.44 2 days 3/23/2023 3/24/2023
Shuttering Sqm 676.28 3 days 3/25/2023 3/28/2023
Concrete Cum 67.628 1 day 3/29/2023 3/29/2023
Abstract Qty
Reinforcement work 94.881
Shuttering 3157.7
Concrete 2488.144
Page 47 of 100
RAILWAY CULVERT
Mr. Guna Sekaran
Qty
S.No Description of work Unit Estimated
Completed Balance
Qty
Duration
S.No Description of work Unit Balance Start Date Finish Date Remarks
(Days)
16 8/25/2022 9/10/2022
Work delayed due
Cum
1 Earthwork Excavation 34.67 3 8/25/2022 8/28/2022 to rain
2 PCC Cum 2.00 1 8/28/2022 8/29/2022
3 Reinforcement works MT 6.43 12 8/25/2022 9/6/2022
4 Shuttering Sqm 79.55 10 8/27/2022 9/6/2022
5 RCC M35 Cum 19.00 7 8/28/2022 9/4/2022
6 RCC M20 Cum 15.00 3 9/2/2022 9/5/2022
7 Boulder filling Cum 150.00 4 9/6/2022 9/10/2022
8 Back filling Cum 311.09 3 9/7/2022 9/10/2022
Page 48 of 100
Helper Nos
Excavator Nos 1.00
Page 49 of 100
RESERVOIR PUMP HOUSE SCHEDULE
Description Unit Qty Duration Start Finish
Reservoir Pump House 136 days 11/16/2022 3/31/2023
Below Ground Level 98 days 11/16/2022 2/21/2023
F2 (4500 x 3500) - D1, D2 & D3 7 days 11/16/2022 11/22/2022
Earthwork Excavation 0 to 2 m Cum 153.032 1 day 11/16/2022 11/16/2022
PCC 1:4:8 Cum 5.217 1 day 11/17/2022 11/17/2022
Reinforcement work MT 2.76 2 days 11/18/2022 11/19/2022
Shuttering work - BGL Sqm 33.84 1 day 11/20/2022 11/20/2022
RCC M30 Cum 28.35 1 day 11/21/2022 11/21/2022
Deshuttering Sqm 33.84 1 day 11/22/2022 11/22/2022
Column - 9 Nos of 11.3 mtr depth (380 X 750) 31 days 12/23/2022 1/22/2023
Lift - 01 - 2.44 mtr Depth 7 days 12/23/2022 12/29/2022
Reinforcement work MT 0.847 2 days 12/23/2022 12/24/2022
Shuttering work - BGL Sqm 38.479 3 days 12/25/2022 12/27/2022
RCC M30 Cum 3.174 1 day 12/28/2022 12/28/2022
Deshuttering Sqm 38.479 1 day 12/29/2022 12/29/2022
Lift - 02 - 2.34 mtr Depth 7 days 12/29/2022 1/4/2023
Reinforcement work MT 0.812 2 days 12/29/2022 12/30/2022
Shuttering work - BGL Sqm 36.902 3 days 12/31/2022 1/2/2023
RCC M30 Cum 3.044 1 day 1/3/2023 1/3/2023
Deshuttering Sqm 36.902 1 day 1/4/2023 1/4/2023
Lift - 03 - 2.34 mtr Depth 7 days 1/4/2023 1/10/2023
Reinforcement work MT 0.812 2 days 1/4/2023 1/5/2023
Shuttering work - BGL Sqm 36.902 3 days 1/6/2023 1/8/2023
RCC M30 Cum 3.044 1 day 1/9/2023 1/9/2023
Deshuttering Sqm 36.902 1 day 1/10/2023 1/10/2023
Lift - 04 - 2.34 mtr Depth 7 days 1/10/2023 1/16/2023
Reinforcement work MT 0.812 2 days 1/10/2023 1/11/2023
Shuttering work - BGL Sqm 36.902 3 days 1/12/2023 1/14/2023
RCC M30 Cum 3.044 1 day 1/15/2023 1/15/2023
Deshuttering Sqm 36.902 1 day 1/16/2023 1/16/2023
Lift - 05 - 2.34 mtr Depth 7 days 1/16/2023 1/22/2023
Reinforcement work MT 0.812 2 days 1/16/2023 1/17/2023
Shuttering work - BGL Sqm 36.902 3 days 1/18/2023 1/20/2023
RCC M30 Cum 3.044 1 day 1/21/2023 1/21/2023
Deshuttering Sqm 36.902 1 day 1/22/2023 1/22/2023
Column - 4 Nos of 9.5 mtr depth (380 X 750) 12 days 1/9/2023 1/20/2023
Lift - 01 - 2.44 mtr Depth 3 days 1/9/2023 1/11/2023
Reinforcement work MT 0.405 1 day 1/9/2023 1/9/2023
Shuttering work - BGL Sqm 1.623 1 day 1/10/2023 1/10/2023
RCC M30 Cum 2.723 1 day 1/10/2023 1/10/2023
Deshuttering Sqm 1.623 1 day 1/11/2023 1/11/2023
Lift - 02 - 2.34 mtr Depth 3 days 1/12/2023 1/14/2023
Reinforcement work MT 0.388 1 day 1/12/2023 1/12/2023
Shuttering work - BGL Sqm 1.556 1 day 1/13/2023 1/13/2023
RCC M30 Cum 2.611 1 day 1/13/2023 1/13/2023
Deshuttering Sqm 1.556 1 day 1/14/2023 1/14/2023
Lift - 03 - 2.34 mtr Depth 3 days 1/15/2023 1/17/2023
Reinforcement work MT 0.388 1 day 1/15/2023 1/15/2023
Shuttering work - BGL Sqm 1.556 1 day 1/16/2023 1/16/2023
RCC M30 Cum 2.611 1 day 1/16/2023 1/16/2023
Deshuttering Sqm 1.556 1 day 1/17/2023 1/17/2023
Lift - 04 - 2.34 mtr Depth 3 days 1/18/2023 1/20/2023
Reinforcement work MT 0.388 1 day 1/18/2023 1/18/2023
Shuttering work - BGL Sqm 1.556 1 day 1/19/2023 1/19/2023
RCC M30 Cum 2.611 1 day 1/19/2023 1/19/2023
Deshuttering Sqm 1.556 1 day 1/20/2023 1/20/2023
Column - 4 Nos of 6.3 mtr depth (380 X 750) 9 days 1/16/2023 1/24/2023
Lift - 01 - 2.44 mtr Depth 3 days 1/16/2023 1/18/2023
Reinforcement work MT 0.434 1 day 1/16/2023 1/16/2023
Shuttering work - BGL Sqm 22.058 1 day 1/17/2023 1/17/2023
RCC M30 Cum 2.782 1 day 1/17/2023 1/17/2023
Deshuttering Sqm 22.058 1 day 1/18/2023 1/18/2023
Lift - 02 - 2.34 mtr Depth 3 days 1/19/2023 1/21/2023
Reinforcement work MT 0.417 1 day 1/19/2023 1/19/2023
Shuttering work - BGL Sqm 21.154 1 day 1/20/2023 1/20/2023
RCC M30 Cum 2.668 1 day 1/20/2023 1/20/2023
Deshuttering Sqm 21.154 1 day 1/21/2023 1/21/2023
Lift - 03 - 1.52 mtr Depth 3 days 1/22/2023 1/24/2023
Reinforcement work MT 0.271 1 day 1/22/2023 1/22/2023
Shuttering work - BGL Sqm 13.741 1 day 1/23/2023 1/23/2023
RCC M30 Cum 1.733 1 day 1/23/2023 1/23/2023
Deshuttering Sqm 13.741 1 day 1/24/2023 1/24/2023
Column - 4 Nos of 3.3 mtr depth (380 X 750) 6 days 1/23/2023 1/28/2023
Lift - 01 - 2.44 mtr Depth 3 days 1/23/2023 1/25/2023
Reinforcement work MT 0.481 1 day 1/23/2023 1/23/2023
Shuttering work - BGL Sqm 21.274 1 day 1/24/2023 1/24/2023
RCC M30 Cum 2.782 1 day 1/24/2023 1/24/2023
Deshuttering Sqm 21.274 1 day 1/25/2023 1/25/2023
Description Unit Qty Duration Start Finish
Lift - 02 - 0.86 mtr Depth 3 days 1/26/2023 1/28/2023
Reinforcement work MT 0.169 1 day 1/26/2023 1/26/2023
Shuttering work - BGL Sqm 7.498 1 day 1/27/2023 1/27/2023
RCC M30 Cum 0.98 1 day 1/27/2023 1/27/2023
Deshuttering Sqm 7.498 1 day 1/28/2023 1/28/2023
S.No Description of work Unit Estimated Qty Completed Qty Balance Qty
COAL SHED-SCHEDULE
1 Earthwork in Excavation Cum 5,400.00 5,400.00 -
2 Back filling/ Ash Filling Cum 20,544.00 2,559.00 17,985.00
3 PCC 1:4:8 Cum 132.61 132.61 -
4 Steel reinforcement Mt 269.77 179.81 89.96
5 Shuttering - BGL Sqm 3,244.22 2,993.60 250.62
6 Shuttering - AGL Sqm 11,421.77 4,870.87 6,550.89
7 RCC M 25 - BGL Cum 702.58 650.78 51.80
8 RCC M 25 - AGL Cum 2,416.23 1,196.36 1,219.88
9 RCC M 30 Cum 62.62 62.62 -
10 RR Masonry Cum 12,300.00 #REF! #REF!
11 Plumb Concrete Cum 4,250.00 1,771.50 2,478.50
RR Stones
Nos 150000 #REF!
(230x230x200mm-80Nos/Cum)
Page 57 of 100
Inplant Road
Budget Approval (Rmt) 2938 Completed (Rmt) 2758 Balance (Rmt) 180
Estimated Completed
S.No Description Unit Balance Qty Duration (Days) Start Date Finish Date Remarks
Qty Qty
INPLANT ROAD WORK - 2938.185 RMT 97 9/26/2022 1/18/2023
Road No. 97 (Cooling Tower
Road upto Fire & Safety Office) -
1 11 days 10/15/2022 10/26/2022 Completed
5.0 Mtr Width of length 148.147
Rmt
Carting away of surplus earth Cum 425.45 425.450 0.000 3 days 12/10/2022 12/13/2022
Hard Shoulder - Murram Laying Cum 180.341 180.341 7 days 1/7/2023 1/14/2023
Carting away of surplus earth Cum 1097.733 1097.733 - 5 days 12/14/2022 12/19/2022
Hard Shoulder - Murram Laying Cum 125.455 125.455 - 6 days 12/26/2022 12/31/2022
S.No Description of work Unit Estimated Qty Completed Qty Balance Qty
COAL SHED-SCHEDULE
1 Earthwork in Excavation Cum 5,400.00 5,400.00 -
2 Back filling/ Ash Filling Cum 20,544.00 2,559.00 17,985.00
3 PCC 1:4:8 Cum 132.61 132.61 -
4 Steel reinforcement Mt 269.77 179.81 89.96
5 Shuttering - BGL Sqm 3,244.22 2,993.60 250.62
6 Shuttering - AGL Sqm 11,421.77 4,870.87 6,550.89
7 RCC M 25 - BGL Cum 702.58 650.78 51.80
8 RCC M 25 - AGL Cum 2,416.23 1,196.36 1,219.88
9 RCC M 30 Cum 62.62 62.62 -
10 RR Masonry Cum 12,300.00 #REF! #REF!
11 Plumb Concrete Cum 4,250.00 1,771.50 2,478.50
RR Stones
Nos 150000 #REF!
(230x230x200mm-80Nos/Cum)
Page 60 of 100
Structure : Coal shed PROCESS SHEET
Work : RR wall weekly work Sheet
Working Details for (GRID A 16 TO 20 ) (B16 TO 25)( C16 TO 25) (D 14 TO 25) BACK
FILLING
RR
STEEL IN SHUTTERIN RCC IN WITH BOTTOM
WORK DETAILS WORK PLUM CC PCC TOP LEVEL HEIGHT REMARKS
S.No Date Mason Carpenter Fitter Helper KG G IN SQM CUM WATER LEVEL
IN CUM
COMPACTI
NOS L B H Qty Qty Qty Qty Qty
ON Qty
1 1/17/2023 45 6 3 120 1 224 0.6 0.5 45 0.85 40.00 6 40 22 253.500 256.150 2.65
2 1/18/2023 45 6 3 120 1 224 0.6 0.5 48 0.85 40.00 6 50 22 253.500 256.150 2.65
3 1/19/2023 45 6 3 120 1 200 0.45 0.75 48 1.20 45.00 6 45 18 253.500 256.150 staging=(68cum) with shifting
4 1/20/2023 45 6 3 100 1 160 0.45 0.9 40 1.00 26.00 8 50 18 253.500 256.150
5 1/21/2023 45 7 3 100 1 160 0.45 0.9 38 1.00 30.00 6 50 22 253.500 256.150 2.65
6 1/22/2023 45 7 3 10 1 160 0.45 0.9 0 0.85 8.00 6 40 18 253.500 256.150 2.65 staging=(64cum) with shifting
7 1/23/2023 45 6 3 100 1 0 0.45 0.9 38 - 0.00 0 50 0 253.500 256.150 2.65
8 1/24/2023 45 6 3 100 1 155 0.45 0.9 33 0.90 28.00 6 50 24 253.500 256.150 2.65
9 1/25/2023 45 6 3 100 1 125 0.45 0.9 42 0.90 29.00 4 50 24 253.500 256.150 2.65
10 1/26/2023 45 5 3 100 1 175 0.45 1 39 0.45 25.00 4 50 24 253.500 256.150 2.65 staging=(96cum) with shifting
11 1/27/2023 45 5 3 100 1 150 0.45 0.9 38 0.50 35.00 6 80 18 253.500 256.150
12 1/28/2023 45 5 3 100 1 130 0.45 0.9 39 0.80 36.00 6 50 16 253.500 256.150 2.65
13 1/29/2023 45 6 3 10 1 165 0.45 0.75 0 0.80 12.00 8 50 12 253.500 256.150 2.65
14 1/30/2023 45 6 3 100 1 0 0.45 0.9 37 - 38.00 0 50 22 253.500 256.150 2.65
15 1/31/2023 45 6 3 100 1 0 0.45 0.9 39 - 30.00 0 50 22 256.150 257.000 0.85
16 2/1/2023 45 7 3 100 1 0 0.45 0.9 41 - 18.00 0 50 22 256.150 257.000 0.85
675 89 45 1380 524 10.10 422.00 72 755 283 0 13.25 APPROX LENGTH (100 TO 120 RMT)
work done 1 week out of 2 week 520 9.30 216.00 102 450 120
balance qty for 1 week 37.43 -4 -1 -206 30 -305 -163 0
ABSTARACT
# Mason utilization @ 42/ day
# Helper utilization @ 105/ day ( i/c @ 3 helper / Mason) due to height (+2 mtr to +5mtr)
# Total man power proposed to be engaged @ 150 / day
# Output RR Work @ 330 cum / Week
# Output RR Work @ 47 cum / day
# Output mason @ 1.15 cum / day
# Output shuttering @ 23 Sqm / day ( mason gang can do the shuttering )
# Output Steel @ 1.0 Mt / day
# Output concrete @ 25 Cum / day
# Output back filling @ 50 Cum / day ( Ash and soil filling)
ASH POND - 3&4 Balance reworks Schedule
Site Engineer : Lavkush singh
Constrains Ash to be Evacuated
Action by
Qty
% Of
S.No Description of work Unit Estimated Complet Completion
% of Balance
Balance
Qty ed
ASH POND - 3&4
1 3&4 Connecting bond soil cutting Cum 54,548.55 7,290.00 47,258.55 13% 87%
Side bond Ash removing & bond Sqm 27% 73%
2 Preparation work 18,530.00 4,921.50 13,608.50
HDPE Sope + bottom Film for Ash Sqm 17% 83%
3 Pond 9,578.00 1,600.00 7,978.00
4 Steel reinforcement MT 6.75 0.19 6.56 3% 97%
5 Shuttering - Bgl Sqm 623.11 - 623.11 0% 100%
6 RCC M20 Cum 76.91 - 76.91 0% 100%
7 Brickwork 115 mm thk Sqm 9,860.99 - 9,860.99 0% 100%
Brick laying above cleaning work & 0% 100%
8 grouting work Sqm 10,355.11 - 10,355.11
Overall 4% 96%
SCHEDULE
Status: Balace civil started for Slope bond area
Duratio
S.No Description of work Unit Balance Start Date Finish Date Remarks
n
ASH POND -3 &4 59
1 3&4 Connecting bond soil cutting Cum 47,258.55 59.00 2/1/2023 3/31/2023
2 Side Bond Ash removing & bond Sqm 13,608.50 33.00 2/1/2023 3/6/2023
Preparation work
3 HDPE Laying work Sqm 7,978.00 39.00 2/3/2023 3/14/2023 1.Ash Evacuation
4 Steel reinforcement MT 6.56 35.00 2/4/2023 3/11/2023 works under progress
in bottom area .
5 Shuttering - Bgl Sqm 623.11 40.00 2/5/2023 3/17/2023
6 RCC Tie Beam Cum 76.91 42.00 2/6/2023 3/20/2023
7 Brick work 115mm thk Sqm 9,860.99 36.00 2/7/2023 3/15/2023
8 Brick laying above cleaning work & 10,355.11 34.00 2/10/2023 3/15/2023
grouting work Sqm
QUARTERS 4th PRIORITY (25 - 48 BLOCKS )
Page 64 of 100
Structure : Family Quarters-Block-18
Work :Brickwork,Plastering, Shuttering ,reinforcement, concrete work
DE-SHUTTERING IN
BRICKWORK in Cum INTERNAL PLASTERING in Sqm EXTERNAL PLASTERING in Sqm STAGING in Sqm STEEL IN MT SHUTTERING IN SQM
SQM
S.No Date Mason Tiles Mason Helper Carpender Fitter Helper Description of item
Planned Executed Planned Executed Planned Executed Planned Executed Planned Executed Planned Executed Planned
i) Internal Plastering
3 8
i) Internal Plastering
3 8
7 12/7/2022
55 0 130 6 0 6
5 Mason
2 Internal Plastering 60 Sqm/day
10 Helper
5 Mason
3 External Plastering 40 Sqm/day
10 Helper
Page 65 of 100
Structure : Family Quarters-Block-18
Work :Brickwork,Plastering, Shuttering ,reinforcement, concrete work
DE-SHUTTERING IN
BRICKWORK in Cum INTERNAL PLASTERING in Sqm EXTERNAL PLASTERING in Sqm STAGING in Sqm STEEL IN MT SHUTTERING IN SQM
SQM
S.No Date Mason Tiles Mason Helper Carpender Fitter Helper Description of item
Planned Executed Planned Executed Planned Executed Planned Executed Planned Executed Planned Executed Planned
Material
Date Description Available balance required
Requirement
1 Cement 200.000 BAG
Stock at site
2 Sand 50.000 CUM
3 Bricks 11700.000 NOS 3000 nos/day from Brickplant 11700
Page 66 of 100
DE-SHUTTERING IN
RCC IN CUM
SQM
Brick shifting
0.50
Brick shifting
1.00
Brick shifting
1.50
Brick shifting
Brick shifting
2.00
Page 67 of 100
DE-SHUTTERING IN
RCC IN CUM
SQM
Brick shifting
Brick shifting
- 5.00 - -
Page 68 of 100
Structure : Family Quarters-Director House
Work :Brickwork,Plastering, Shuttering ,reinforcement, concrete work
INTERNAL WALL CEILING PLASTERING in EXTERNAL WALL DE-SHUTTERING IN
BRICKWORK in Cum STAGING in Sqm SHUTTERING IN SQM RCC IN CUM SCREED CONCRETE
PLASTERING in Sqm Sqm PLASTERING in Sqm SQM
S.No Date Mason Helper Carpender Fitter Helper Description of item
Planned Executed Planned Executed Planned Executed Planned Executed Planned Executed Planned Executed Planned Executed Planned Executed Planned
5 8
5 8
4 6
5 8
5 8
Page 69 of 100
Structure : Family Quarters-Director House
Work :Brickwork,Plastering, Shuttering ,reinforcement, concrete work
INTERNAL WALL CEILING PLASTERING in EXTERNAL WALL DE-SHUTTERING IN
BRICKWORK in Cum STAGING in Sqm SHUTTERING IN SQM RCC IN CUM SCREED CONCRETE
PLASTERING in Sqm Sqm PLASTERING in Sqm SQM
S.No Date Mason Helper Carpender Fitter Helper Description of item
6 12/6/2022
Planned Executed Planned Executed Planned Executed Planned Executed Planned Executed Planned Executed Planned Executed Planned Executed Planned
5 8
5 8
65 116
5 Mason
2 Internal Plastering 60 Sqm/day
10 Helper
5 Mason
3 External Plastering 40 Sqm/day
10 Helper
4 Brick requirement from plant 3000 nos/day
Material balance
Date Description Available
Requirement required
1 Cement 200.000 BAG
Stock at site
2 Sand 50.000 CUM
3 Bricks 12924.000 NOS 3000 nos/day from Brickplant 12924
Page 70 of 100
SCREED CONCRETE
Executed REMARKS
Sand Shifting
Sand Shifting
Brick Shifting
Sand Shifting
Brick Shifting
Sand Shifting
Brick Shifting
Sand Shifting
Brick Shifting
Sand Shifting
Page 71 of 100
SCREED CONCRETE
Executed REMARKS
Brick Shifting
Sand Shifting
Brick Shifting
Page 72 of 100
Structure : Family Quarters-Block-15
Work :Brickwork,Plastering, Shuttering ,reinforcement, concrete work
BRICKWORK in Cum INTERNAL PLASTERING in Sqm EXTERNAL PLASTERING in Sqm STAGING in sqm SHUTTERING IN SQM RCC IN CUM
S.No Date Mason Helper Carpender Fitter Helper Description of item
Planned Executed Planned Executed Planned Executed Planned Executed Planned Executed Planned Executed REMARKS
i) Internal Plastering
10
6 12/6/2022
i) Internal Plastering
8 16
7 12/7/2022
Page 73 of 100
Structure : Family Quarters-Block-15
Work :Brickwork,Plastering, Shuttering ,reinforcement, concrete work
BRICKWORK in Cum INTERNAL PLASTERING in Sqm EXTERNAL PLASTERING in Sqm STAGING in sqm SHUTTERING IN SQM RCC IN CUM
S.No Date Mason Helper Carpender Fitter Helper Description of item
Planned Executed Planned Executed Planned Executed Planned Executed Planned Executed Planned Executed REMARKS
7 12/7/2022
44 78 5 4 31 0
5 Mason
2 Internal Plastering 60 Sqm/day
10 Helper
5 Mason
3 External Plastering 40 Sqm/day
10 Helper
Material balance
Date Description Available
Requirement required
1 Cement 250.000 BAG
Stock at site
2 Sand 75.000 CUM
3 Bricks 15300.000 NOS 3000 nos/day from Brickplant 15300
Page 74 of 100
Structure : Family Quarters-Guest House
Work :Brickwork,Plastering, Shuttering ,reinforcement, concrete work
BRICKWORK i
S.No Date Mason Helper Carpender Fitter Helper Description of item
Planned
2 12/2/2022
ii)GF- Ceiling Plastering
Page 75 of 100
Structure : Family Quarters-Guest House
Work :Brickwork,Plastering, Shuttering ,reinforcement, concrete work
BRICKWORK i
S.No Date Mason Helper Carpender Fitter Helper Description of item
Planned
3 12/3/2022
4 04-12-2022 (Sunday)
iii)GF- Lintel sunshade work
Page 76 of 100
Structure : Family Quarters-Guest House
Work :Brickwork,Plastering, Shuttering ,reinforcement, concrete work
5 12/5/2022
BRICKWORK i
S.No Date Mason Helper Carpender Fitter Helper Description of item
Planned
7 12/7/2022
ii)GF- Lintel sunshade work
Page 77 of 100
Structure : Family Quarters-Guest House
Work :Brickwork,Plastering, Shuttering ,reinforcement, concrete work
BRICKWORK i
S.No Date Mason Helper Carpender Fitter Helper Description of item
Planned
10.00
Page 78 of 100
Structure : Family Quarters-Guest House
Work :Brickwork,Plastering, Shuttering ,reinforcement, concrete work
BRICKWORK i
S.No Date Mason Helper Carpender Fitter Helper Description of item
Planned
4 Nos
1 MT/Day
1 Barbending works 7 Nos
1 Nos
5 sqm/Day
2 Shuttering Works 1 Nos
3 Mason
3 cum/Day
3 Brick work 8 Helper
5 Mason
4 Internal Plastering 60 Sqm/day
10 Helper
5 Mason
5 External Plastering 40 Sqm/day
10 Helper
Material balance
Date Description Available
Requirement required
1 Cement 200.000 BAG
Stock at site
2 Sand 50.000 CUM
3 Bricks 4500.000 NOS 1000 nos/day from Brickplant 4500
Page 79 of 100
ICKWORK in Cum CEILING PLASTERING in Sqm PCC in Cum STEEL MAKING IN MT STEEL FIXING IN MT SHUTTERING IN SQM RCC IN CUM
Executed Planned Executed Planned Executed Planned Executed Planned Executed Planned Executed Planned
10.00
13.32
10.00
25.00
Page 80 of 100
ICKWORK in Cum CEILING PLASTERING in Sqm PCC in Cum STEEL MAKING IN MT STEEL FIXING IN MT SHUTTERING IN SQM RCC IN CUM
Executed Planned Executed Planned Executed Planned Executed Planned Executed Planned Executed Planned
4.00
15.00
13.00
6.00
25.00
12.00
2.00
Page 81 of 100
ICKWORK in Cum CEILING PLASTERING in Sqm PCC in Cum STEEL MAKING IN MT STEEL FIXING IN MT SHUTTERING IN SQM RCC IN CUM
Executed Planned Executed Planned Executed Planned Executed Planned Executed Planned Executed Planned
1.00
8.00
0.50
1.00
4.00
2.00
Page 82 of 100
ICKWORK in Cum CEILING PLASTERING in Sqm PCC in Cum STEEL MAKING IN MT STEEL FIXING IN MT SHUTTERING IN SQM RCC IN CUM
Executed Planned Executed Planned Executed Planned Executed Planned Executed Planned Executed Planned
Page 83 of 100
RCC IN CUM
Executed REMARKS
Page 84 of 100
RCC IN CUM
Executed REMARKS
Page 85 of 100
RCC IN CUM
Executed REMARKS
Page 86 of 100
RCC IN CUM
Executed REMARKS
Page 87 of 100
S.No Description Supervisor Painter Plumber Mason Carpenter Fitter Helper Total
1 Ash Pond-2B 0.00
2 Reservoir 0.00
3 Reservoir-Pump House 0.00
4 Coal shed 0.00
5 Coal Road 0.00
6 Ash water recovery structure 0.00
7 Inplant road 0.00
8 Road - Family quarters 0.00
9 Stacker Reclaimer 0.00
10 TG 0.00
11 Weigh Bridge 0.00
12 Admin Building 0.00
13 Family Quarters 0.00
14 Railway culvert 0.00
15 Store 0.00
16 Labour colony 0.00
Grand Total 0.00
Time Study
S.No Description Unit Capacity
1 Excavator Cum 0.80
2 Hywa Capacity Cum 11.50
Loading time of one excavator to
3 Hywa (10 Buckets) Mins 15.00
Leading from source to Ash
4 pond 2B Mins 25.00
Leading from source to
Reservoir Mins 15.00
Leading from source to Ash
Pond 01 Mins 20.00
5 No of Trips per Day
Ash Pond 2 B 8 to 9
Reservoir 10 to 11
Ash Pond 01 8 to 9
STRUCTURE NO'S START DATE COMPLETION DATE
DEPUTY MANAGER 1 10/1/2023 3/30/2024
SUPERVISOR
17 NO'S
QUARTERS
Phase 1 6 10/1/2023 3/30/2024
Phase 2 6 11/1/2023 4/30/2024
phase 3 5 11/15/2023 4/14/2024
ASH RECOVERY-SCHEDULE
S.No Description of work Duration Start Date Finish Date
Supervisor Nos -
Mason Nos -
Carpenter Nos 2.00
Fitter Nos 2.00
Helper Nos 2.00
Total Manpower Nos 6.00
Remarks
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Work in progress
Available Qty Total Qty
1.00 1.00
1.00 1.00
1.00 3.00
1.00 4.00
5.00 6.00
9.00 15.00
ASH POND -2B DECANTING WELL-SCHEDULE
S.No Description of work Duration Start Date Finish Date
Manpowe
Unit Required Qty
r details
Supervisor Nos -
Mason Nos -
Carpenter Nos 2.00
Fitter Nos 1.00
Helper Nos 4.00
Total Manpower Nos 8.00
EDULE
Remarks
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
work in progress
Available Qty Total Qty
1.00 1.00
1.00 1.00
1.00 3.00
2.00 3.00
3.00 7.00
8.00 15.00
22