Cumulative Environment, Health and Safety Reports

Site: BGPL Project Section-VI Guwahati Date:03.10.2022


For the Month: Septmber-2022 Report No.:42
Cumulative Year- 2022
SR.NO. DATA REQUIRED Cumulative
upto 2021
Jan Feb Mar April May June July Aug Sep Oct Nov Dec Total
1 Average No. of staff's and workman / Day 6,417 248 225 258 182 174 179 176 161 173 1776 8,193
2 Total Man-hours worked 1,745,316 74400 67500 77,400 54,600 53940 53700 52800 49910 51,900 536,150 2,281,466
3 Total safe man hours achieved since inception 1,745,316 74400 67500 77,400 54,600 53940 53700 52800 49910 51,900 536,150 2,281,466
4 Number of First Aid cases 8 3 4 2 1 1 2 1 2 1 17 25
5 Lost Time Injury cases (Absent due to injury over 48 hours) 0 0 0 0 0 0 0 0 0 0 0 0
6 Number of Fatalities 0 0 0 0 0 0 0 0 0 0 0 0
Incident Rate - ( No. of occurrences in the period x 100/ No.of
7 0 0 0 0 0 0 0 0 0 0 0
workers ) 0
Frequency rate - (No. of occurrences in the period x 25,000/
8 0 0 0 0 0 0 0 0 0 0 0
No. hours worked in the period)
0
Average Time Lost Rate - (No. of working days lost / No. of
9 0 0 0 0 0 0 0 0 0 0 0 0
occurrences in the period)
10 Number of Man days lost 0 0 0 0 0 0 0 0 0 0 0 0
11 Number of Near miss cases 4 2 1 2 0 0 0 0 2 1 8 12
12 Number of Fire Incident 0 0 0 0 0 0 0 1 0 0 1 1
13 Number of Restricted work Medical Cases 0 0 0 0 0 0 0 0 0 0 0 0
14 Number of Environmental Incidents 0 0 0 0 0 0 0 0 0 0 0 0
15 Number of Road Incident 4 0 0 0 0 0 0 1 0 0 1 5
16 Number of unsafe acts & conditions detected 60 26 18 20 10 0 24 18 16 10 142 202
17 Number of induction training conducted 39 4 0 8 0 0 2 0 2 3 19 58
18 Number of audits conducted 1 0 0 1 0 0 1 0 0 0 2 3
19 Number of tool box talk conducted 580 29 26 24 20 22 40 30 22 24 237 817
20 Number of Mock drill conducted 0 0 0 0 0 0 1 0 0 0 1 1
21 Number of HSE Inspection conducted 103 4 4 4 2 0 4 4 4 4 30 133
22 Total KMH driver (Light transport vehicle including buses) 2,281,796 112197 111246 109054 96338 84085 58463 69956 64439 63112 768,890 3,050,686

PREPARED BY : EHSM/O Date: 03.10.2022 VERIFIED BY : Project Manager/RCM Date:03.10.2022

SIGN. : SIGN. :

NAME: Pawan Mani Tripathi NAME : KUMAR RAVISHANKAR / VISHNU SANKAR OJHA