Professional Documents
Culture Documents
Table of Contents
1. Purpose
This document describes the method and work sequence of the cast in place Bridge BCM Works
(Balance Cantilever Method) for the Dompak - Bintan Bridge Project, Riau islands.
2. Workscope
2.1 Scope
The scope of this method statement includes the construction of the superstructure of the
Dompak - Bintan Bridge Project, Riau Islands. The work starts from the installation of the
form travelers on the pier head until the completion of the closure segments and dismantling
of form travelers.
Installation of Form
Travellers (P6 & P7)
Construction of Closure
Segments
Dismantling of Form
Travellers
Method
Dompak – Bintan Statement
Bridge Project Date : 11 Mar, 2014
Bridge BCM Works Page : 3 of 23
Install formwork
Method
Dompak – Bintan Statement
Bridge Project Date : 11 Mar, 2014
Bridge BCM Works Page : 4 of 23
Fixing of formwork
Survey Check
Installation of end formwork,
anchor block
segment 1 to segment
10 of P6 & P7 both Curing
sides
Installation of tendon
Prestessing
Prestressing
Grouting
Method
Dompak – Bintan Statement
Bridge Project Date : 11 Mar, 2014
Bridge BCM Works Page : 5 of 23
Survey Check
Pouring concrete 1st stage
Curing
Fix front end of bottom and web Front end of bottom and web
formwork to concrete of opposite formwork must still hang from the
segment form traveler but tight against
concrete of opposite segment
Pouring concrete
Method
Dompak – Bintan Statement
Bridge Project Date : 11 Mar, 2014
Bridge BCM Works Page : 7 of 23
Prestressing
Grouting
Bottom formwork shall be pre-assembled under the pier head on its lifting position.
5.1 Survey
After form traveler installation, survey the Bottom Form, Cantilever Form, Drive Deck
Form and make necessary adjustments according to design camber specified in
construction engineering.
5.3.1 Install longitudinal ducting after rebar is finished. Provide support bars
in every 0.5m – 0.8m of the duct to attain the desired profile of the
tendon. Additional bar supports shall be put to keep the ducts in place.
Install anchorage system temporarily. Fixing of the anchorage and
grouting tubes shall be done later simultaneously with the end formwork.
5.3.2 Install holes location for form traveler anchors and miscellaneous
embeds on location.
Set up a 32m pump car from the ground wherein the discharge end can reach the
bottom formwork through the inside of web. Concrete must not be dropped higher than
1.5m from end of pipe to the formwork to avoid segregation. Using concrete of class
K500, pour bottom slab first one side at a time pouring 0.5m high of concrete each
time. Pour concrete from the side towards the center until the whole bottom slab is full.
While pouring, consolidate concrete using high frequency vibrators of not less than
7,000 impulses per minute in a uniform pattern of about 450mm distance for about
5~15 second not farther apart where vibrator is visibly effective. Proceed to the web
pouring the center one then from one side to the other at a time with 0.5m high of
concrete each time in layers and cover each layer of fresh concrete within 45minutes.
While pouring consolidate concrete using high frequency vibrators. Work vibrator well
around rebars, ducts and embeds to create a good concrete compaction. Proceed to the
top slab by pouring from one side to the other working towards the center until the top
slab is full. Again, while pouring, consolidate concrete using high frequency vibrators
and work well around rebars, ducts and embeds. Keep an eye on the grouting tubes,
making sure that nothing is damaged/broken. Finish concrete to desired level and slope
2 2 2
5.8 Curing
Burlap sheets and water shall be used for curing the deck; and curing compound for
soffit and web walls.
5.11 Stressing
5.11.1 Installation of wedge plates and wedges
Place the wedge plate both on the anchorage end and on the stressing end. Rotate
the plates to align strands. Install the wedges over the strands. Use a 1-inch G.I.
pipe to push the wedges into the wedge plate.
5.11.4 Stressing
Stressing shall commence only upon required concrete strength of 28 Mpa has been
reached.
Method
Dompak – Bintan Statement
Bridge Project Date : 11 Mar, 2014
Bridge BCM Works Page : 13 of 23
- When the stressing report has been approved, the strands can be cut
approximately 30 - 50 mm from the wedge plate by using a grinding
disc.
5.12 Grouting
Grout consists of:
- Portland cement in 50 kg bags
- Water
- Sika Intraplast Z additive, or similar
- Water / cement ratio: 0.4 ~ 0.45
The DSI mixers are specially designed for the purpose of mixing and agitating the
grout and carrying out the grouting operation in a single unit of equipment.
5.13 Advance Form Traveller to Next Segment (repeat sequence up to last segment)
Upon completion of each segment, release forms, anchors and advance form traveller
to next segment.
FT
CLOSURE
BCM Segments
Closure Segment
Abutment
BCM
Segment on Falsework
8.2.2 Survey
Establish survey points on top of forms, marking layout and elevation from which all
other measurements shall be reckoned.
8.3.1 Rebar
Install web rebar.
2 2 2
8.4.2 Formwork
Install top formwork on the scaffolding.
8.4.3 Survey
Establish survey points on top of forms, marking layout and elevation from which all
other measurements shall be reckoned.
8.4.8 Curing
Burlap sheets and water shall be used for curing deck; and curing compound for soffit
and web walls.
8.4.9 Remove end forms, side forms, & form ties (Refer to Section 5.9)
8.4.10 Insert Strand (Refer to Section 5.10)
8.4.11 Stressing (Refer to Section 5.11)
8.4.12 Grouting (Refer to Section 5.12)
8.4.13 Removal of Formwork
Important : Formwork shall not be removed until the closure segment has been
constructed and prestressed. However, a space of 1.2m shall be provided to
accommodate the front end of the form traveler formwork after launching for the
closure segment. This shall be done by arranging the scaffolding in such a way that
the end row can be removed independently without removing the rest of the scaffolding.
9.0 Safety
9.1 Conduct safety orientation to equip personnel with the knowledge, skill and attitude that will
enable them to perform their duties in a safe manner and to prevent accidents, and the findings of
the risk and method statements.
9.9.2 Concrete Pump – Use pump car fitted with elephant trunk pipes with
sufficient capacity to suit construction condition. It should be positioned on stable
ground during operation.
9.9.3 Jack – Use jack suitable for the required tendon type and stressing load. All
accessories shall be maintained in good condition prior to every operation.
Mount jack with proper hoisting gear. Maximum pressures shall never be exceeded.
10.0Environmental Management
10.3 Cleanliness
All vehicles and transport trucks are to be cleaned before they are used on the road.