PROJECT IMPLEMENTATION
1
In this chapter, we will describe the implementation of the work that the writer
observed while carrying out practical work starting 01 August 2019 until 01 November
2019, which is the upper structure work from the second floor to the fourth floor. The top
structure work observed in the development of the Project of Hotel Quest by Aston
Semarang was as follows:
a. Column work, especially the focus of the study of second, third
and fourth floors
b. Beam Work, especially the focus of the study on the third and
fourth floors
c. Floor plate work, specifically the focus of study on the third and
fourth floors
4.2 Work column
The column work on this project is carried out after the
ground floor work is completed. The column is the main structure
of the portal building which serves to carry vertical, horizontal, and
momentary loads, both from fixed and temporary loads.
The general provisions for structural columns in The
Project of Hotel Quest by Aston Semarang:
a. Using the Quality Concrete fc '26.89 MPa
b. Thick blankets Concrete is 5 cm
c. Main reinforcement using steel screw D25
d. Stirrup reinforcement using steel screw D10
e. Column 4 meters high (2nd floor - 4th floor)
Conduct field work in general can be seen in the
flowchart as follows:
START
PREPARATORY
REINFORCEMENT COLUMN
NO
CEK REINFORCING
YES
INSTALLATION OF FORMWORK
NO
CEK FORMWORK
YES
CASTING COLUMN
RELEASE FORMWORK
d. Casting Column
Before doing casting, slump test was tested on ready mix
concrete materials and making samples for concrete press tests
in the laboratory. The concrete used is ready mix concrete with
K-300 quality and fc’ concrete compressive strength of 26.89
MPa. This concrete is sent
from PT.BetonAdhimix Precast uses concrete mixer truck in
accordance with the ordering needs in the field. The casting of
the 3rd floor column is done on 12 September 2019.
At the time of casting, the slump value obtained is 12 cm.
The slump value is in accordance with the requirement that the
required slump value is 12 ± 2 cm.
The implementation of column casting on this project uses
a concrete pump truck, because this project does not use a
tower crane, each casting always uses a concrete pump truck
type super long boom. When the concrete casting process must
be mixed with concrete vibrators so that the concrete can be
solid and perfectly does not cause porous concrete.
START
PREPARATORY WORK
INSTALLATION SCAFFOLDING
NOT
CHECK
FORMWORK
YES
RELEASE FORMWORK
Then using water pass, the other columns are also given
the same elevation marking
From the elevation, is used as a benchmark to measure
the elevation beam and slab with
measure formwork of the beam and the floor plate
30
0
40
0
10
0
b. Installation Scaffolding
Scaffolding or scaffolding is used as a temporary structure
that functions as a buffer/buffer load on it, namely, formwork,
concrete mortar, and floor slabs and labor during the casting
process takes place on the construction of buildings.
Scaffolding is arranged so that it can support the load above
it. If there is an error or elevation change, the scaffolding can
be reset again without the need to dismantle it, just by setting
the u-head or jack base to adjust the elevation. Scaffolding for
beams is established based on the position of the beam and is
usually established between columns while for the floor plate is
established in the middle of the floor plate area by adjusting the
distance of each frame based on needs.
Figure 4.18 Installation Scaffolding
c. Installation Formwork
1) Installation Formwork Beam
Installation of beam formwork and floor plates is
installed as beams and floor plates are finished, the
installation is done at the location. Formwork is prepared
before installation. Beam formwork is supported by solar
beam and scaffolding. Scaffolding or scaffolding is the
main support of formwork. Scaffolding on this project uses
PCH where there are 2 types of sizes, 1.8 meters for
beam restraints and
2.4 meters for floor plate restraints. After that, give the suri
beam and the picul beam above. The main ingredients
above that must be prepared include:
o PCH framework consisting of:
1. Jack base
2. standart
3. Ledger
4. U-head
5. Hollow
6. Suri- suri
7. plywood
o plywoodwith a thickness of 20 mm
o Tooling tools such as saws, hammers and nails
Solution
Somealternatives are made so that the porous column can
return smoothly and the structure can function properly:
Closing porous parts by grouting or patching with ordinary
mortar material if porous/damage is not too large
Thickening the dimensions of the column, how to install
additional reinforcement iron outside the column, then cast
it again covering the existing column
If there is a lot of porosity, it must be demolished to be
replaced with a new one. To find out whether the column
still meets the requirements or cannot be done with the
hammer ters.
Solution
The solution to overcome the as-point that is not precise in
The Project of Hotel Quest by Aston in Semaang is as follows :
Thicken the dimensions of the column so that it is equal to
the others
Remeasuring the column connection stage for the next
column, namely by bending the reinforcement iron to align
with the others.
CHAPTER V
CONCLUSION AND SUGGESTION
5.1 CONCLUSION
Based on the results of observations in the field while following
the Job Training on the implementation of the work of the Project of Hotel
Quest by Aston Semarang the authors took several conclusions, namely as
follows :
1. Lack of a culture of occupational safety and health (K3) that causes
undisciplined workers, therefore they easily ignore the use of safety
equipment
2. The construction of this building used is reinforced concrete structure
with K-300 concrete compressive strength
3. In the construction of the Project of Hotel Quest by Aston Semarang
the value of the Slump Test was 12 ± 2 cm
4. In the contruction less perfect structural work on the column not
precision,errors in the process of installaton of fromwork.but the
nominal difference < 10 cm is normal tolerance.
5.2 SUGGESTION
By looking at a number of problems during the practical work
activities at PT. Purikencana, namely Project of Hotel Quest by Aston
Semarang. For this reason, try to provide some suggestion, including
the following :
1. It was recommended that in the execution of casting columns, beams
or floor plates, it should be considered in cleaning the casting area and
using concrete vibrators so that the concrete is completely solid so that
porous concrete does not occur
2. During work construction, the guarantee of labor safety and security
was always available and well maintained such as the availability of
safety helmets, safety shoes and safety belts. This is intended so that
work safety during construction work takes place more assured
3. It was better if the consultants have their own divisions in the
development process, not only one consultant who would later confuse
the consultant himself if not in his field
4. In the implementation of development, which was already on the upper
floor, it was better to install a project safety net, so that the debris
falls from the project not in the house, so it does not favor the local
residents.