Professional Documents
Culture Documents
ON
INDUSTRIAL TRAINING
Starting date of training March - 2019
Roll no :-15113240
Semester :- 8th
Acknowledgement
It is great pleasure to present this report on Industrial training undertaken by me as a part of my Civil
Engineering curriculum.
I am thankful to “MRSPTU” for offering me such a wonderful challenging oppurtunity and I express
my deepest thanks to all coordinators of “GULMOHAR HEIGHTS” for providing all the possible
help and assistance and their constant encouragement during my training.
It is pleasure that we find ourselves penning down these lines to express our sincere thanks to the
people who helped us along the way in completing our project. We find inadequate words to express
our sincere gratitude towards them.
First and foremost we would like to express our gratitude towards our training guide Er. Narendra
Singh
(Site Engineer)for placing complete faith and confidence in our ability to carry out this project and for
providing us his time, inspiration, encouragement, help, valuable guidance, constructive criticism and
constant interest. He took personal interest in spite of numerous commitments and busy schedule to
help us complete this project. Without the sincere and honest guidance of our respected project guide
we would have not been to reach the present stage.
Project Details
Project Name:Construction of multi-storey residential building in Ropar Road NH Kharar
(Mohali)
Store
Parking space
Health unit
Transportation facilities
SECTION - 2
CONSTYRUCTION STEPS INVOLVED IN BUILDING
CONSTRUCTION
2.3 Excavation
2.5 Concreting
Auto level is a modified form of dumpy level. We used auto level to transfer the
level of ground to retaining wall and setting thickness of slab in which first of all
marking was made to fix the level of particulars elevations then casting of slab was
performed.
4- Locate the staff on the formwork of retaining wall and adjust the staff in such a
way that reading of staff is same as staff reading in step 3.
2.3 EXCAVATION
Excavation work on the site was being done by the JCB machines and excavated
soil was transferred using dumpers.
2.4 FOUNDATION
Footing are strips of concrete or filled concrete blocks placed under foundation
wall. Gravel or crushed stone footings may also be used. The purpose of footing is
to transfer the loads safety in the ground.
Generally in high rise buildings three types of buildings are
provided
Isolated footing:-
The slump test is the most simple workability test for concrete, involves low cost and provides
immediate results. Due to this fact, it has been widely used for workability tests since 1922.
The slump is carried out as per procedures mentioned in ASTM C143 in the United States,
IS: 1199 – 1959 in India and EN 12350-2 in Europe.
Generally concrete slump value is used to find the workability,which indicates water-
cement ratio, but there are various factors including properties of materials, mixing
methods, dosage, admixtures etc. also affect the concrete slump value.
Factors which influence the concrete slump test:
1. Material properties like chemistry, fineness, particle size distribution, moisture content and
temperature of cementitious materials. Size, texture, combined grading, cleanliness and
moisture content of the aggregates,
2. Chemical admixtures dosage, type, combination, interaction, sequence of addition and its
effectiveness,
3. Air content of concrete,
4. Concrete batching, mixing and transporting methods and equipment,
5. Temperature of the concrete,
6. Sampling of concrete, slump-testing technique and the condition of test equipment,
7. The amount of free water in the concrete, and
8. Time since mixing of concrete at the time of testing.
Equipments Required for Concrete Slump Test:
Mould for slump test, non porous base plate, measuring scale, temping rod. The mould for the test
is in the form of the frustum of a cone having height 30 cm, bottom diameter 20 cm and top
diameter 10 cm. The tamping rod is of steel 16 mm diameter and 60cm long and rounded at one
end.
When the slump test is carried out, following are the shape of the concrete slump that can be
observed:
o True Slump – True slump is the only slump that can be measured in the test. The
measurement is taken between the top of the cone and the top of the concrete after the
cone has been removed as shown in figure-1.
o Zero Slump – Zero slump is the indication of very low water-cement ratio, which
results in dry mixes. These type of concrete is
o generally used Collapsed Slump for road construction.– This is an indication that the water-
cement ratio is too high, i.e. concrete mix is too wet or it is a high workability mix, for which
a slump test is not appropriate.
o Shear Slump – The shear slump indicates that the result is incomplete, and concrete to be
retested.
2.6 WALL CONSTRUCTION
In framed structure generally brick walls are constructed for partition purpose and half
brick walls are made. But at the site no wall was constructed with brick because it was a
high rise building. All the walls were constructed as RCC wall because these acts as a
shear wall and provide horizontal stability to building and reduces the deflection.
Fig. 9:- Workers at site during forming work for R.C.C. wall
construction
In framed structure fixed type beams are constructed. In such type of proper
reinforcement should be done for positive as well as negative bending moments. In such
type of structures short columns are constructed with minimum eccentricity. In square or
rectangular shaped columns min. 4 no's of 12 mm diameter bars must be used and spacing
should not be more than as per code IS 456:2000
Fixed beam
constructed at
site with
positive as well
as negative
reinforcement
A view of short
column at site
Fig. 10:- Workers at site during forming work for R.C.C. wall
construction
SLABS
In one way slab load transfer occurs only in one direction. For one way slob aspect
ratio should be more than or equal to 2. In one way slab reinforcement calculated is
provided only in shorter direction and in other direction distribution steel is provided.
Two way slab-
In two way slab load transfer occurs in both the directions. For two way slab aspect
ratio should be less thon 2. In two way slab reinforcement is provided in both shorter
and longer directions and at the supports negative reinforcement is also provided
Fig. 11 Detailing of reinforcement in two way slab
MATERIALS
31.1 Cement
The function of cement is to combine with water and to form cement paste. This
paste first sets i.e. it becomes firms and then hardens due to chemical reaction, called
hydration, between the cement and water. On setting & hardening cement binds the
aggregate together into o stone like hard moss & thus pro strength durability &
water-tighten to the concrete. Quality of cement is based on grade of cement. The
grades of cement are as :-
33 Grades
43 Grades
53 Grades
3.1.2 Aggregate-
Aggregates are small pieces of broken stones in irregular size and shapes Neat
cement is very rarely used in construction works since it is liable to shrink too much
and become cracks on setting Moreover, it will be costly to use neat cement
in construction work. Therefore cement is mixed with some inert strong & durable
hard materials They also reduce the cost of concrete because they are comparative
Fine Aggregate
Coarse Aggregate
The aggregate, which pass through 4.75 mm IS sieve and entirely retain on 75
micron (.075mm) I.S sieve is known as fine aggregate.
The function of using fine aggregate in o concrete mix is to fi up the voids existing
in the coarse aggregate and to obtain a dense and strong concrete with les quantity of
cement and increase the workability of the concrete mix
Coarse aggregate:-
The aggregate, which pass through 75 mm I.S sieve and entirely retain on 4.75 LS
sieve is known as coarse aggregates
3.1.3 Reinforcement
Function of reinforcement-
The main reason of using steel bars in RCC is that, the coefficients of therma
expansion of steel bars and concrete is of approximately equal value.
Fig.19:-Shuttering of
columns
Fig.20:-Columns after
concreting
SECTION-4 QUALITY CONTROL
Quality control is the part of quality management that ensures products and service
comply with requirements. It is a work method that facilitates the measurement of
the quality characteristics of a unit, compares them with the established standards,
and analysis the differences between the results attained and the desired results in
order to make decisions which will correct any differences.
Technical specifications define the type of controls that must be carried out to ensure
the construction works are carried out correctly. They include not only products
materials, but also the execution and completion of the works.
These can be summarized as ignorance, poor materials, poor design, poor detailing
poor workmanship, improper quantity of cement improper concrete mix excess
water, inadequate compaction, substandard forms, inadequate curing, inadequate
cover, poor construction practices, poor supervision and above all .of technical
knowledge.
There should proper compacting of poured concrete because every 1 % void reduce
the strength of concrete by 20 %
There should be proper curing of concrete work for at least 7ho 10days because
it helps in gaining the strength.
Level of formwork should be some throughout the building while costing the slab.
There should be a lab to test the properties of Green Concrete like slump, initial
setting time etc.
compaction.
SECTION-5
CONTRIBUTION
In the retaining wall two sided reinforcement was provided with 16mm steel bars
with 200mm c/c spacing .
Fig.29:-Layout plan
stair case
Fig.30:- Columns reinforceme
reinforcement:-
Fig.31:-Foundation plan
Section
at 2A-2A
Section
at 4A-4A
Joinery Details
Joinery Detail
Ventilation Details
Types of Stairs
1. Straight Stair
2. Dog legged Stair
3. Quarter tur n Stair
4. Open newel Stair
5. Three quarter turn Stair
6. Bifurcated Stair
7. Geometrical Stair
8. Circular Stair
2. D o g legged Stair :
change of direction.
Transit mixer is a piece of equipment that is used for transporting concrete/ mortar or ready mix
material from a concrete batching plant directly to the site where it is to be utilized.
Transit mixer is loaded with dry material and water. The interior of the transit drum is fitted with a
spiral blade. Spiral blade is able to move in two directions. During clockwise Movement drum is
charged with concrete and in counter lock wise direction concrete discharge out from the transit drum.
Concrete mixing drum ensures the liquid state of Materials through rotation of the drum about its own
axis.
PARTS OF TRANSIT MIXER
Transit mixer is utilized for many projects. For example: it delivers concrete for construction of airports,
multi story building, dams, highways, bridges, factories etc. It has various parts named as hopper,
discharge chute, rotating mixing drum and a water tank. Hopper is that part through which transit mixer
is charged with concrete. Water tank with transit mixer is for washing of concrete mixing drum so that
no concrete left with the internal walls.
Discharge chute is utilized during discharging of concrete from the mixer. It ensures the same quality of
concrete as it was at the mixer. Chute guides the concrete directly to the job site.
Sometimes it happens when pouring site is not close enough to the truck, then in such cases
concrete is discharged the conveyor belt. The conveyor belt is about 8-10 meters long that
came along with the modern transit mixer. If it is not enough, then concrete is poured into a temporarily
made concrete box. From here concrete is pumped to site with the help of the
concrete pump. This mostly happens during multi story building construction.
If concrete drops from a height of above one meter without discharge chute then concrete strength
drops because of breaking of internal bonds and this also affects the workability of concrete.
Concrete mixer must be at the site within 90 minutes after charging. This is because concrete final
setting starts which affect the workability as well as strength. If the truck is not on the site within
defined time limits, then concrete hardens in the truck and now for breakup workers need to blast
barrels.
DISCHARGING OF CONCRETE
During delivering of concrete the driver must ensure that the material is discharged at the
requested location. After that wash the concrete drum, discharge chute and stow it safely on the
vehicle. Sometimes it happens, when concrete is more than the customer requirement. In such
cases contact back to the supervisor before returning back the remaining concrete.
Different concrete mix and their purpose use in differentwork:
Mix
Concerttype prepartion Nature of work
M10 1:3:6
PCC CONCRETE(1:4:8)
BRICK MASONARY (1:6)
DPC(1:2:4)
FLOOR MASALA USE (1:4:8)
LINTEL(1:4:8)
RCC SLAB (1:1.5:3) TWO TYPE OF MASAL USE(1:2:4)
PLASTER RATIO(1:6)
Autocad Drawings
Drawings by using autocad and learning more about the scale and printing .
The Architectural and Structural dreawings are the most important thing for the site and design
engineer.
Civil Engineering needs a practical practice in the field and a place to test the theorems taken in
the university and this training gives you the opportunity to do that, which will help in practical
life to be a better engineer.
Civil engineers require some sort of interaction with workers. Whether they are working in a team
situation, or
just asking for advice, engineers have the ability to communicate and work with other people.
Conclusions
The training is an important course because it closes the gap between the scientific and
practical study.
Learning you how to deal with other.
Finding the team work is most important element in every successful project.
Learned you that a civil engineer is capable of lot of work such as supervision, implementation,
and the calculation of quantities and the design engineering apprentice engineer and in the
future can work as a consultant and contractor.
Learning you how to control and manage the site and how behaves when their problems by
taken a professional decisions.
Plans must be clear and easy to use for those who read.
Successful engineer will find the economic design and the project is implemented less time.
Recommendations
The training is an excellent method and very important to each student in the engineering faculity,
because it teaches us what happened in the field .
The engineers in the engineering projects teach you and gave you from their long experience, accept
all our questions, and encourage you to ask.
The training teaches you the important thing that the engineer must learn the regulation and done
the work at time.