Professional Documents
Culture Documents
1. Acknowledgement…………………………………………3
2. Company profile…………………………………………...4
3. Introduction about project………………………………..6
4. Construction Methodology………………………………..7
5. Construction sequence…………………………………….12
6. Excavation………………………………………………….19
7. Excavation equipments…………………………………….22
8. Design consideration……………………………………….22
9. Guide wall (g-wall)………………………………………....23
10. Diaphragm wall (d-wall)………………………………….27
11. D-Wall Construction Sequence…………………………..33
12. Plunge -in column…………………………………………38
13. Grouting……………………………………………………42
14. Cross Passage………………………………………………43
15. QA & QC…………………………………………………..49
**
ACKNOWLEDGEMENT
I would like to express my deepest appreciation to all those who
provided the possibility to complete this report. A special gratitude we
give to our final Project Director, Mr. R.G. Saini, Project Leader, Mr.
Sandeep Singh, IR Manager Mr. S. Hariharan whose contribution in
stimulating suggestions and encouragement, helped us to coordinate our
project especially in writing this report.
Furthermore we would also like to acknowledge with much appreciation
the crucial role of the L&T staff of Munirka Site and Pushpvihar site,
who gave the permission to use all required equipment and the necessary
material to complete training. A special thanks goes to Station Manager
Mr. P.J. Rao, Mr. Mahendra Singh, Mr. Shahrukh and Mr.
Vinayak who guided me to throughout our tenure.
COMPANY PROFILE
Construction methodology
Top-Down Method
The vertical retaining panels (piles, diaphragm walls etc.) along the
perimeter of the excavation to follow are constructed from the surface.
An excavation is initially carried out up to the level of the roof slab of
the structure. Depending upon the excavation depth, a light retaining of
the slopes may be needed.
The roof slab on the excavation bottom is concreted. The slab is
connected with the perimeter retaining and it is supported on it.
The excavation works for the station or the tunnel commence
underneath the roof slab by means of the ramp which has been left at a
certain point. The excavation is executed in phases, while the required
retaining elements (e.g. anchors, struts) are installed gradually.
Upon completion of excavation of the entire trench, works related to
the construction of the permanent bearing structure elements commence.
These elements usually consist in the raft (foundation slab) and the
lateral walls, while in case of a station it is also the construction of the
intermediate floor slabs. In case of diaphragm walls are used as a lateral
retaining means, other permanent walls are not constructed, since the
same diaphragm wall act as a final perimeter structure.
PROCEDURE
The typical construction procedure of top down construction is as
follows
Construct the retaining wall.
Construct piles. Place the steel columns or stanchions where the
piles are constructed.
Proceed to the first stage of excavation.
cast the floor slab of first basement level
Begin to construct the superstructure
Proceed to the second stage of excavation; cast the floor slab of the
second basement level.
Repeat the same procedure till the desired depth is reached
Construct the foundation slab and ground beams, etc. Complete the
basement
keep constructing the superstructure till it gets finished.
The roof slab is constructed, with access openings provided on the slab
for works to proceed downwards. The roof slabs not only provides a
massive support across the .
Advantages:
The advantages of this method consists in the reduced time of extended worksite
occupations and the rate of reinstatement and release of the area for use (vehicular
circulation, squares etc.) and finally the mitigation of disturbance as to the
functions of the city.
Disadvantages:
Its disadvantages are the increased cost and the more complicated construction
procedure.
CONSTRUCTION SEQUENCE FOR TOP DOWN APPROACH AT
MUNIRKA.
EXCAVATION
EQUIPMENTS QUANTITY
Excavator Ex-200 1
Excavator Ex-70 2
Long Arm Stick 1
JCB/Loader 2
Hydraulic Breaker 1
Crane 75 Ton capacity 2
Auto Level/Total Station 1
Dump Truck 10
Steel Bucket 1
GUIDE WALL
Survey works:-
Survey and setting out operations shall be carried out in accordance with
approved drawings. Sufficient reference datum and lines shall be
available and visible on site for reference.
Survey and setting out will be done in the following manner:
Fixing Of Shutters:-
Formwork will be fixed after proper cleaning the inner face and
applying proper de-shuttering oil.
The clear horizontal distance of guide wall i.e. diaphragm wall
width plus 50 mm will be maintained.
Cover blocks will be inserted to maintain specified cover at both
faces of reinforcement cage.
Joints between shutters will be sealed to avoid leakage of
cement slurry.
Shuttering is checked with respect to the dimensions, line,
alignment and verticality.
Placing Of Concrete:-
Approved grade of concrete mix (M20) will be placed.
Placing of concrete and compaction will be taken care.
De-Shuttering:-
De-shuttering will be done after concrete gets set and the area
will be backfilled for the safety purpose.
Curing shall be taken care by site Engineer and randomly
checked by QC personnel.
Construction Sequence :
The diaphragm wall panels basically comprise of :
a) Primary panels
b) Secondary panels
c) Closing panels
The arrangements of panels allows greater flexibility in terms of
commencement and conclusion of panels .
The primary panel is the starting panel, which is cast with 2stop
ends in place. These panels are logistically placed to suit
construction schedule. The panel proceeds in both directions from
the primary panel using secondary panels, which are cast with a
single stop end in a place. The closing panel is the final panel,
which is cast after the removal of both stop-ends.
The panel length is defined as the distance between center lines of
the two stop end (including the water stop).The orientation of the
stop end can therefore be changed without effect to the
reinforcement cage position or size.
DIAPHRAGM WALL EXCAVATION
The diaphragm wall will be located between the guide walls. The
guide wall will be marked with the panel reference no. and Centre
line of stop-end position.
The trenching will be carried out by the grab attached to the
telescopic Kelley who is mounted on hydraulic rigs. The hydraulic
rigs support and operate Kelly bars and the grabs through hydraulic
power of the rig. The swing, leveling, hoisting, closing and
lowering of grab is controlled by the rig.
Once the grab is set up over the designated location, the operator
shall lower the grab onto the ground and commence trenching.
Excavation by grabbing will be done in presence of the poly mud
solution. The density of fresh polymer solution for circulation will
be kept more than the normal density to ensure the stability of the
trench.
The standard panel will be excavated in three main “bites”.
The first “bite” will be excavated to the design toe level. The
second “bite” will be a repeat of the first and finally the third
“bite” will be the center portion.
Grabbing will be start in presence of polymer solution from one
bites of the panel and will excavate up-to founding level i.e. up-to
the required depth of excavation as per the cross section details of
approved drawings.
The rig is then shifted to the second bite of the panel and excavates
up-to the founding level. Then the rig is shifted to the middle bite
of the panel and excavates up-to a required depth. This gives a full
length excavated trench of the panel.
The panel bottom is then cleaned by final grabbing.
Excavated muck mixed with polymer slurry will be kept aside, and
the same will be disposed in the dumping yard at appropriate
designated dumping yard.
When the grab reaches at guide wall level upon exit, a momentary
suspension is recommended to allow the excess mud to drain from
the spoil through the drainage holes of the grab.
The operator then rotates the rig via crane swing and discharges
the spoil either into skips or onto the ground.
An excavation exceeds, poly mud is pumped in to the excavated
trench to ensure that it shall kept full and the level of polymer
slurry must always be above the bottom of the guide wall. During
the course of the excavation, and upon reaching final depth, the
panel depth is verified using a sounding chain and 30 m tape.
Logging of the slurry will be carried out during the excavation to
check the slurry losses.
Checking for the verticality of the trench will be carried out by
KODEN instrument.
Verticality shall be checked for every D-wall panel by KODEN
.during excavation of each panel verticality by panel shall be
checked two times(after 50% excavation and 100% excavation of
D-wall panel for initial five panels subsequently it shall be checked
after 100% excavation for each panel.
The panel of D-wall face to be exposed shall be vertical to within a
tolerance of 1:200, relative to a vertical line projected from the
base of the guide wall.
The ends of the panel shall be vertical to within a tolerance of 1:80.
The stopend with waterstop attached will be lowered in to position.
Disposal of polymer is not required as it can be cleaned in the
trench using polymud.
Excavated soil shall be disposed during night shift at the
designated dumping yard.
Procedure for Rock chiseling in D-wall panel:
Lifting and placing of cage will be done with the help of 2 cranes
and the cage lifter assembly. The cage lifter will be fixed directly
to the lifting hooks of the cage with D’ shackles and slings of the
80/100 MT lifting capacity cranes. The bottom end of the cage
shall be fixed to the second crane (minimum 50 MT capacity
service crane) with two slings will be ensured.
The lifting beam will be designed acc. The calculation provided by
design team will be ensured for fabrications.
The cage will be lifted slowly with 80/100 MT crane operating
both the slings and bottom shall be lifted by the supporting second
crane which will move at a synchronized speed with the movement
of the cage under skilled supervision. When the cage is fully lifted,
the load in service crane shall be freed so that the entire load of the
cage will come on 80/100 MT crane.
After completion of lifting process, the cage will be lowered
slowly in –to the panel and positioned with verifying the line
verticality with plumb-bobs.
Placing of Concrete-
Parameter Value
Slump 150-200 mm
Temperature >5 & <32 degree Celsius
Frequency of cube sampling A set of 3 cubes will be casted
for every 25 cum of concrete
Muck Removal
The bore muck generated from the excavation process shall be shifted to
space available near by the work area using JCB/Excavator.
After completion of piling the working area shall be cleaned for stacking
of plunge column and reinforcement cage.
The bore muck should be shifted to designated dumping yard by leak
proof tipper / truck.
Preparation of Rebar cage
Reinforcement steel Cage Cutting , Bending
After completion of excavation, the reinforcement cage shall be lowered
into trench. The reinforcement shall be cut and bent at steel yard or at
site as per bar bending schedule and cages will be prepared at site over a
level ground. Necessary spacer bars, fixtures, inserts and cover blocks
will be provided along with the reinforcement cage. While cage
fabrication, roller blocks shall be introduced to the outer rebars before
fixing. Cover of 150 mm shall be maintained as per drawing.
Fabrication of Rebar cage:
Based on the approved reinforcement drawing, the bar bending schedule
shall be prepared. The reinforcement is then cut and bent as per bar
bending schedule, and cage is prepared in reinforcement yard at site. The
reinforcement cage shall be tied using the winding wire and wherever
required welding will be done.
The cage shall be fabricated over the fabrication bed consisting either of
steel chairs, channels or wooden sleepers. The clear cover shall be
maintained as per design which is 150mm. lifting hooks and resting
hooks shall be provided as per requirement.
PILE CAGE LOWERING
After cage fabrication, cage lifter will be fixed directly to the lifting
hooks of the cage with shackles and slings of the crane and cage lifting
will be done with help of cranes and cage will be lowered upto desired
depth and will be rested with help of steel beams located at the top of
prefabricated casing to connect the plunge column in order to secure the
plunge column exact position as per drawing. Lifting points and lifting
lugs are designed in such a manner which will not cause distortion of the
cage.
TREMIE LOWERING
After lowering the rebar cage and plunge column, tremie of minimum
200mm dia and length of 1.2m to 3m will be lowered into the trench and
connected while lowering for full depth of trench with the help of
service crane. Concrete funnel/hopper of approx. 1.5cum capacity will
be attached to the top tremie pipes.
GROUTING
Tests on cement
1. NORMAL CONSISTENCY
Object:
Determination of the quantity of water required to produce a
cement paste of standard consistency.
Apparatus:
Vicat apparatus with plunger (10mm in dia.).
Theory:
The standard consistency of a cement paste is defined as that
consistency which will permit the Vicat plunger to
penetrate to a point 5 to 7 mm from the bottom of the Vicat
mould, when the cement paste is tested.
Procedure:
Prepare a paste of weighted quantity of cement (350g) with a weighted
quantity of water, start with 30% water of 350 g of cement taking care
that the time of gauging is not less than 3 minutes and not more than 5
minutes and the gauging shall be completed before any sign of setting
occurs. The gauging time shall be counted from the time of adding the
water to the dry cement until commencing to fill the mould. Fill the
Vicat mould with this paste, the mould resting upon a non-porous plate.
After completely filling the mould, trim off the surface of the paste,
making it in level with the top of the mould. The mould may slightly be
shaken to expel the air. Place the test
block with the mould, together with the non-porous resting plate,
under the rod bearing the plunger (10mm dia.)
lower the plunger gently to touch the surface of the test block and
quickly release, allowing it to penetrate into the paste. This operation
shall carried out immediately after filling the mould. Prepare trial pastes
with varying percentages of water and test as described above until the
amount of water necessary for making the standard consistency as
defined above is obtained. Express the amount of water as a percentage
by weight of the dry cement.
Observation :
1 350 27 94.5 4
2 350 29 101.5 6
3 350 30 105 8
Result:
Normal consistency = 29%
Precautions:
Use clean appliances for gauging. The temperature of cement and water
and that of test room, at the time when the above operations are being
performed, shall be 270C +/- 20C.
The room temperature shall be maintained at 270C +/- 20C.
Sample:
350 g of cement is taken.
Procedure:
Preparation of Test Block :
Prepare a neat cement paste by gauging 350g of cement with 0.85
times the water required to give a paste of standard consistency. The
paste shall be gauged in the manner and under the conditions
prescribed in determination of consistency of standard cement paste.
Start a stopwatch at the instant when water is added to the cement. Fill
the mould with the cement paste gauged as above, the mould resting on
a non-porous plate, fill the mould completely and smooth off the surface
of the paste making it level with the top of the mould. The cement
block thus prepared in the mould is the test block. Use clean
appliances for gauging. The temperature of water and that of the test
room, and the time gauging, shall be 270C +/- 20C. During the test, the
block shall be kept at a temperature of 270C +/- 20C and at not less than
90% relative humidity.
3.SOUNDNESS
Object:
Determination of the Soundness of cement by the Le Chatelier method.
Apparatus:
The apparatus for conducting the test consists of small split
cylinder of spring brass or other suitable metal of 0.5 mm thickness,
forming a mould 30 mm internal diameter and 30 mm high. On either
side of the split mould are attached two indicators with pointed
ends, the distance from these ends to the center of the cylinder being 165
mm. The mould shall be kept in good condition with the Jaws not more
than 0.50 mm apart.
Procedure:
Place the mould on a glass sheet and fill it with cement paste formed by
gauging cement with 0.78 times the water required to give a paste of
standard consistency. The paste shall
be gauged in the manner and under the conditions prescribed in
determination of consistency of standard cement paste, taking care to
keep the edges of the mould gently together while this operation is being
performed. Cover the mould with another piece of glass sheet, place a
small weight on this covering glass sheet and immediately submerge the
whole assembly in water at a temperature of 27degree C +/-
2degree C and keep there for 24 hours. Measure the distance
separating the indicator points. Submerge the moulds again in water at
the temperature prescribed above. Bring the water to boiling, with the
mould
kept submerge, in 25 to 30 minutes, and keep it boiling for three
hours. Remove the mould from the water, allow it to cool and
measure the distance between the indicator points. The difference
between these two measurements represents the expansion of the
cement.
Limits:
Expansion should not be more than 10 mm.
4.FINENESS
Object:
To determine the fineness of cement by dry sieving.
Apparatus:
a) Standard balance with 100 g. weighing capacity.
b) IS: 90 micron sieve confirming to IS : 460 – 1962 and a Brush.
Procedure:
a) Break down any air-set lumps in the cement sample with fingers.
b) Weigh accurately 100 g of the cement and place it on a standard 90
micron IS Sieve.
c) Continuously sieve the sample for 15 minutes.
d) Weigh the residue left after 15 minutes of sieving. This completes the
test.
Result:
The percentage weight of residue over the total sample is reported.
Weight of Sample Retained on the Sieve = 4 gms
% Weight of Residue = 4 %
Total Weight of the Sample =100 gms
Limits:
The percentage residue should not exceed 10%.
Precautions:
Sieving shall be done holding the sieve in both hands and gentle wrist
motion, this will involve no danger of spilling the cement, which
shall be kept well spread out on the screen. More or less
continuous rotation of the sieve shall be carried out throughout
sieving. Washers, shots and slugs shall not be used on the sieve.
The underside of the sieve shall be lightly brushed with a 25 or 40 mm
bristle brush after every five minutes of sieving. Mechanical sieving
devices may be used, but the cement shall not be rejected if it meets the
fineness requirement when tested by the hand method.
Tests On Aggregates
1. IMPACT STRENGTH
Apparatus :
Aggregate testing machine.
Steel measuring cup of dia 75mm & height 50mm.
Cylindrical cup steel dia 102mm &height 50mm.
Balance to an accuracy of 0.1gm.
Oven.
Sieves of sizes -12.5mm,10mm,2.36mm.
Procedure :
Take the sample passing through 12.5 mm sieve and retained in 10 mm
sieve and keep it in oven for 24 hrs. Fill the sample in measuring cup in
three layers for each layer weigh the sample(A).
Transfer the sample to the cylinder steel cup and tamp for 25 times and
fix it in the testing machine. The hammer of the testing machine shall be
allowed to fall freely for 15 times in 15 seconds from a height of 380
mm. Take the sample out of the cup and sieve it through 2.36mm sieve
and weigh the sample (B).
Observation table:
RESULT
SR DESCRIPTION
No 1 2
1 Weight of Dry Aggregate (W1) gms 370 336
2 Weight of Aggregate retained on 2.36mm 315 260
Weight of Aggregate Passing through 2.36mm
3
Sieve ( W2) gms 55 76
4 Impact Value = W2/W1x100 % 14.86 22.62
5 Average Impact Value % 18.74
Calculation :
Aggregate impact value = (b/a)*100
AIV=18.74 %
2. CRUSHING VALUE
Object :
To determine the crushing strength of aggregates when a compressive
load is applied gradually.
Apparatus :
Compression testing machine
Calibrated sieves of size 12.5mm, 10mm, 2.36mm
Crushing mould
Balance readable to an accuracy of 1 gm
Stop watch
Measuring cylinder of dia 11.5 cm and height 18 cm
Tamping rod of 16 mm dia and 45 to 60 cm long
Preparation of test sample :
Take approx. 6.5kg of sample which is passing through 12.5mm and
retained in 10mm sieve.
Now fill the sample in the measuring cylinder in three layers, each layer
being tamped 25 times.
Now level the sample in the measuring cylinder.
Note down the weight of the sample (A).
Test Procedure :
Fix the crushing cylinder in the base plate and put the weighed sample in
the mould in three layers and tamped for 25 strokes in each layer.
Keep the plunger in position on top of the aggregate.
Place the sample in Compression Testing Machine, centre it and apply a
uniform load of 40 t reached in 10 minutes.
Release the load. Take the sample out of the mould and sieve through
2.36mm
The fraction passing through 2.36mm sieve shall be noted down (B).
Calculate the crushing value of the aggregate by using the formula,
B/A*100
Two trials shall be done and the mean value to be reported.
Observation table:
Total weight of sample gms, 2959
Weight of sample passes in 12.5mm sieve and
2425
retained on 10 mm sieve in gms , A
weight of fraction passing the 2.36mm sieve in gms,
534
B
Crushing value = B/A * 100 %
18.05
3.Flakiness Index:-
Object:
To determine the flakiness index(“is the percentage by weight whose
least dimension(thickness) is less than 3/5 th of their mean dimension”) of
the aggregate.
Apparatus/Equipment:
1.Metal gauge-Thickness gauge & Length gauge
2.IS:Sieve of sizes 63,50,40,31.5,25,20,16,12.5,10,6.3 mm
3.Balence of accuracy of 0.1% of the total weight of aggregate.
Test Procedure:
1) The sample shall be sieved through the sieves specified in table:
Dimension of Thickness and
Length gauge
Passing through Thickness gauge Length
IS sieve Retained on IS sieve (mm) gauge
(A) (B) (C) (D)
63 mm 50 mm 33.9 …
50 mm 4o mm 27 81
40 mm 31.5 mm 21.5 64.4
31.5 mm 25 mm 16.95 …
25 mm 20 mm 13.5 40.5
20 mm 16 mm 10.8 32.4
16 mm 12.5 mm 8.55 25.6
12.5 mm 10 mm 6.75 20.2
10 mm 6.3 mm 4.89 14.7
2) At least 200 pieces shall be taken from each fraction and the flaky
samples shall be weighted to an accuracy of 0.1% of the test sample.
3)Calculate the flakiness index
= ( Wt.of flaky samples(passing)/(Wt. of total sample taken for
test))*100
Tests On Concrete
1. COMPRESSIVE STRENGTH
Procedure:
Specimens stored in water shall be tested immediately on removal
from the water and while they are still in the wet condition.
Surface water and grit shall be wiped off the
Specimens and any projecting find removed specimens when received
dry shall be kept in water for 24 hours before they are taken for testing.
The dimensions of the specimens to the nearest 0.2mm and their weight
shall be noted before testing. Placing the specimen in the testing
machine the bearing surface of the testing machine shall be wiped clean
and any loose sand or other material removed from the surface of the
specimen, which are to
be in contact with the compression platens. In the case of cubes,
the specimen shall be placed in the machine in such a manner that the
load shall be applied to opposite sides of the cubes as cast, that is,
not to the top and bottom. The axis of the specimen shall be
carefully aligned with the center of thrust of the spherically seated
platen. No packing
shall be used between the faces of the test specimen and the steel
platen of the testing machine. As the spherically seated block is
brought to bear on the specimen the movable
portion shall be rotated gently by hand so that uniform seating may be
obtained. The load shall be applied without shock and increased
continuously at a rate of approximately 140 kg/cm2/min. until the
resistance of the specimen to the increasing load breaks down and no
grater load can be sustained. The maximum load applied to the specimen
shall then be recorded and the appearance of the concrete and any
unusual features in the type of failure shall be noted.
Object:
This method of test specifies the procedure to be adopted, either
in the laboratory or during the progress of work in the field, for
determining, by the slump test, the consistency of concrete.
Apparatus:
a) Mould: the mould for the test specimen shall be in the form of the
frustum of a cone having the following internal dimensions:
Dimensions cm:-
Bottom diameter:- 20
Top diameter:-. 10
Height:- 30