Weekly Activity Report

Mohammed Fasil
NIMFRA ARCHITECTS
DIALYSIS CENTER: KARIYAD

Flooring – First Floor finished


1
Flooring – Stair room

2
Flooring – Ground Floor

3
Flooring - Stair case

4
STP – Plastering of interior walls finished. STP works will start on Wednesday
5
PCC – First floor toilets
6
RO Platform – RO works will start today
7
Notes:-
 Pending works
o All site house keeping
o Boundary wall
o Handrail
o Industrial works like truss and the design works in the stair room
o Stretched Glass
o Aluminium fabrication works
o Cladding
o Ramp

8
RESIDENCE: FAISAL MAHE

Plastering – Living room


9
Plastering – Main Hall

10
Setting out – Garage
11
Concrete – Window seating
12
Belt concrete – Double Wall

13
14
15
16
Notes:-
 Stair case – Shuttering works have not yet started
 Garage area – Setting out done. Excavation for footing will start today
 Plastering interior walls– remaining areas
o Dining room
o Family living
o Main hall – on going
o Living room – on going
 Pergola in courtyard – not started yet
 Parapet works – on going