Mohammed Fasil
NIMFRA ARCHITECTS
DIALYSIS CENTER: KARIYAD
2
Flooring – Ground Floor
3
Flooring - Stair case
4
STP – Plastering of interior walls finished. STP works will start on Wednesday
5
PCC – First floor toilets
6
RO Platform – RO works will start today
7
Notes:-
Pending works
o All site house keeping
o Boundary wall
o Handrail
o Industrial works like truss and the design works in the stair room
o Stretched Glass
o Aluminium fabrication works
o Cladding
o Ramp
8
RESIDENCE: FAISAL MAHE
10
Setting out – Garage
11
Concrete – Window seating
12
Belt concrete – Double Wall
13
14
15
16
Notes:-
Stair case – Shuttering works have not yet started
Garage area – Setting out done. Excavation for footing will start today
Plastering interior walls– remaining areas
o Dining room
o Family living
o Main hall – on going
o Living room – on going
Pergola in courtyard – not started yet
Parapet works – on going
17