Work Progress Report

As on Dated: 14.12.23

S. No. Proposed Work Status Remarks


01 Landscaping from temple to store building (North One side Completed.
side of plant main road).
02 Landscaping from store building to old gate (West Completed.
side).
03 Landscaping from West gate to South west end. Incomplete.
04 South west end to south east end (Crusher Incomplete.
limestone yard).
05 West gate of factory closure. Completed.
06 Corporate Office setup 2nd Floor. Completed only furniture work to
be done.
07 Corporate Office setup 3rd Floor. This will be started after
completion of work on 2nd Floor.

08 Construction of Directors Residence. Structure, brick work and indoor


plastering are completed.
Tiling, sanitary work & Interior
design work are to be done.
09 Renovation of Guest House. Not Started.

10 Factory Main Gate Modification. Not Started.


11 Boundary wall. Plaster completed lighting &
painting work to be done.
12 Sculpture park factory area. RCC work completed. Sculpture
fixing and finishing work to be
done.
13 Car parking beside Temple. Yet to be started.
14 Residence colony area walkway & Road. Completed except director
residence area.
15 Landscaping and play ground work at colony side. Remaining beside colony.