Dr.Sathyamoorthy Project -Work Schedule - for completion

Date of
S.No. Nature of Work Remarks
completion

1 Inner wall plastering to be completed 24.11.18 completed

2 External wall plastering work to be completed 15.12.18 completed

Ground floor toilet wall tiles and General flooring tile


3 15.12.18 completed
laying work

General
First floor toilet wall tiles and General flooring tile laying
4 22.12.18 flooring
work
completed

5 Staircase Granite laying work 22.1.19 Progress

6 Elevation - Natural stone tiles laying work 22.1.19

7 Drainage and chamber work 30.1.19

8 Inner wall painting work completion 15.2.19

9 Terrace floor Weathering course work 30.12.18 completed

10 External wall painting work completion 28.2.19

11 Compound wall construction 15.2.19