WEEKLY REVIEW – 20.03.

2020
H 134 PROJECT SCHEDULE
Sl.
Description Start Date Finish Date Remarks
No
PROJECT START DATE / EARTH WORK
1 17-Jun-19
EXCAVATION

2 FOUNDATION 24-Jun-19 24-Jul-19 Completed

3 STRUCTURE
ROOF
Stilt floor 25-Jul-19 13-Aug-19 Completed
First floor 14-Aug-19 2-Sep-19 Completed
Second floor 3-Sep-19 22-Sep-19 Completed
Third floor 23-Sep-19 12-Oct-19 Completed
Fourth Floor 13-Oct-19 1-Nov-19 Completed

4 SUB STRUCTURE
POROTHERM BLOCK WORK &
BRICKWORK
First floor 5-Oct-19 20-Oct-19 Completed
Second floor 21-Oct-19 4-Nov-19 Completed
Third floor 5-Nov-19 19-Nov-19 Completed
Fourth Floor 20-Nov-19 4-Dec-19 Completed

5 CEILING & INTERNAL PLASTERING


First floor 5-Nov-19 19-Nov-19 Completed
Second floor 20-Nov-19 4-Dec-19 Completed
Third floor 5-Dec-19 19-Dec-19 Completed
Fourth Floor 20-Dec-19 3-Jan-20 Progress
H 134 PROJECT SCHEDULE
Sl.
Description Start Date Finish Date Remarks
No
6 WATERPROOFING 20-Dec-19 20-Jan-20 Completed

7 INTERNAL PLUMBING WORK 25-Dec-19 25-Jan-20 Progress

8 INTERNAL PAINTING 30-Dec-19 30-Jan-20 Putty work progress

EXTERNAL PLASTERING & ELEVATION


9 20-Dec-19 30-Jan-20 Completed
WORK

10 TOILET WALL DADO 25-Jan-20 10-Feb-20 Progress

11 GENERAL FLOORING TILE 30-Jan-20 15-Feb-20 Progress

12 ELECTRICAL WORK 5-Feb-20 5-Mar-20

PAVING BLOCK LAYING,COMPOUND


Compound wall & outer
13 WALL WORKS, FINAL PAINTING AND 25-Feb-20 25-Mar-20
chamber work progress
FINISHING WORKS

14 HANDING OVER 5-Apr-20