H 134 PROJECT SCHEDULE
Sl.
Description Start Date Finish Date Remarks
No
PROJECT START DATE / EARTH WORK
1 17-Jun-19
EXCAVATION
3 STRUCTURE
ROOF
Stilt floor 25-Jul-19 13-Aug-19 Completed
First floor 14-Aug-19 2-Sep-19 Completed
Second floor 3-Sep-19 22-Sep-19 Completed
Third floor 23-Sep-19 12-Oct-19 Completed
Fourth Floor 13-Oct-19 1-Nov-19 Completed
4 SUB STRUCTURE
POROTHERM BLOCK WORK &
BRICKWORK
First floor 5-Oct-19 20-Oct-19 Completed
Second floor 21-Oct-19 4-Nov-19 Completed
Third floor 5-Nov-19 19-Nov-19 Completed
Fourth Floor 20-Nov-19 4-Dec-19 Completed