Commencement End Commencement End

Project Kick off 15/Nov/19 - 15/Nov/19 -


Site Data & Geo Tech Reports Completed Completed Completed Completed
Concept Engineering 16/Nov/19 20/Nov/19 16/Nov/19 20/Nov/19
Master Plan - 28/Nov/19 - 28/Nov/19
Concept Design review 29/Nov/19 30/Nov/19 29/Nov/19 30/Nov/19
Detailed design & Approval 1/Dec/19 28/Dec/19 1/Dec/19 28/Dec/19
Work commencement at site 1/Jan/20 - 1/Jan/20 -
Warehouse works - - - -
Substructure works 1/Jan/20 20/Feb/20 1/Jan/20 11/Mar/20
Warehouse inside filling 1/Feb/20 20/Feb/20 1/Feb/20 11/Mar/20
PEB Erection 29/Jan/20 28/Apr/20 29/Jan/20 28/May/20
Fire Fighting works 19/Feb/20 19/May/20 19/Feb/20 18/Jun/20
Flooring 4/Mar/20 2/Jun/20 14/Apr/20 3/Jul/20
First Dry Access (50% area) - 30/Apr/20 - 15/Jun/20
Warehouse Completion - 20/Jul/20 - 20/Sep/20
Boundary wall 1/Jan/20 31/Mar/20 With SC Area With SC Area
External Development 1/Mar/20 15/Jul/20 1/Apr/20 15/Sep/20
Fire Fighting Network & Pump Room 1/Mar/20 30/May/20 1/Apr/20 30/Jul/20
HT & LT Electrical Works 16/Mar/20 30/May/20 16/Apr/20 25/Jul/20
Overall Project Handover - 31/Jul/20 - 30/Sep/20