The document outlines schedules of work for various projects including an athletic stadium, aquatic center, government building, athletes village, and residences. It lists activities and their committed start and finish dates for things like asphalt laying, roof covering, bleacher installation, track laying, structural steel phases, excavation, and other construction tasks. However, many of the dates are missing or incomplete.
The document outlines schedules of work for various projects including an athletic stadium, aquatic center, government building, athletes village, and residences. It lists activities and their committed start and finish dates for things like asphalt laying, roof covering, bleacher installation, track laying, structural steel phases, excavation, and other construction tasks. However, many of the dates are missing or incomplete.
The document outlines schedules of work for various projects including an athletic stadium, aquatic center, government building, athletes village, and residences. It lists activities and their committed start and finish dates for things like asphalt laying, roof covering, bleacher installation, track laying, structural steel phases, excavation, and other construction tasks. However, many of the dates are missing or incomplete.
Asphalt Laying Feb. 15/March 31, 2018 Roof Cover (Finish) June 2019 Lower Bleacher Complete Upper Bleacher (Finish) April 2019 Bleacher Seats March 3, 209 (Delivery) Track Laying - Commissioning and Testing July 2019 SCHEDULE OF WORK FOR AQUATIC CENTER
Activity Committed Date of (Start/Finish)
Structural Steel (Phase 1) GL 11 to 8 January 30 – Feb 19 Phase 2 GL 8 to 4 Feb 20 – March 6 Phase 3 GL 4 to 1 March 7 – March 21 Removal of Tempacil End of February Excavation for Pools SCHEDULE OF WORK FOR GOVERNMENT BUILDING