SCHEDULE OF WORK FOR ATHLETIC STADIUM

Activity Committed Date of (Start/Finish)


Asphalt Laying Feb. 15/March 31, 2018
Roof Cover (Finish) June 2019
Lower Bleacher Complete
Upper Bleacher (Finish) April 2019
Bleacher Seats March 3, 209 (Delivery)
Track Laying -
Commissioning and Testing July 2019
SCHEDULE OF WORK FOR AQUATIC CENTER

Activity Committed Date of (Start/Finish)


Structural Steel (Phase 1) GL 11 to 8 January 30 – Feb 19
Phase 2 GL 8 to 4 Feb 20 – March 6
Phase 3 GL 4 to 1 March 7 – March 21
Removal of Tempacil End of February
Excavation for Pools
SCHEDULE OF WORK FOR GOVERNMENT BUILDING

Activity Committed Date of (Start/Finish)


SCHEDULE OF WORK FOR ATHLETES VILLAGE

Activity Committed Date of (Start/Finish)


SCHEDULE OF WORK FOR THE RESIDENCES

Activity Committed Date of (Start/Finish)