DAILY ACCOMPLISHMENT REPORT

PROJECT LOCATION: Royale Estates (Tagaytay City)


NAME IN CHARGE: Engr. Errold Paul Gagarin
DISCIPLINE: Civil Engineer & Sanitary Engineer
DATE: Saturday, July 1, 2023

NO. OF UNIT
WORK ACTIVITY DATE START CATEGORIZATION STATUS REMARKS
WORKERS
BLK LOT

Concrete pouring (1 column), installation of


formworks for stairs (landing to second
1 (mason), 3
43 32 floor), installation of steel rebars for stairs 6/21/2023 Turnover Unit On going -
(helper)
(landing to second floor), dismantling of
formworks for concrete poured columns.

NOTE/S: 1. Work activities are limited due to unavailability of workers (absences).

PREPARED BY:

Engr. Errold Paul B. Gagarin