Jun 29-23 DR-TGT
Jun 29-23 DR-TGT
NO. OF UNIT
WORK ACTIVITY DATE START CATEGORIZATION STATUS REMARKS
WORKERS
BLK LOT
Work progress
are slowed due
to inavailability
Formworks installation for stairs
1 (mason), 3 of necessary
43 32 (continuation), concrete pouring (stairs 6/21/2023 Turnover Unit On going
(helper) materials, also
steps), inspection of electrical rough-ins.
to include the
inavailability of
workers.
NOTE/S: 1. Work activities are limited due to unavailability of necessary materials; 2. Clearing & rearranging of leftover materials
are necessary to ensure complete access within the site.