You are on page 1of 7

J Fail. Anal. and Preven.

(2015) 15:474–479
DOI 10.1007/s11668-015-9977-9

CAS E HISTORY—PE E R-R EVI EWE D

Investigation on Failure of a Drilling Rig Mast Structure


. . .
D. Ghosh H. Roy S. Ray A. K. Shukla

Submitted: 27 November 2014 / in revised form: 16 April 2015 / Published online: 24 June 2015
ASM International 2015

Abstract A drilling rig that was used for exploration of material, fabrication procedure, or operational error in
gaseous fuels was inspected. During its operation the rig handling. This investigation primarily deals with the
mast suddenly collapsed and the structure got twisted from assessment of probable cause of damage of an in-service
the middle. The failure investigation was carried out to drilling rig mast structure for exploration of methane gas
determine the probable causes of failure in the rig. Esti- from a coal bed. Photographs of mast structure before and
mation of mechanical properties, optical microscopic after failure are shown in Fig. 1. There are few available
analysis along with scanning electron microscopy exami- reports on failure analysis of mast structures [1–5], how-
nations were necessary supplements to this investigation. ever, failure of these types of drilling rig mast structures
Detailed stress analysis of the structure for different con- are very rare as they are too expensive (millions of Euros)
ditions of loads and anchors was examined. It was and are handled with utmost care. It is evident from Fig. 1a
ultimately concluded that non-functioning of record-o- that during operation, the mast structure was anchored with
meter was responsible for rapid increase in operating load cables and were fixed at different ends such that resultant
and one or more cables/anchoring points did not have of the stresses were concentrated on the main structure.
sufficient strength to withstand the operating load. The The complete mast structure was inclined toward the
anchoring cable broke with a jerk and the mast structure borehole at an angle of 4L. Four cables, identified (RTG1,
collapsed under its weight. RTG2, FTG1, and FTG2) from the rear and front top ends
of the mast were anchored at four points on the ground.
Keywords Defect analysis Failure analysis These points were located at equal angles with symmetry
Fractography Structural Integrity along the line joining the borehole point and center of the
winch drum. All the cables were positioned at angle of 45L
in the vertical plane. There were two cables (RTC1 and
Introduction RTC2) connecting the top end of the mast to the anchors
on the carrier. Two more cables (RMC1 and RMC2) are
In spite of the best efforts of design engineers and material connected between the middle portion of the mast and two
scientists, engineering components fail in service. Occur- anchor points on the carrier. Two cables (RMG1 and
rence of failure of engineering components may lead to RMG2) are anchored to the ground and connected to the
serious consequences such as significant financial loss, middle part of the mast. The anchor points on the ground
environmental contamination, and even loss of life. In the have also been located in similar manner as of the cables,
event of a failure, it is sometimes essential to investigate used to anchor the top of the mast. Other cables, which do
the root cause of failure in terms of design, quality of not share the load on the mast structure, have not been
considered in the analysis.
While in operation, the drilling pipe jammed at a level
D. Ghosh (&) H. Roy S. Ray A. K. Shukla NDT &
Metallurgy Group, CSIR-Central Mechanical
of 1175 m, which was slowly brought to a level of 1153 m.
Engineering Research Institute, Durgapur 713209, India Thereafter, a jarring action was followed with no success.
e-mail: dghosh@cmeri.res.in; dbs1012000@gmail.com Hence, an additional pull on the cable was applied to

123
J Fail. Anal. and Preven. (2015) 15:474–479 475

release it. During this operation, the rig mast suddenly Investigations
collapsed and the structure twisted from the middle (Fig.
1b). Circumstantial evidences revealed that the record-o- Visual Examination and Preliminary Findings
graph was non-functional at that time, which therefore
could not record the level of loading applied at the moment Visual examination of the failed mast structure was carried
of failure. The root cause of the failure of the different out and it revealed the following:
engineering components has been conducted to prevent the
repetitive failure and at the same time remedial measures (i) The maximum damage and bending/twisting were
are also highlighted to avoid similar failure in near future localized near to middle portion of the mast
structure (Fig. 2).
[6–20].
(ii) Plastic deformation in the form of bending and
The basic objective of this work was to identify the root
twisting of the failed structure was evident as shown
cause of the failure and to ascertain whether it was due to in the Fig. 3.
problem related to materials or the failure was deficiencies
(iii) A number of cracks open to the surface of various
in the design, fabrication, installation, error in functioning,
magnitudes and direction were present at many of
etc. Apart from preliminary visual examination, chemical
the welded joints away from the damaged locations
analysis of the chain link material, magnetic particle
of the mast structure (Fig. 4). It is possible that
examination of welded joints, mechanical testing, fracto-
appropriate non-destructive testing was not carried
graphic analysis, and detailed finite element analysis using
out during its scheduled inspection.
ANSYS software package form the different steps of this
investigation in order to identify the probable cause of (iv) There was inadequate reporting of previous NDT
inspections.
failure of the mast structure.
(v) The stress record-o-graph was not functioning
properly during the event of failure.
(a)

Cables Cables Material Characterization

The failed material is subjected to analyze chemically by


Cables Cables spectrometer (Model: Q4 TASMAN, Bruker, Germany). The
results of the analysis of the materials are provided in Table 1.
The chemical analysis confirmed to the specifi-cation ASTM-
Carrier 595 grade steel [21]. Microstructural analysis was carried out
Carrier from the samples extracted from region shown in Fig. 3.
Tensile tests were carried out as per ASTM standard E-8m
[22]. Flat specimens of 25 mm gage length and 5 mm
thickness were fabricated from the as

(b)

Fig. 1 Drilling rig mast structure during (a) in-service condition and Fig. 2 The middle portion of the mast structure is the region with
(b) after collapse maximum damage

123
476 J Fail. Anal. and Preven. (2015) 15:474–479

Materials twisted due to plastic


the specimens was taken at 10 kgf load and is reported in
deformation
Table 2. The obtained values (mechanical properties) of the
mast structure confirms to the specification of ASTM
Location for sample
removal for material 595/572A, though the UTS values (528 Mpa) are on the
characterization higher side in comparison to the specified value (450
Mpa). However, ASTM 595/572A grade materials are
recom-mended for mast structure [6]. The fracture surface
was saw cut and carefully extracted from the failed mast
structure (from location marked in Fig. 3). The fracture
surface was subsequently cleaned by ultrasonic cleaner
(acetone is used as solvent) followed by surface
replication. It is to be noted that the fracture surface being
exposed to open atmosphere for a long time resulted in the
formation of severe corroded layer on its outer surface. An
Fig. 3 Deformed and twisted angle near the middle portion of the
attempt was made to remove the corroded layer using HCL
structure as cleaning media. The fracture surface was then examined
using scanning electron microscope (SEM), S-3000N,
Hitachi Ltd, Japan (Figs. 5, 6).

Results and Discussion

Metallographic analysis of a damaged and undamaged


region revealed a microstructure consisting of pearlite and
widmanstatten ferrite (Fig. 5). There was no abnormal
material degradation in the damaged location of the failed
mast structure. Thorough examination of the fracture sur-
faces (Fig. 6) revealed a texture indicative of cleavage-type
cracking with river line patterns at places along with duc-
tile voids around the vicinity. The crack initiation zone was
observed in Fig. 6b. It can be concluded from the SEM
image that the failure was due to application of the stress
that exceeded the strength of the part. The sudden jerk
during the collapse of the mast structure showed that the
material had undergone high rate of loading and then
plastically collapsed. Some type of steels are stain rate
dependent and may exhibit cleavage-type cracking under
high strain rate, while exhibiting dimple rupture under
slower strain rate. The evidence of ample plastic defor-
mation in the failed component is shown in Fig. 3.

Structural Analysis Using FEM

In order to identify probable cause of failure of the mast


structure, simulated analysis of the structure for different
conditions of loads and anchors was examined. The anal-ysis
Fig. 4 Magnetic particle examination revealed presence of fine cracks was carried out by finite element method (FEM). The FEM is
in the weld joints at many location of undamaged part of the mast a numerical method, being used extensively in the areas of
structure Solid Mechanics, Heat Transfer, Fluid Mechanics, Aero-
elasticity, coupled field analysis etc. [23]. The method is
received failed sample. The tensile properties, yield based on discretization of a structure in finite number of inter-
strength (YS), ultimate tensile strength (UTS), and per- connected elements. The physical behavior of the field
centage elongation are shown in Table 2. The hardness of variables of the elements, viz., displacement,

123
J Fail. Anal. and Preven. (2015) 15:474–479 477
Table 1 Chemical analysis (weight percent) of the samples extracted from the failed mast structure

Element C Mn Si S P
Weight percent 0.21 0.85 0.027 0.022 0.012
Specified ranges 0.15–0.25 0.30–0.90 0.035 max 0.035 max 0.060 max

Table 2 Observed tensile properties along with average hardness value

Sample No. Y.S, MPa U.T.S, MPa % Elongation Avg. hardness, 10 Kgf, HV
1 338 528 31 132
2 340 528 28
3 324 527 27.5

Fig. 5 Microstructures of the (a) undamaged part and (b) damaged part of the mast structure

slope (degree of freedom) in case of structural analysis, are All the configurations have been analyzed for 160 T load
defined in terms of variables at the nodes by suitable on the mast structure.
interpolation function. The elastic characteristics of an The probable total cases have been considered are as
element is defined from the geometrical and material follows:
properties of the element and expressed in the form of a
(i) Case-1: The complete structure before failure with
matrix, called element stiffness matrix. The stiffness
all the anchored cables in positions and 160 T load
matrices of the elements are assembled suitably to form the on the structure.
global stiffness matrix of the complete assembly. Subse-
(ii) Case-2: The complete structure without one
quently, the simulated loads and the support conditions are
anchored cable connecting top of the mast and
applied and the resulting matrix is solved to obtain the anchoring point (RTG1).
unknown nodal variables, loads, and reactions at supports.
(iii) Case-3: The complete structure without one
Different conditions have been used to simulate possible
anchored cable connecting top of the mast and
failure causes. Examining different possibilities of failures, anchoring point (RTC1).
different structural conditions, which may lead to final
(iv) Case-4: The complete structure without one
failure, have also been examined. Five different configu-
anchored cable connecting the middle of the mast
rations have been analyzed to examine the possibility of and anchoring point (RMC1).
failure of any member of the structure or anchoring cable.

123
478 J Fail. Anal. and Preven. (2015) 15:474–479

Fig. 8 Simulated FEM of the


deformed mast structure without
cables

(v) Case-5: The complete structure without one


anchored cable connecting the middle of the mast
and one anchoring cable (RMG1).
Depending on the results, subsequent load cases have been
defined for examination.
The physical properties or real properties of the ele-
ments, such as plate thickness, cross-sectional area, and
moment of inertia of different members have been calcu-
lated from the measured dimensions of the corresponding
structural members and cables.
Fig. 6 Fracture surface showing (a) river line and high magnification
image showing (b) river lines and ductile voids along crack initiation The following material properties have been used for
zone different structural members:

Fig. 7 Finite element models


developed for stress analysis

123
J Fail. Anal. and Preven. (2015) 15:474–479 479

Modulus of elasticity, E = 210,000 MPa; mast structure was beyond the yield strength and mast
Poisson’s ratio = 0.3; deformed plastically failing under its own weight.
Yield stress = 334 MPa. The finite element model
developed for stress analysis is shown in Fig. 7.
References
The detailed FEM analyses reveal the following:
The maximum deformation of the structure, maximum 1. G. Das, S. Chakrabarty, A.K. Dutta, S.K. Das, K.K. Gupta, R.N.
cable tensions and maximum equivalent von Mises stress, Ghosh, Failure analysis of a high mast lamp post. Eng. Fail.
is given by the relation, Anal. 13, 1153–1158 (2006)
2. J.H. Lee, W.D. You, J.W. Kim, J.H. Choi, B.H. Choe, Failure
p p 2 2 2 2 analysis of a mast column. Eng. Fail. Anal. 10, 317–323 (2003)
req ¼ 1= 2 ðrx ryÞ þ ðry rzÞ þ ðrz rxÞ þ ð6s xy þ 3. W.P. Sung, J.C.M. Kao, R. Chen, Failure analysis of Q345 steel
2 2 structures on port cranes. Appl. Mech. Mater. 401–413, 844–847
6s zx þ 6s yzÞ: (2013)
ðEq 1Þ 4. F. Frendo, Analysis of the catastrophic failure of a dockside
crane jib. Eng. Fail. Anal. 31, 394–411 (2013)
Here rx, ry, and rz represent normal stresses and s xy, szx,
5. E.S. Kim, S.K. Choi, Failure analysis of connecting bolts in
and syz represent shear stresses. collapsed tower crane. Fatigue Fract. Eng. Mater. Struct 36, 228–
From simulated studies under different conditions of the 241 (2012)
mast, it was observed that with all ropes in proper 6. J. Swaminathan, K. Guguloth, M. Gunjan, P.K. Roy, R.N. Ghosh,
Eng. Fail. Anal. 15, 311–316 (2008)
anchored condition, the mast would not have failed even 7. D. Ghosh, H. Roy, A.K. Shukla, Investigation of probable cause of a
with enhanced load or jerks. Therefore, initiation of premature cracking of down comer nozzle of heat recovery steam
deformation must have started owing to failure of some generator (HRSG). J. Fail. Anal. Prev. 9(6), 517–521 (2009)
cables. There-fore, the sequence of operations, conditions 8. D. Ghosh, H. Roy, S. Ray, A.K. Shukla, High temperature corro-sion
failure of a secondary superheater tube in thermal power plant boiler.
of the mast, anchored cables and loads, which have led to High Temp. Mater. Process. 28(1–2), 109–114 (2011)
failure of the mast, is concluded as follows: 9. G. Das, S.G. Chowdhury, A.K. Ray, S. Das, D.K. Bhattacharya,
Eng. Fail. Anal. 9, 563–570 (2002)
(a) One of the anchoring cables of the top of the mast 10. H. Roy, D. Ghosh, A.C. Pankaj, A.K. Shukla, J. Basu, A case
has failed due to either improper anchoring or poor study on the premature failure of a cooling water pump shaft. Int.
service condition of the cable. J. Manuf. Sci. Prod. 9(1–2), 99–106 (2011)
11. H. Roy, A. Saha, D. Ghosh, S. Roy, A.K. Shukla, Failure
(b) Excessive load on the mast due to jerks has led to
investigation of platen superheater outlet header. J. Mech. Behav.
failure of the anchoring cables of the top of the mast. Mater. 19(6), 373–382 (2011)
(c) Without anchors at the top, stress near the intercon- 12. D. Ghosh, S. Ray, H. Roy, Failure investigation of high tem-
nection between the lower and upper parts of the perature Stud. J. Fail. Anal. Prev. 14(1), 17–20 (2014)
mast structure goes beyond yield strength and the 13. S.G. Chowdhury, P. Kumar, S.K. Das, D.K. Bhattacharyya, N.
Parida, Failure analysis of high temperature studs. Eng. Fail.
mast deforms plastically. Anal. 8, 521–528 (2001)
(d) With higher inclination of the mast, effective 14. D. Ghosh, S. Ray, H. Roy, N. Mandal and A.K. Shukla, High
bending load on the structure increases substantially temperature graphitization failure of primary superheater tube.
High Temp. Mater. Process. doi:10.1515/htmp-2014-0137
and bending continues further.
15. D. Ghosh, H. Roy, A. Mondal, failure investigation of condensate
(e) Finally, even in absence of load tension, because of pump shaft. J. Fail. Anal. Prev. 14(4), 450–453 (2014)
self weight, the mast fails as shown in Fig. 8, similar 16. W. Muhannad, K.M. Deen, Failure analysis of water pump shaft.
to Fig. 1b (actual failure). J. Fail. Anal. Prev. 10, 161–166 (2010)
17. D. Ghosh, S. Ray, H. Roy and A.K. Shukla, Investigation into
cause of high temperature failure of boiler superheater tube. High
Temp. Mater. Process. doi:10.1515/htmp-2014-0018
Conclusions
18. A.M. Lancha, M. Serrano, D. Gomez, Bricane. Eng. Fail. Anal.
8, 271291 (2001)
Based on the findings of this investigation, it is concluded that 19. H. Roy, P. Sharma, D. Ghosh and A.K. Shukla, Corrosion failure
non-functioning record-o-meter did not provide ade-quate of in-service economizer tube. J. Fail. Anal. Prev. doi:10.1007/
s11668-014-9848-9
warning that the load applied to the mast was applied at the 20. D. Ghosh, S. Ray, A. Mondal, H. Roy, Failure investigation of
dangerous levels. This ultimately led to rapid increase in radiant platen superheater tube of thermal power plant boiler.
operating load. One or more of the cables or the anchoring High Temp. Mater. Process. doi:10.1515/htmp-2013-0128.
21. ASM, ASM Handbook, vol. 1 (ASM, Metals Park, 1993)
points did not have sufficient strength to withstand the rapid
22. ASTM standard E-8M, Standard Test Methods for Tension
increase in operating load exerted due to the sudden addi- Testing of Metallic Materials, vol. 03.01, 2011
tional pull. One or two anchoring cables at the top failed first, 23. T.R. Chandrapatla, A.D. Belegundu, Introduction to Finite Ele-
thereafter stress between the lower and upper parts of the ments in Engineering. Pearson Higher Ed USA, 2011

123
Reproduced with permission of the copyright owner. Further reproduction prohibited
without permission.

You might also like