You are on page 1of 6

J Fail. Anal. and Preven.

(2015) 15:474–479
DOI 10.1007/s11668-015-9977-9

CASE HISTORY—PEER-REVIEWED

Investigation on Failure of a Drilling Rig Mast Structure


D. Ghosh . H. Roy . S. Ray . A. K. Shukla

Submitted: 27 November 2014 / in revised form: 16 April 2015 / Published online: 24 June 2015
Ó ASM International 2015

Abstract A drilling rig that was used for exploration of material, fabrication procedure, or operational error in
gaseous fuels was inspected. During its operation the rig handling. This investigation primarily deals with the
mast suddenly collapsed and the structure got twisted from assessment of probable cause of damage of an in-service
the middle. The failure investigation was carried out to drilling rig mast structure for exploration of methane gas
determine the probable causes of failure in the rig. Esti- from a coal bed. Photographs of mast structure before and
mation of mechanical properties, optical microscopic after failure are shown in Fig. 1. There are few available
analysis along with scanning electron microscopy exami- reports on failure analysis of mast structures [1–5], how-
nations were necessary supplements to this investigation. ever, failure of these types of drilling rig mast structures
Detailed stress analysis of the structure for different con- are very rare as they are too expensive (millions of Euros)
ditions of loads and anchors was examined. It was and are handled with utmost care. It is evident from Fig. 1a
ultimately concluded that non-functioning of record-o- that during operation, the mast structure was anchored with
meter was responsible for rapid increase in operating load cables and were fixed at different ends such that resultant
and one or more cables/anchoring points did not have of the stresses were concentrated on the main structure.
sufficient strength to withstand the operating load. The The complete mast structure was inclined toward the
anchoring cable broke with a jerk and the mast structure borehole at an angle of 4°. Four cables, identified (RTG1,
collapsed under its weight. RTG2, FTG1, and FTG2) from the rear and front top ends
of the mast were anchored at four points on the ground.
Keywords Defect analysis  Failure analysis  These points were located at equal angles with symmetry
Fractography  Structural Integrity along the line joining the borehole point and center of the
winch drum. All the cables were positioned at angle of 45°
in the vertical plane. There were two cables (RTC1 and
Introduction RTC2) connecting the top end of the mast to the anchors on
the carrier. Two more cables (RMC1 and RMC2) are
In spite of the best efforts of design engineers and material connected between the middle portion of the mast and two
scientists, engineering components fail in service. Occur- anchor points on the carrier. Two cables (RMG1 and
rence of failure of engineering components may lead to RMG2) are anchored to the ground and connected to the
serious consequences such as significant financial loss, middle part of the mast. The anchor points on the ground
environmental contamination, and even loss of life. In the have also been located in similar manner as of the cables,
event of a failure, it is sometimes essential to investigate used to anchor the top of the mast. Other cables, which do
the root cause of failure in terms of design, quality of not share the load on the mast structure, have not been
considered in the analysis.
While in operation, the drilling pipe jammed at a level
D. Ghosh (&)  H. Roy  S. Ray  A. K. Shukla
of 1175 m, which was slowly brought to a level of 1153 m.
NDT & Metallurgy Group, CSIR-Central Mechanical
Engineering Research Institute, Durgapur 713209, India Thereafter, a jarring action was followed with no success.
e-mail: dghosh@cmeri.res.in; dbs1012000@gmail.com Hence, an additional pull on the cable was applied to

123
J Fail. Anal. and Preven. (2015) 15:474–479 475

release it. During this operation, the rig mast suddenly Investigations
collapsed and the structure twisted from the middle
(Fig. 1b). Circumstantial evidences revealed that the Visual Examination and Preliminary Findings
record-o-graph was non-functional at that time, which
therefore could not record the level of loading applied at Visual examination of the failed mast structure was carried
the moment of failure. The root cause of the failure of the out and it revealed the following:
different engineering components has been conducted to
(i) The maximum damage and bending/twisting were
prevent the repetitive failure and at the same time remedial
localized near to middle portion of the mast
measures are also highlighted to avoid similar failure in
structure (Fig. 2).
near future [6–20].
(ii) Plastic deformation in the form of bending and
The basic objective of this work was to identify the root
twisting of the failed structure was evident as shown
cause of the failure and to ascertain whether it was due to
in the Fig. 3.
problem related to materials or the failure was deficiencies
(iii) A number of cracks open to the surface of various
in the design, fabrication, installation, error in functioning,
magnitudes and direction were present at many of
etc. Apart from preliminary visual examination, chemical
the welded joints away from the damaged locations
analysis of the chain link material, magnetic particle
of the mast structure (Fig. 4). It is possible that
examination of welded joints, mechanical testing, fracto-
appropriate non-destructive testing was not carried
graphic analysis, and detailed finite element analysis using
out during its scheduled inspection.
ANSYS software package form the different steps of this
(iv) There was inadequate reporting of previous NDT
investigation in order to identify the probable cause of
inspections.
failure of the mast structure.
(v) The stress record-o-graph was not functioning
properly during the event of failure.
(a)

Cables Cables Material Characterization

The failed material is subjected to analyze chemically by


Cables Cables spectrometer (Model: Q4 TASMAN, Bruker, Germany).
The results of the analysis of the materials are provided in
Table 1. The chemical analysis confirmed to the specifi-
Carrier cation ASTM-595 grade steel [21]. Microstructural
Carrier
analysis was carried out from the samples extracted from
region shown in Fig. 3. Tensile tests were carried out as per
ASTM standard E-8m [22]. Flat specimens of 25 mm gage
length and 5 mm thickness were fabricated from the as

(b)

Fig. 1 Drilling rig mast structure during (a) in-service condition and Fig. 2 The middle portion of the mast structure is the region with
(b) after collapse maximum damage

123
476 J Fail. Anal. and Preven. (2015) 15:474–479

Materials twisted due to plastic the specimens was taken at 10 kgf load and is reported in
deformation
Table 2. The obtained values (mechanical properties) of
the mast structure confirms to the specification of ASTM
Location for sample
removal for material
595/572A, though the UTS values (528 Mpa) are on the
characterization higher side in comparison to the specified value (450 Mpa).
However, ASTM 595/572A grade materials are recom-
mended for mast structure [6]. The fracture surface was
saw cut and carefully extracted from the failed mast
structure (from location marked in Fig. 3). The fracture
surface was subsequently cleaned by ultrasonic cleaner
(acetone is used as solvent) followed by surface replication.
It is to be noted that the fracture surface being exposed to
open atmosphere for a long time resulted in the formation
of severe corroded layer on its outer surface. An attempt
Fig. 3 Deformed and twisted angle near the middle portion of the
was made to remove the corroded layer using HCL as
structure cleaning media. The fracture surface was then examined
using scanning electron microscope (SEM), S-3000N,
Hitachi Ltd, Japan (Figs. 5, 6).

Results and Discussion

Metallographic analysis of a damaged and undamaged


region revealed a microstructure consisting of pearlite and
widmanstatten ferrite (Fig. 5). There was no abnormal
material degradation in the damaged location of the failed
mast structure. Thorough examination of the fracture sur-
faces (Fig. 6) revealed a texture indicative of cleavage-type
cracking with river line patterns at places along with duc-
tile voids around the vicinity. The crack initiation zone was
observed in Fig. 6b. It can be concluded from the SEM
image that the failure was due to application of the stress
that exceeded the strength of the part. The sudden jerk
during the collapse of the mast structure showed that the
material had undergone high rate of loading and then
plastically collapsed. Some type of steels are stain rate
dependent and may exhibit cleavage-type cracking under
high strain rate, while exhibiting dimple rupture under
slower strain rate. The evidence of ample plastic defor-
mation in the failed component is shown in Fig. 3.

Structural Analysis Using FEM

In order to identify probable cause of failure of the mast


structure, simulated analysis of the structure for different
conditions of loads and anchors was examined. The anal-
Fig. 4 Magnetic particle examination revealed presence of fine ysis was carried out by finite element method (FEM). The
cracks in the weld joints at many location of undamaged part of the FEM is a numerical method, being used extensively in the
mast structure areas of Solid Mechanics, Heat Transfer, Fluid Mechanics,
Aero-elasticity, coupled field analysis etc. [23]. The
received failed sample. The tensile properties, yield method is based on discretization of a structure in finite
strength (YS), ultimate tensile strength (UTS), and per- number of inter-connected elements. The physical behavior
centage elongation are shown in Table 2. The hardness of of the field variables of the elements, viz., displacement,

123
J Fail. Anal. and Preven. (2015) 15:474–479 477

Table 1 Chemical analysis (weight percent) of the samples extracted from the failed mast structure
Element C Mn Si S P

Weight percent 0.21 0.85 0.027 0.022 0.012


Specified ranges 0.15–0.25 0.30–0.90 0.035 max 0.035 max 0.060 max

Table 2 Observed tensile properties along with average hardness value


Sample No. Y.S, MPa U.T.S, MPa % Elongation Avg. hardness, 10 Kgf, HV

1 338 528 31 132


2 340 528 28
3 324 527 27.5

Fig. 5 Microstructures of the (a) undamaged part and (b) damaged part of the mast structure

slope (degree of freedom) in case of structural analysis, are All the configurations have been analyzed for 160 T load
defined in terms of variables at the nodes by suitable on the mast structure.
interpolation function. The elastic characteristics of an The probable total cases have been considered are as
element is defined from the geometrical and material follows:
properties of the element and expressed in the form of a
(i) Case-1: The complete structure before failure with
matrix, called element stiffness matrix. The stiffness
all the anchored cables in positions and 160 T load
matrices of the elements are assembled suitably to form the
on the structure.
global stiffness matrix of the complete assembly. Subse-
(ii) Case-2: The complete structure without one
quently, the simulated loads and the support conditions are
anchored cable connecting top of the mast and
applied and the resulting matrix is solved to obtain the
anchoring point (RTG1).
unknown nodal variables, loads, and reactions at supports.
(iii) Case-3: The complete structure without one
Different conditions have been used to simulate possible
anchored cable connecting top of the mast and
failure causes. Examining different possibilities of failures,
anchoring point (RTC1).
different structural conditions, which may lead to final
(iv) Case-4: The complete structure without one
failure, have also been examined. Five different configu-
anchored cable connecting the middle of the mast
rations have been analyzed to examine the possibility of
and anchoring point (RMC1).
failure of any member of the structure or anchoring cable.

123
478 J Fail. Anal. and Preven. (2015) 15:474–479

Fig. 8 Simulated FEM of the


deformed mast structure without
cables

(v) Case-5: The complete structure without one


anchored cable connecting the middle of the mast
and one anchoring cable (RMG1).
Depending on the results, subsequent load cases have been
defined for examination.
The physical properties or real properties of the ele-
ments, such as plate thickness, cross-sectional area, and
moment of inertia of different members have been calcu-
lated from the measured dimensions of the corresponding
structural members and cables.
Fig. 6 Fracture surface showing (a) river line and high magnification
image showing (b) river lines and ductile voids along crack initiation The following material properties have been used for
zone different structural members:
Fig. 7 Finite element models
developed for stress analysis

123
J Fail. Anal. and Preven. (2015) 15:474–479 479

Modulus of elasticity, E = 210,000 MPa; mast structure was beyond the yield strength and mast
Poisson’s ratio = 0.3; deformed plastically failing under its own weight.
Yield stress = 334 MPa. The finite element model
developed for stress analysis is shown in Fig. 7.
References
The detailed FEM analyses reveal the following:
The maximum deformation of the structure, maximum 1. G. Das, S. Chakrabarty, A.K. Dutta, S.K. Das, K.K. Gupta, R.N.
cable tensions and maximum equivalent von Mises stress, Ghosh, Failure analysis of a high mast lamp post. Eng. Fail. Anal.
is given by the relation, 13, 1153–1158 (2006)
2. J.H. Lee, W.D. You, J.W. Kim, J.H. Choi, B.H. Choe, Failure
p p analysis of a mast column. Eng. Fail. Anal. 10, 317–323 (2003)
req ¼ 1= 2 ðrx ry Þ2 þ ðry rz Þ2 þ ðrz rx Þ2 þ ð6s2xy
3. W.P. Sung, J.C.M. Kao, R. Chen, Failure analysis of Q345 steel
þ 6s2zx þ 6s2yz Þ: structures on port cranes. Appl. Mech. Mater. 401–413, 844–847
(2013)
ðEq 1Þ 4. F. Frendo, Analysis of the catastrophic failure of a dockside crane
jib. Eng. Fail. Anal. 31, 394–411 (2013)
Here rx, ry, and rz represent normal stresses and sxy, szx,
5. E.S. Kim, S.K. Choi, Failure analysis of connecting bolts in
and syz represent shear stresses. collapsed tower crane. Fatigue Fract. Eng. Mater. Struct 36, 228–
From simulated studies under different conditions of the 241 (2012)
mast, it was observed that with all ropes in proper anchored 6. J. Swaminathan, K. Guguloth, M. Gunjan, P.K. Roy, R.N. Ghosh,
Eng. Fail. Anal. 15, 311–316 (2008)
condition, the mast would not have failed even with
7. D. Ghosh, H. Roy, A.K. Shukla, Investigation of probable cause of
enhanced load or jerks. Therefore, initiation of deformation a premature cracking of down comer nozzle of heat recovery steam
must have started owing to failure of some cables. There- generator (HRSG). J. Fail. Anal. Prev. 9(6), 517–521 (2009)
fore, the sequence of operations, conditions of the mast, 8. D. Ghosh, H. Roy, S. Ray, A.K. Shukla, High temperature corro-
sion failure of a secondary superheater tube in thermal power plant
anchored cables and loads, which have led to failure of the
boiler. High Temp. Mater. Process. 28(1–2), 109–114 (2011)
mast, is concluded as follows: 9. G. Das, S.G. Chowdhury, A.K. Ray, S. Das, D.K. Bhattacharya,
Eng. Fail. Anal. 9, 563–570 (2002)
(a) One of the anchoring cables of the top of the mast 10. H. Roy, D. Ghosh, A.C. Pankaj, A.K. Shukla, J. Basu, A case
has failed due to either improper anchoring or poor study on the premature failure of a cooling water pump shaft. Int.
service condition of the cable. J. Manuf. Sci. Prod. 9(1–2), 99–106 (2011)
(b) Excessive load on the mast due to jerks has led to 11. H. Roy, A. Saha, D. Ghosh, S. Roy, A.K. Shukla, Failure
investigation of platen superheater outlet header. J. Mech. Behav.
failure of the anchoring cables of the top of the mast. Mater. 19(6), 373–382 (2011)
(c) Without anchors at the top, stress near the intercon- 12. D. Ghosh, S. Ray, H. Roy, Failure investigation of high tem-
nection between the lower and upper parts of the perature Stud. J. Fail. Anal. Prev. 14(1), 17–20 (2014)
mast structure goes beyond yield strength and the 13. S.G. Chowdhury, P. Kumar, S.K. Das, D.K. Bhattacharyya, N.
Parida, Failure analysis of high temperature studs. Eng. Fail.
mast deforms plastically. Anal. 8, 521–528 (2001)
(d) With higher inclination of the mast, effective 14. D. Ghosh, S. Ray, H. Roy, N. Mandal and A.K. Shukla, High
bending load on the structure increases substantially temperature graphitization failure of primary superheater tube.
and bending continues further. High Temp. Mater. Process. doi:10.1515/htmp-2014-0137
15. D. Ghosh, H. Roy, A. Mondal, failure investigation of condensate
(e) Finally, even in absence of load tension, because of pump shaft. J. Fail. Anal. Prev. 14(4), 450–453 (2014)
self weight, the mast fails as shown in Fig. 8, similar 16. W. Muhannad, K.M. Deen, Failure analysis of water pump shaft.
to Fig. 1b (actual failure). J. Fail. Anal. Prev. 10, 161–166 (2010)
17. D. Ghosh, S. Ray, H. Roy and A.K. Shukla, Investigation into
cause of high temperature failure of boiler superheater tube. High
Conclusions Temp. Mater. Process. doi:10.1515/htmp-2014-0018
18. A.M. Lancha, M. Serrano, D. Gomez, Bricane. Eng. Fail. Anal. 8,
271291 (2001)
Based on the findings of this investigation, it is concluded 19. H. Roy, P. Sharma, D. Ghosh and A.K. Shukla, Corrosion failure
that non-functioning record-o-meter did not provide ade- of in-service economizer tube. J. Fail. Anal. Prev. doi:10.1007/
quate warning that the load applied to the mast was applied s11668-014-9848-9
20. D. Ghosh, S. Ray, A. Mondal, H. Roy, Failure investigation of
at the dangerous levels. This ultimately led to rapid increase radiant platen superheater tube of thermal power plant boiler.
in operating load. One or more of the cables or the anchoring High Temp. Mater. Process. doi:10.1515/htmp-2013-0128.
points did not have sufficient strength to withstand the rapid 21. ASM, ASM Handbook, vol. 1 (ASM, Metals Park, 1993)
increase in operating load exerted due to the sudden addi- 22. ASTM standard E-8M, Standard Test Methods for Tension
Testing of Metallic Materials, vol. 03.01, 2011
tional pull. One or two anchoring cables at the top failed first, 23. T.R. Chandrapatla, A.D. Belegundu, Introduction to Finite Ele-
thereafter stress between the lower and upper parts of the ments in Engineering. Pearson Higher Ed USA, 2011

123

You might also like