Jun 30-23 DR-TGT
Jun 30-23 DR-TGT
NO. OF UNIT
WORK ACTIVITY DATE START CATEGORIZATION STATUS REMARKS
WORKERS
BLK LOT
Work progress
are slowed due
Concrete pouring for stair landings, to inavailability
1 (mason), 3 concrete pouring for columns (10 of necessary
43 32 6/21/2023 Turnover Unit On going
(helper) columnns), inspection of electrical rough- materials, also
ins. to include the
inavailability of
workers.
NOTE/S: 1. Work activities are limited due to unavailability of necessary materials; 2. Clearing & rearranging of leftover materials
are necessary to ensure complete access within the site.
PREPARED BY: