DOC NO: ATOM/SIEMENS/001/03 Date: 12/03/2023


Purchase Order: - 4511947292/0 DATED :-( O3/February/2023)

SUBJECT: LALITPUR POWER GENERATION COMPANY LIMITED (3X660MW) OVERHAULING OF


BEARING INSPECTION,) AT CIGLAUWA, LALITPUR, JHANSI.

Project:- AOH Unit#2 Bajaj Energy Lalitpur.

Atom Power Representative SIEMENS Representatives


Asif
Ansari ( Site Manager) Mr. Ram Kumar Sharma (TA)
Shivam Singh (Site Co-Ordinator) Mr. Venugopal Nakka (TA)

ATOM POWER, Mobilized the site with their tools and manpower on dated 2 nd February 2023
during AOH Bearing inspection of Steam turbine, Generator & Exciter work of unit#2 as per
received P.O. 4511947292/0 dated 03-feb-2023.

The following activities has been carried out during AOH: -

1. Dy-synchronization unit on 03-02-2023 at 23.40


2. Barring Gear Stopped on 12-02-2023 at 11;45hrs.
3. All Dismantling, Quality checks & Inspection activities carried out as per scope.
4. Additional scope of works was carried out during outage. (Detail scope submitted to H.O.)
5. Assembly activities were completed and unit put on Barring Gear on 09-03-2023 at 16;20hrs.
6. TG Rolled to its rated speed on 11-03-2023 at 11;30hrs.
7. All parameters were in acceptable limit.
8. Unit Synchronized on 12-03-2023 at 01;25 hrs.
9. Vibration data has been recorded during partial loads/full load. (No any abnormality observed
during full load).

The overhauling works were successfully completed as per schedule. Customer satisfied with site team
dedication towards works, quality and safety.

For, ATOM POWER PROJECTS PVT LTD. For, SIEMENS ENERGY