23-01-2023

Nizam Sagar HEP DPR


D&D System and R&M work unit #1&2

1. Manpower
Manpower Site Generator Site cook Foreman Fitter Welder Rigger/Elec S.S.W. Helper Total
Mgr Supervisor Engineer

Voith 01 01 02

Sub-
Contractor 01 01 01 0 01 03 03 03 12
Ravi Hydro

2. Progress of Works: Start End


A) Unit#2 machine dismantling work 07-01-2023
1, unit#3 and #2 governor system foundation chipping work in progress
2, UCB top cover removing completed 23-01-2023
3, UCB window cover removing completed 21-01-2023 23-01-2023
4, pit 1 and pit 2 dewatering sump inside pipes black painting work is under progress
5, inside bearing Guide pads gap checking & oil drain work is under progress. 23-01-2023

Unit#2 dismantiling Photo


Nizam Sagar HEP DPR
D&D System

4. HSE
Environmental conditions: Weather: Sunny
Temperature 20.5°C, Humidity 42 %
5. Quality
Inspections and Handovers

None

6. Visitors at site:
None

7. Meetings
None

8. Other Remarks
None
9. Changes and Deviations (Change Management)
Technical Change request (TCR)

None

Voith Hydro
Mukesh Sharma
VHN