Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 1 (17)

. Projekt Projektnummer Upprättad av Datum

Ängelholm – Maria, Dubbelspårsutbyggnad 207271 Markus Johansson 20210909


Block: Granskad av PC: Datum

Betong Byggnadsverk
Aktivitet / Arbetsberedning för Startdatum Slutdatum Nr

Bro 14 Kulvert v.39_2021 v.41_2021 Rev.01

1. Aktuella handlingar och tillstånd / Relevant documents and permits

- Krav Brobyggande, version 2.0


- 144113-14A-052-BRO_14-1001.pdf Teknisk Beskrivning
- SS-EN_13670_2009 Execution of Concrete Structures
- 144113-05-025-0001 GESTALTNINGSÅTGÄRDER
- AF_Ängelholm_Helsingborg_TE
- Bro 14 Lyftplan 1 Armering och Byggmaterial
- Kommunikationsflöde Olycka & Tillbud
- BIM360 Field Management Checklist’s
- Arbetsmiljöplan / Health & Safety Plan, version 2.0
- ETS for Concrete pump.
-

1. Tidigare erfarenheter / Past Experiences

Did we learn anything from prior bridge constructions?

- Earlier experiences of both Skanska and Lambda have been worked into the methodology
INTERN INFORMATION
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 2 (17)

2. Startläge 3. Slutläge
Tidigare aktiviteter, tillgänglighet och skick arbetsområde, krav enligt handlingar, material, Förutsättningar för nästkommande aktivitet, färdigställda arbeten, kvarstående arbeten och färdiga
arbetskraft och maskiner samt yttre omständigheter. Ta med tillämpbart normalläge. kontrollplaner.

(Previous activities, availability and condition work area, requirements according to documents, (Prerequisites for next activity, completed work, remaining work and completed control plans.)
materials, labor and machinery and external circumstances. Bring the applicable normal position.)
- Lambda responsible to complete Site Induction for own personnel (both - All permanent works completed including patching & defect rectification
digital & physical inductions) before starting any works. (where/if necessary).
- Ground excavation and foundation preparation completed by civil, clear - Joint inspection of the works by Skanska & subcontractor, for acceptance,
approval, and/or defect notification.
space 1 meter outside of bottom slab around the bridge
- BIM Checklist’s complete.
Checklist environment (checklista miljö) performed - Removal of temporary works, equipment & materials (scaffold, formwork
etc).

2. Metodbeskrivning / Methodology
Tillvägagångssätt, strategi eller teknik för att gå från startläge till slutläge (Approach, strategy, or technology to move from start to finish mode)
• Site Establishment
- Survey / site set-out
- Delivery of materials & equipment
- Establish storage container facilities
INTERN INFORMATION
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 3 (17)

2. Metodbeskrivning / Methodology
Tillvägagångssätt, strategi eller teknik för att gå från startläge till slutläge (Approach, strategy, or technology to move from start to finish mode)
• Bottom Slab
- Formwork is made out of prefabricated form pieces that will be reused on the slabs, formwork from bridge 8/13 with height 600 mm will be reused as slab is
around 300 mm in height.
INTERN INFORMATION
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 4 (17)

2. Metodbeskrivning / Methodology
Tillvägagångssätt, strategi eller teknik för att gå från startläge till slutläge (Approach, strategy, or technology to move from start to finish mode)
- Form oil is applied to forms before they are mounted.
- Formwork is supported by 45x95 attached to a ‘stockmatta’
- All sharp cornes will be softened with the use of a 21 mm wodden triangle list montaged in the form. Beware of concrete cover after placement of triangle lists.
- Concrete cover to the bottom is 100 mm including the montage bars, 16 mm on the bottom and 12 mm on the sides of the slab.
- Concrete cover for sides and top are 35 mm.
- Bars larger than fi16 mm cannot be joint at the same cut. See BMUK EBC for details.
- Survey tolerance check of both steel and formwork including measuring the spot for concrete sampling. Cubes for sampling will be taken during casting but as a
backup we also measure a spot where a cylinder can be taken if necessary.
- If tempertures during casting will be sub zero we need to place cables for concrete computer.
- Prior to casting a cast meeting will be held where detailed man power planning will be done. Sufficient plans will
also be made for possible weather scenarios and for any other problem that might occur during casting.
- Lambda will notify Skanska when the works are ready for visual inspection, during this checklist 1 will be filled
out by Lambda.
- The client will be notified about castings in advance and be given a possibility for a joint inspection.
- For detailed planning regarding the casting a cast program and schedule will be developed.
- Concrete pump will be placed and installed according to ETS from Skanska Teknik.
- Neither concrete pump or concrete cars will be washed on site.
- During casting checklist 2 will be controlled and filled out by Lambda.
- After/during casting wall/slab connections will be sprayed with retarder for a coarse surface.
- When surface is finished it will be covered with tarps and/or plastic.
- Retarder will be cleaned off the day after casting.
- Strike formwork after OK from Skanska supervisor.
- Cut form ties along the concrete surface and repair as necessary.

• Wall and roof


INTERN INFORMATION

- Make sure connection between wall and slab is cleaned of retarder and sufficiently coarse before continuing works.
- Construct formwork for legs & wings starting with the inside. Follow dimensions of approved drawings for form.
- Formwork panels are prepared on the ground and lifted down with manitou or lorry crane.
- Formwork will be supported by supports connecting to the bottom slab with concrete screws. These will be placed
to not collide with formsupports. See sketches for dimensions of formwork and typical solutions.
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 5 (17)

2. Metodbeskrivning / Methodology
Tillvägagångssätt, strategi eller teknik för att gå från startläge till slutläge (Approach, strategy, or technology to move from start to finish mode)
While opening the formwork work on heights will be done with the use of aluminium scaffolding, (zip-up).
Form oil is applied to formwork. Don,’t forget to put oil on triangular lists as well.
- Concrete cover for walls and roof are 35 mm on the inside and 35 mm on the outside.
- Montage bars for walls will be done with fi12 mm bars.
- Cables for measuring temperature needs to be installed inside walls before closing of the formwork, 3 pc.
- Construct formwork for frame legs/wings on the outside AFTER cleaning out the bottom.
- Construct formwork for roof, see sketches for dimensions.
- Lay reinforcement and make room for casting spots and concrete sampling.
- Montage EKP according to model, OK to weld where EKP is placed in model.
- Montage cables for concrete computer in roof if there is risk for freezing.
- Survey tolerance check including measuring spot for concrete sampling.

- Cast concrete
- Prior to casting a cast meeting will be held where detailed man power planning will be done. Sufficient plans will also be made for possible weather scenarios
and for any problem that might occur during casting.
- Before casting a visual inspection will be done and checklist 1 will be finished and signed before casting.
- The client will be notified about castings in advance and be given a possibility for a joint inspection.
- For detailed planning regarding the casting a cast program will be developed.
- Concrete pump will be placed and installed according to ETS from Skanska Teknik.
- Neither concrete pump or concrete cars will be washed on site.
- Measurement of temperature will be started as casting begins.
- During casting checklist 2 will be controlled and filled out by Lambda.
- Finished surface will be covered as soon as possible with plastic and if applicable some water on top.
INTERN INFORMATION

- After casting
- Start of striking form & form support after OK from Skanska supervision.
- After formwork have been dismantled concrete surfaces are inspected and fixed as necessary.
- When works are finished a joint inspection is carried out.
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 6 (17)
INTERN INFORMATION
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 7 (17)

3. Kritiska arbeten / Critical works


Ange alla kritiska aktiviteter avseende produktivitet, Kvalitet, Miljö, Arbetsmiljö mm .
(Enter all critical activities related to productivity, Quality, Environment, Work
environment, etc. .) Förebyggande åtgärder / Preventative & mitigation measures Ansvarig Klar till
Produktivitet / Productivity
1. Crane mob/demob, operation, and lifting operations: 1. Mob/demob according to manufacturers instructions
Equipment failure only. Crane operator and riggers must be trained &
Falling materials competent. All team members to be briefed on lift plans.
Loads to be slung according to industry standards. All
lifting equipment/plant to be certified, rated & inspected
regularly. Use tag lines where necessary. Positive
communication between rigger & operator at all times
(radio/signals). Don’t lift loads above site personnel.
Involve lifting coordinators for special lifts.

2. Installation and striking of formwork and form support: 2. Installation of form support must be in accordance with
Falling materials manufacturers instructions and temporary works design
Working at height drawings. Check equipment and do not use damaged
Manual handling items. Harness & fall restraint with approved anchor
Noise point must be used when not on a working platform.
Failure of temporary structure Avoid manual handling where possible by mechanical
means. Lift materials in a team to lighten the load per
person. Use good technique when lifting (bend at the
legs, do not twist). Know your lifting capacity - do not
exceed it. Wear ear protection, especially when striking.
Follow drawings for temp form support and use
specified materials only. Check temporary structure
before loading. Check concrete test strength results
before unloading & striking.
3. Installation of steel reinforcement & cast-in items:
Injuries from working with reinforcement 3. Protect ends of protruding rebar with caps. Follow
INTERN INFORMATION

Slips/trips/falls correct installation sequence and ensure reinforcement is


Manual handling injuries adequately fixed before moving on (especially important
for vertical bars). Only use approved equipment for
cutting rebar, by a trained/competent person, after
obtaining a hot works permit. Lift as a team where
possible. Keep fingers clear of potential crushing areas.
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 8 (17)

3. Kritiska arbeten / Critical works


Ange alla kritiska aktiviteter avseende produktivitet, Kvalitet, Miljö, Arbetsmiljö mm .
(Enter all critical activities related to productivity, Quality, Environment, Work
environment, etc. .) Förebyggande åtgärder / Preventative & mitigation measures Ansvarig Klar till
Good housekeeping (keep area tidy and free of loose
material lying around).

4. Perform works required for earthing: 4. Obtain hot works permit before starting. Only
Hot works trained/competent personnel to use equipment. Use
correct fire resistant PPE. Equipment shall be
checked/serviced regularly. Fire Extinguishers to be at
the workface ready for emergency use. Inspect/monitor
area for 1 hour after hot works complete.

5. Concrete works: 5. Prior inspection/approval of pump operating location.


Concrete pump set-up, ground bearing capacity GEO temporary works if required to increase foundation
Concrete leakage bearing capacity. Cooling pipes need to be installed with
Failure of temporary works Double clamps in connection points and leak test before
Concrete burns doubling. Follow IFC drawings only for temporary form
Leakage of cooling pipes support and use specified, undamaged materials only.
Check temporary structure against IFC drawings before
loading. Monitor during casting. Protective clothing
should be worn to protect skin against concrete burns.
Wash concrete off if splashed. Use barriers to protect
personnel from hazardous areas.

6. Material deliveries: 6. Inform delivery drivers where (and whom) to report to


Personnel not inducted by Skanska when they arrive. Inform delivery drivers of minimum
Delivery driver(s) not familiar with site PPE required on site. Site supervisors should brief
Unloading materials from truck drivers of any specific hazards to be aware of. Delivery
personnel are to be escorted by site inducted personnel.
Materials are to be unloaded by site crane and site
INTERN INFORMATION

personnel.

7. Ensure exclusion zones are well demarcated, fenced off


7. Interface with other trades: with barrier and all site personnel are familiar with
Working in close proximity to a live railway line exclusion zones.
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 9 (17)

3. Kritiska arbeten / Critical works


Ange alla kritiska aktiviteter avseende produktivitet, Kvalitet, Miljö, Arbetsmiljö mm .
(Enter all critical activities related to productivity, Quality, Environment, Work
environment, etc. .) Förebyggande åtgärder / Preventative & mitigation measures Ansvarig Klar till
Kvalitet / Quality
1. Incorrect/unapproved materials 1. Ensure the correct documentation when ordering
materials. Ensure materials are approved where required
by design. Obtain material data from supplier where
required (incl. CE marking, material certificate, data
sheet, manufacturers instructions, concrete mix design).

2. Risk of defects, deformation, deflection, damages 2. Survey tolerance checks before casting. Temperature
monitoring. Prepour inspections must be carried out by
UE & Skanska and checklists completed/approved
before casting. Casting operations to be in accordance
with “Krav Brobyggande, version 2.0” and “SS-
EN_13670_2009 Execution of Concrete Structures”.
Control rise rate, pour height, vibration. Ensure
temporary works are sufficient.

3. Traditional form 3. Only new materials to be used for ‘board form’ concrete
surfaces which are exposed and seen as final product.
Take care to ensure consistency in finish across project
entirety. Plywood form may be reused <5 times.
4. Winter castings
4. Planning based on temperature cracking measures.
Planning in casting schedule.

Miljö / Environment
1. Material useage & sustainability 1. Reuse materials where possible. Planning meetings to
identify opportunity to share material resources between
INTERN INFORMATION

different bridge locations. Keep material/equipment


schedule to help conserve and keep stock of available
material. Recycle materials after use where possible.

2. Keep cars and work machinery not in use, at least 50 m


Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 10 (17)

3. Kritiska arbeten / Critical works


Ange alla kritiska aktiviteter avseende produktivitet, Kvalitet, Miljö, Arbetsmiljö mm .
(Enter all critical activities related to productivity, Quality, Environment, Work
environment, etc. .) Förebyggande åtgärder / Preventative & mitigation measures Ansvarig Klar till
2. Oil Spills from Flöjenbäcken (Flöjen stream) as well as from the
ditches leading to the stream. Have spill kits and water
secure kits (“länskorvar”) readily available at each
worksite. Also, fuel must be kept secured (invallat) at
least 50 m from the stream. Fueling of vehicles must be
performed at least 50 m from the stream.

3. Concrete wasteage 3. Volume calculations shall be made carefully to avoid


eccessive wasteage from over ordering. Extra ‘fresh’
concrete should be returned to batching plant. Extra over
concrete which has been through the pump should be
tipped neatly on site for later removal by excavator.

4. Control water run-off from work site. Only pump out


4. Waterway contamination water to approved locations.

5. Ensure that the concrete works is performed at low


5. Minimize risk for in-leakage of water during concrete water flow in the stream.
works. Water in the work area may lead to leakage of
concreate downstream in Flöjenbäcken.

6. Vehicles and machines are logged (fordonslista)

Arbetsmiljö / Working environment


1. Covid-19 1. Maintain social distancing. Use hand sanitizer. Keep
good personal hygene, wash hands regularly,
cough/sneeze in elbow (not in hands), stay home if
INTERN INFORMATION

feeling unwell, notify supervisor if start to feel unwell at


work. Adhere to the reccommendations of the Swedish
health authority.

2. Housekeeping 2. Maintain a clean and tidy worksite area. Minimum score


of 3/5 is required from Skanskas inspection regime.
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 11 (17)

3. Kritiska arbeten / Critical works


Ange alla kritiska aktiviteter avseende produktivitet, Kvalitet, Miljö, Arbetsmiljö mm .
(Enter all critical activities related to productivity, Quality, Environment, Work
environment, etc. .) Förebyggande åtgärder / Preventative & mitigation measures Ansvarig Klar till

3. EMERGENCY PROCEDURE & CONTACT 3. All personnel on the project shall install the “SOS
NUMBERS Alarm” application on their mobile phone device. This
app is the preferred method of raising an emergency call.
If not working - For AMBULANCE call 112

8. Kapaciteter och tider. / Capacities and times. Åtgärder för att säkerställa kapaciteterna. / Measures to ensure capacities Uppföljning. 7
Vad finns i kalkylen? Follow-up
Kapaciteter
Text Text
Text
Tider
Text Text Text

9. Material, Resurser och kompetens / Materials, Resources and Competence Mängd / Finns. Säkerställ att materialet finns tills momentet startar. Ansvarig Klart till
Förteckna material, maskiner,Utbildningar, YA och UE Amount Ja/Nej (Ensure the resource is available when the task begins).
Material
Formwork (Traditional)
Form support (Layher)
Working platform (Layher)
Steel reinforcing bar (loose bar, pre-bent, cages prefab’d)
Concrete (Sydsten)
Cast-in items (pipes, bolts, earthing items etc)
Chemicals (eg. Deseil, retarder, form oil, bitumen board etc)

Resourses
INTERN INFORMATION

Crane supplier (Skanska Rental)


Crane operator (UE Concrete – Lambda)
Logistics Team (Skanska)
UE Form/rebar/concrete (Lambda)
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 12 (17)

9. Material, Resurser och kompetens / Materials, Resources and Competence Mängd / Finns. Säkerställ att materialet finns tills momentet startar. Ansvarig Klart till
Förteckna material, maskiner,Utbildningar, YA och UE Amount Ja/Nej (Ensure the resource is available when the task begins).
UE Form support & working platform (Lambda)

Competence
Personnel requiring task specific education and competency:
- Crane Operator
- Rigger/banksman
- Hot works personnel (cutting, welding, etc)
- Machine/vehicle operators
- Site specific safety introduction
- Råd och skydd training (railway education)
- Scaffolding education
- Personnel installing & inspecting Layher form support
- Personnel installing & inspecting working platform scaffold
- Personnel installing any load bearing temporary works of any kind

10. Kommunikation
Säkerställ att all berörd personal har full kännedom hur aktiviteten ska utföras (Ensure that all relevant personnel are fully aware of how to perform the activity).

Skanska will deliver Toolbox talks to communicate important safety information throughought the project duration.

Lambda take responsibility for translating the information in this document and assurance that their personnel understand the content.

Register of signatures

UE/arbetsledare to help deliver

11. Säkerhetsgenomgång
INTERN INFORMATION

Inventera risker som kan vara aktuella vid arbetsmomentet. Bocka i rutan ”Ja” först efter att åtgärder från AMP hanterats i arbetsberedningen,
(Inventory risks that may be relevant at the time of the operation. Check the box "Yes" only after handling measures from AMP in the work preparation,)
Uppdatering
Riskinventering (Risk Inventory) Nej Ja Ytterligare åtgärder/Kommentarer (Additional Actions/Comments) AMP?

1. Arbete med risk för fall från högre höjd än två meter. ☐ ☒ Consrtuct & use working platform where risk is present. Use harness & fall ☐
Work with risk of falling from a height greater than two metres. restraint with approved anchor point when not on a working platform.
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 13 (17)

11. Säkerhetsgenomgång
Inventera risker som kan vara aktuella vid arbetsmomentet. Bocka i rutan ”Ja” först efter att åtgärder från AMP hanterats i arbetsberedningen,
(Inventory risks that may be relevant at the time of the operation. Check the box "Yes" only after handling measures from AMP in the work preparation,)
Uppdatering
Riskinventering (Risk Inventory) Nej Ja Ytterligare åtgärder/Kommentarer (Additional Actions/Comments) AMP?
Rescue plan in the case where a person falls and is hanging by harness:
1. If the person can be safely reached from an adjacent working platform, they
can be lifted by hand by persons on to that platform. Those performing the rescue
should also be protected by wearing a harness if they need to reach/climb outside
of the platform.

2. Arbete som innebär risk att begravas under jordmassor eller sjunka ner i lös ☒ ☐ ☐
mark.
Work that involves the risk of being buried under soil or sinking into loose ground.

3. Arbete som kan medföra exponering för kemiska och biologiska ämnen. ☐ ☒ Protective clothing should be worn to protect skin against concrete burns. Wash ☐
Work likely to involve exposure to chemical and biological substances. concrete off if splashed. Before working with any chemical, check material data
sheet and follow manutacturers instructions for use & protective measures.
4. Arbete som kan medföra exponering för joniserande strålning. ☒ ☐ ☐
Work that may result in exposure to ionizing radiation.

5. Arbete i närheten av högspänningsledning (samt övriga ledningar i mark). ☐ ☒ Site briefing to notify personnel of services to be aware of & avoid. Such services ☐
Work in the vicinity of a high-voltage line (as well as other lines in the ground). are to be demarcated with warning signs/barriers.

6. Arbete med risk för drunkning. ☒ ☐ ☐


Work with risk of drowning.

7. Arbete i brunnar eller tunnlar samt anläggningsarbete under jord. ☒ ☐ ☐


Work in wells or tunnels or underground construction work.

8. Undervattensarbete med dykarutrustning. ☒ ☐ ☐


Underwater work with diving equipment.

9. Arbete i kassun under förhöjt lufttryck. ☒ ☐ ☐


Work in a caisson under elevated air pressure.

10. Arbete vid vilket sprängämnen används. ☒ ☐ ☐


Work involving the use of explosives.

11. Arbete vid vilket lansering, montering och nedmontering av tunga byggelement ☐ ☒ Avoid manual handling where possible to lift by mechanical means. Lift materials ☐
eller tunga formbyggnadselement ingår. in a team to lighten the load per person. Use good technique when lifting (bend at
INTERN INFORMATION

Work involving the launch, assembly and dismantling of heavy building elements the legs, do not twist). Know your lifting capacity - do not exceed it.. Follow
or heavy formwork building elements. drawings for temporary form support, temporary structure must be checked by
Layher before loading.
12. Arbete på plats eller område med passerande fordonstrafik. ☐ ☒ Separate working area from trafficked areas with barriers & reduce traffic speed ☐
Work on site or area with passing vehicle traffic. with signage.

13. Rivning av bärande konstruktioner eller hälsofarliga material eller ämnen ☐ ☒ Removal of load bearing form support must be authorized by Skanska’s Work ☐
Demolition of load-bearing structures or hazardous materials or substances Supervisor, Project Engineer, or Block Manager.
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 14 (17)

11. Säkerhetsgenomgång
Inventera risker som kan vara aktuella vid arbetsmomentet. Bocka i rutan ”Ja” först efter att åtgärder från AMP hanterats i arbetsberedningen,
(Inventory risks that may be relevant at the time of the operation. Check the box "Yes" only after handling measures from AMP in the work preparation,)
Uppdatering
Riskinventering (Risk Inventory) Nej Ja Ytterligare åtgärder/Kommentarer (Additional Actions/Comments) AMP?

14. Rörelse av maskiner och fordon ☐ ☒ Only trained personnel to operate machines and vehicles. Use a spotter (assistant ☐
Movement of machines and vehicles person) to help when reversing in a congested area.

15. Arbetsmaskiner (inkl utrustning) ☐ ☒ Only trained personnel to operate machines & equipment. ☐
Work machines (incl. Equipment)

16. Arbete med risk för kläm-, såg- och skärskador ☐ ☒ Only trained operatives to use powertools. Use guards on tools where there is a ☐
Work with risk of crushing, sawing and cutting injuries risk of cutting. Keep fingers clear of potential crushing areas. Good housekeeping
(keep area tidy and free of loose material lying around).
17. Arbete med temporära konstruktioner ☐ ☒ Drawing details and manufacturers instructions must be followed when installing ☐
Work with temporary constructions temporary works. Temporary structures must not be loaded without prior
inspection & approval from Layher’s representative and Skanska’s Work
Supervisor, Project Engineer, or Block Manager.
18. Arbete med VA-system, FJV etc. ☒ ☐ ☐
Work with VA system, FJV etc.

19. Heta arbeten, brand- och explosionsskydd ☐ ☒ Obtain hot works permit before starting. Only trained/competent personnel to use ☐
Hot works, fire and explosion protection equipment. Use correct fire resistant PPE. Equipment shall be checked/serviced
regularly. Fire Extinguishers to be at the workface ready for emergency use.
Inspect/monitor area for 1 hour after hot works complete.
20. Risker för fall till samma nivå ☐ ☒ Keep worksite clean and tidy. Don’t leave unused materials lying around. Don’t ☐
Risks of falls to the same level walk around congested areas while using a mobile phone.

21. Arbete med knackning av skut ☒ ☐ ☐


Work with blasting or hammering boulders

22. Arbete med ergonomiska risker ☐ ☒ Avoid manual handling where possible to lift by mechanical means. Lift materials ☐
Work with ergonomic risks in a team to lighten the load per person. Use good technique when lifting (bend at
the legs, do not twist). Know your lifting capacity - do not exceed it.
23. Arbete med exponering för buller ☐ ☒ Wear ear protection when using noisy equipment or striking formwork. Wear ear ☐
Work with exposure to noise protection when working near noisy equipment/activities. Tell people around you if
you plan to start using noisy equipment.
24. Arbete med exponering för vibrationer ☐ ☒ Rotate personnel using vibrating equipment to minimize exposure. ☐
Work with exposure to vibrations

25. Arbete i dammande miljö ☐ ☒ Always wear respiratory protection when working with / near dusty activities. ☐
INTERN INFORMATION

Work in a dusty environment

26. Risker för tredje man i anslutning till arbetsplatsen ☐ ☒ Separate work area and restrict access from public with barriers & signage. ☐
Risks to third parties in connection with the workplace

27. Elektriska arbeten ☒ ☐ ☐


Electrical work
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 15 (17)

11. Säkerhetsgenomgång
Inventera risker som kan vara aktuella vid arbetsmomentet. Bocka i rutan ”Ja” först efter att åtgärder från AMP hanterats i arbetsberedningen,
(Inventory risks that may be relevant at the time of the operation. Check the box "Yes" only after handling measures from AMP in the work preparation,)
Uppdatering
Riskinventering (Risk Inventory) Nej Ja Ytterligare åtgärder/Kommentarer (Additional Actions/Comments) AMP?
28. Arbete vid järnväg och spårbunden trafik ☐ ☒ Ensure exclusion zones are used, fenced off with barrier and all site personnel ☐
Work near railway tracks and rail traffic are familiar with exclusion zones.

29. Organisation (B AMP) ☒ ☐ ☐


Organization (B AMP)

30. Etableringsytor - Konflikt mellan transporter och oskyddade personer(Arbetare) ☐ ☒ Ensure positive communication between transporters and site personnel. ☐
Establishment areas - Interface between transport and unprotected persons Transporters should be accompanied by a site inducted person.
(Workers)

31. Tidplan-risk för försämrad arbetsmiljö på grund av kort byggtid och begränsade ☒ ☐ ☐
Tider för spåravstängning(tågstopp). (B AMP)
Risk of deterioration of work environment due to over-ambitious
program/capacities and/or limited times for track closure (train stop). (B AMP)

32. Arbete med risk att utsättas för hot ☒ ☐ ☐


Work with a risk of being exposed to public threats

33. Projektspecifik risk ☒ ☐ ☐


Project specific risk

12. Signering
Följande produktionspersonal har tagit del av aktuell arbetsberedning
(The following production staff have read, understood and agree with this arbetsberedning)
INTERN INFORMATION
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 16 (17)

13. Godkännande / Approval


PC (eller motsvarande, tex Blockchef) godkänner arbetsberedningen / PC (or equivalent, e.g. Block Manager) approves the work preparation
Signatur Datum
INTERN INFORMATION
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 17 (17)

Efter utfört arbete stängs upprättad arbetsberedning i syfte att vara en del av vår egenkontroll samt förbättra arbetet med arbetsberedningar.
Nedanstående rubriker diskuteras tillsammans med de som utfört arbetet och varit med att upprätta arbetsberedningen

After the work has been completed, the established work preparation is closed in order to be part of our own control and to improve the work with work preparations.
The following headings are discussed together with those who carried out the work and helped to establish the work preparation

14. Uppföljning, erfarenheter och övrigt. / Follow-up, experiences and other.


Lista de problem som stötts på under arbetsmomentet, erfarenheter vi bör sprida. / List the problems encountered during the work, experiences we should share.