You are on page 1of 7

Resume

Nilesh Sutradhar
MANAGER (PROJECTS)
A result-oriented professional with the distinction of executing prestigious
projects of large magnitude within strict time schedule, seeking
challenging assignments in Planning, Fabrication / Erection & Pre-
Commissioning with an organization of high repute preferably in
Chemicals, Petrochemicals / Oil & Gas industry.

Proven Roles:

 13+ Years of onsite experience for project execution planning, piping


fabrication, erection, testing, final handover. Equipment & structure
erection. Tanks & Bullets fabrication, erection, testing and
commissioning.
 Managing the Contracts & vendors for various Mechanical Packages
from Bid specification to completion of the contracts.
EDUCATION/QUALIFICATIONS  Monitoring the project’s L3 schedule & preparing the L4 schedule for
various Contracts. Monitor & controlling the project progress using the
BE (Mechanical) from Gannt Charts & Key Performance Indicators (S-Curves & Histograms)
University of Rajasthan, Jaipur in  Expedite & monitor the status of agreed Delivery Schedules for the
2008 required construction materials & equipment from Order Specification till
Certificate Course in Microsoft pre-commissioning at site.
Projects.  Prepare, Review, and approve the various Work Method Statements,
th
12 from DAV Public Installation procedures, Risk Assessments & Lifting Plans for Storage
Tanks, Bullets, Piping & Equipment.
School, Kota in 2004
 Resolving the daily site issues related to Inter-Departmental clashing
10th from DAV Public
and fouling at site with approvals from Engineering Consultant via Site
School, Kota in 2002 Engineering Request or Field Design Change Note.
 Piping System & Sub-System identification, Marking the P&IDs,
AWARDS/HONORS Preparation of Piping Loops as per the Design Pressure and Test Packs
from the piping loops.
Performance Award for Site
 Inspection and preparation of punch list for Mechanical Clearance,
coordinator (ROGC) in Reliance
witnessing Hydro/Pneumatic Testing, Flushing of Piping Systems.
Jamnagar Mega J3 project in 2016
 Surveying the actual quantity of the work executed at site. Contractor
Best Safety Award by SHV monthly RA Bill certification, Cash Flow Reconciliation, Free Issue
Energy’s COO in 2021 Material Reconciliation, Final Bill Certification.
Award from SHV Energy’s CEO on Area of Expertise: -
completion of Tanks & Bullets in
2022 Project Planning & Control (Engineering, Procurement & Construction coordination)

LANGUAGES API 620 & API 650 (Fabrication, Erection, Testing, Commissioning of Tankages)

Bengali, English & Hindi ASME Sect. VIII/SMPV-U (Fabrication, Erection, Testing, Commissioning of Bullets)

Nationality – Indian API 686 (Erection & Alignment of Equipment)

Passport No. Z2800058 ASME B31.3 & PNGRB (Fabrication, Erection, Testing of piping works)

Date of Issue: 01/2014 Contractor & Vendor Management at site

Date of Expiry: 01/2024 Microsoft & Autodesk Applications (MS Excel/Word, MS Projects, AutoCAD,
Navisworks)

Document Number 1
Resume

Nilesh Sutradhar Relevant Project Experience


MANAGER (PROJECTS)
SHV ENERGY PVT LTD (SUPERGAS)
CT INFO. Project-1
Tuticorin Terminal Expansion
Project, Tuticorin
Title: - Manager (Projects)
Scope Description: 2.6 Lacs IM &
95000 ID Piping, Equipment (API
686) Installation, alignment, Pre-
Commissioning activities, 2 x
426
15000 MT Cryogenic Double Wall
Tanks (API 620), 2 x 100 MT
mail.com Mounded Bullets (ASME Sec.VIII &
SMPV-U), 2 nos. Fire Water tanks
(API 650) fabrication, erection,
testing, pre-commissioning &
commissioning activities.
Responsibilities:
Planning & executing the
fabrication & erection of 2.6 Lacs
IM & 95000 ID Piping works, 800
MT structure & piping support
erection, painting, insulation,
Piping materials expedition from
vendor, Issue of Material Dispatch
Notes to vendors, Equipment
installation and its alignment
check. Conducting Mechanical
Clearance & witnessing the
Hydro/Pneumatic Tests for the 238
nos. piping loops.
Responsible for the Construction,
Inspection, Testing &
Commissioning of 2 nos. Double
Wall Tanks (15000MT each), 2
nos. Mounded Bullets (100MT
each), 2 nos. Fire water tanks
(4000m3 each) adhering to the
Safety & Quality Standards
established for project. Installation,
testing & commissioning of Tank’s
PSV/Vacuum Breaker & 6 nos.
Retractable Cryogenic In Tank
pumps
Pre-commissioning activities like
liquidation of P&ID Punch Points,
final box-up, leak test, air drying &
N2 purging for the piping System &

Document Number 2
Resume

Nilesh Sutradhar Subsystems. Ensuring the


MANAGER (PROJECTS) Equipment readiness for
Mechanical Run Tests, Call to
various vendors and coordinate for
successful Trial Runs. Managing a
departmental team of 02
supervisors & 20 fully skilled
manpower. Actively participate in
Commissioning with the Operation
& Process teams for Gassing up,
Cooling Down sequence & first fill-
up of tanks

IPS-Mehtalia Pvt. Ltd (Employer)


Project-01
Multi Facility Multi Product
Plant, Jalpaiguri
Title: Construction Planning
Engineer
Client: Hindustan Coca-Cola Pvt.
Ltd
Start and End Dates: May-19 to
Feb-20
Scope Description: 1.2 Lac IM
Process & Utility piping erection,
HP & LP Compressor, Bottling
Units, Installation of DG & DG
Stack, Boiler & Boiler Chimney,
Multi-Level ETP, Co2 Bullet tank,
Pump House, WTP
Responsibilities: Planning &
Execution of Fast track Project
for HCCB, Concrete buildings with
PT slabs & interior finish works,
Equipment installation at Main
facility & Ancillary buildings (RCC
Qty 45000 CuM). Scheduling &
tracking the project in Microsoft
Projects. Regular interaction with
vendors like JMC/TetraPak/Forbes
Marshall/Caterpillar/Sicgil etc.
Process, Utility & Firefighting
piping fabrication, erection, testing
& handover. Progress review
meetings, MOM preparation &
circulation, S-Curves, updating
material tracker list, Progress
Reports, Method statements &
Erection plans, Contractor billing &

Document Number 3
Resume

Nilesh Sutradhar certification, Payment advise


MANAGER (PROJECTS) statement, Bill reconciliation &
material reconciliation.

Jacobs Engineering India Pvt.


Ltd (Employer)
Project-01
Water based Decorative Paint
Plant, Mysore
Title: Field Piping Engineer
Client: Asian Paints Ltd
Start and End Dates: Mar-18 to
May-19
Scope Description: 2.20 Lacs IM
Piping
(SS304/SS304L/SS316L/CS/GI),
145 nos. Equipment
erection,1600MT structure
fabrication & erection.
Responsibilities: Supervision,
Assistance and providing technical
support to contractors (H’Reck
Pvt. Ltd & Jobby Engineers Pvt.
Ltd) on matters related to piping
and structural fabrication/erection.
Equipment erection, Confirmation
for the mechanical integrity of the
piping systems erected.
Coordination with other disciplines
like Civil/Electrical &
Instrumentation teams Quantity
analysis for contractor bill
certification, active role in Work
Order Amendment and material
expedition, Insulation & Material
Reconciliation.

Reliance Industries Ltd


(Employer)
Project-01
Refinery off Gas Cracker Unit- J3
Project, Jamnagar
Title: Manager (Construction)
Start and End Dates: Aug 2014 to
Sept-2017

Document Number 4
Resume

Nilesh Sutradhar Scope Description: 3.0 lac IM


MANAGER (PROJECTS) piping erection & 1.25 lac ID site
fabrication of CS/SS304/LTCS
material over 3 tier pipe rack, 2
nos. Cold box erection, Civil Pipe
Supports, expander compressor,
tube & shell heat exchanger, utility
stations, pre-dressed column
erection,
Responsibilities: Planning & coordination for all the mechanical & piping
works including unit & rack piping erection at Area J (Cold Section) of
ROGC Unit, Isometric clearance, Loop file checking, Hot & cold
insulation, Bolt torquing & leak test, PSSR Punch Point Clearance,
Updating the Reliance MIS System (SPMS)
Managing the MOU Contractor
(L&T Hydrocarbon Engineering),
Issuance of Materials as per the
BOM, Preparation of the additional
MTO as per the Site modifications,
Surveying the actual quantity of the
work completed and certify the
monthly RA bills, Final Material
Reconciliation & Hand Over Take
Over of the area to Operations.

Project-02
Delayed Coker Unit-Revamp
Project, Jamnagar
Title: Manager (Construction)
Start and End Dates: Sept-2017 to Jan-2018
Scope Description: 2 Lacs IM / 1.35 Lacs ID Piping for the newly
installed Coke Drums. Installation of Central Feeding Device, Top Un-
heading Device, Bottom Un-heading Device
Responsibilities: Supervision, monitoring and providing technical
support to Contractor (H’Reck Pvt Ltd) on matters related to piping
fabrication & erection (CS/SS/AS), structural fabrication & erection,
Equipment erection as well as in all other mechanical systems.
Coordination with Delta Valve (Vendor) for erecting BUD/TUD &CFD on
New Coke Drums.

IOT Engineering Project Ltd


(Employer)
Project-01
Panipat Refinery Additional Expansion Project, Panipat
Title: GET / Jr. Manager (Piping Construction)

Document Number 5
Resume

Nilesh Sutradhar Client: Indian Oil Corporation Ltd


MANAGER (PROJECTS) (IOCL)
EPCM: Engineers India Limited
(EIL)
Start and End Dates: May 2010 to
April-2011
Scope Description: 2.5 Lacs IM/ 70000 ID(CS/IBR/NACE) piping
fabrication, erection & hydrotesting, all interface joints with Units at
battery limits like DCU/SRU/CDU-VDU/DHDT Units. Installation of new
Crude Pumps, Insulation & Painting of the new facility installed.
Responsibilities: Planning & execution of Offsite piping, Rack piping,
Sleeper piping Steam tracing, Hydrotesting, Box-up activities, Hot & cold
insulation, Manpower handling, Generation of Material Issue Note,
Material control at site, Quantity analysis for billing, As-Built drawings,
Cradle & Saddle support installation, Client Bill follow-up, Contractor bill
checking & certification, Material reconciliation

Project-02
Paradip Refinery, Odisha
(BOOT-3, Crude Area)
Client: Indian Oil Corporation Ltd
(IOCL)
PCM: Fact Engineering & Design
Organization (FEDO)
Title: Jr. Manager (Piping
Construction)
Start and End Dates: April-2011
to June-2013
Scope Description: 3.0 lac IM /
90000 ID fabrication & erection,
testing and final hand over of
piping systems from jetty battery
limit to 11 nos. crude tanks
including a pump house and Tilted
Plate Interceptor
Responsibilities: Supervising the
fabrication, erection & testing of
total piping & mechanical systems
related to the 11 nos. of Crude

Document Number 6
Resume

Nilesh Sutradhar Tank. Structural fabrication &


MANAGER (PROJECTS) erection inside & outside the tank
dyke walls, billing & material
reconciliation, Pre-commissioning
activities & final handover to client
for operation.

Project-03
Paradip Refinery, Odisha (BOOT-3, Product Area)
Client: Indian Oil Corporation Ltd
(IOCL)
PMC: Fact Engineering & Design
Organization (FEDO)
Title: Jr. Manager (Piping
Construction)
Start and End Dates: June-2013
to July-2014
Scope Description: 1.0 Lac IM
piping (CS, LTCS, IBR, GI)
installation & testing, System
completion & pre-commissioning
activities for HSD, MS, Kerosene,
LPG, Propylene etc. Flushing &
box-up of the systems.
Responsibilities: Planning &
installation of all the piping &
equipments, Loop mechanical
clearance, Testing & all pre-
commissioning activities
completion. Clearance of all punch
points and successfully handed
over to IOT Utkal Energy
Services for 15 years of operation,
Involved in activities like final billing
& final material reconciliation.

Employment History

Month/YEAR Company
Feb 2020 – Current SHV Energy Pvt Ltd
May 2019 – Feb 2020 IPS-Mehtalia Pvt Ltd
February 2018 – May2019 Jacobs Engineering Pvt Ltd
August 2014 – January 2018 Reliance Industries Ltd
May 2010 – July 2014 IOT Engineering Projects Ltd

Document Number 7

You might also like