Basic Construction Plan

PROJECT NAME

ID Project Name Sub-contractor Days Start End 9-Jul 12-Jul 15-Jul 18-Jul 21-Jul 24-Jul 27-Jul 30-Jul 2-Aug 5-Aug 8-Aug 11-Aug 14-Aug 17-Aug 20-Aug 23-Aug 26-Aug 29-Aug 1-Sep 4-Sep 7-Sep 10-Sep 13-Sep 16-Sep 19-Sep 22-Sep
1.0 Substation - Zone 3 70 9-Jul 17-Sep

1.1 Establishment 8 9-Jul 17-Jul


1.1.1 Collect Building permit Perfect Builders 1 9-Jul 10-Jul
Apply for permanent water &
1.1.2 electrical connections Perfect Builders 7 10-Jul 17-Jul
Erect stores & welfare facilites on
1.1.3 site Perfect Builders 2 15-Jul 17-Jul

1.2 Earthworks + Substructure 27 18-Jul 14-Aug


1.2.1 Clear site ABC Earthworks 2 18-Jul 20-Jul
1.2.2 Setting out of foundations AN Bricklayers 2 21-Jul 23-Jul
1.2.3 Excavate Trenches ABC Earthworks 4 22-Jul 26-Jul
1.2.4 Cast Concrete FH Concrete 1 27-Jul 28-Jul
1.2.5 Build foundation walls AN Bricklayers 5 29-Jul 3-Aug
1.2.6 Backfill under floors ABC Earthworks 2 4-Aug 6-Aug
1.2.7 Lay Damp proof membrane FH Concrete 1 7-Aug 8-Aug
1.2.8 Install electrical 1st fix services Spark Electrical 3 9-Aug 12-Aug
1.2.9 Install plumbing 1st fix services Pro Plumbing 2 10-Aug 12-Aug
1.2.10 Cast surface bed slab FH Concrete 1 13-Aug 14-Aug

1.3 Super Structure 39 9-Aug 17-Sep


1.3.1 Activity AN Other 2 9-Aug 11-Aug
1.3.2 Activity AN Other 2 11-Aug 13-Aug
1.3.3 Activity AN Other 1 13-Aug 14-Aug
1.3.4 Activity AN Other 4 16-Aug 20-Aug
1.3.5 Activity AN Other 2 18-Aug 20-Aug
1.3.6 Activity AN Other 1 19-Aug 20-Aug
1.3.7 Activity AN Other 1 20-Aug 21-Aug
1.3.8 Activity AN Other 1 23-Aug 24-Aug
1.3.9 Activity AN Other 2 24-Aug 26-Aug
1.3.10 Activity AN Other 1 25-Aug 26-Aug
1.3.11 Activity AN Other 2 26-Aug 28-Aug
1.3.12 Activity AN Other 10 28-Aug 7-Sep
1.3.13 Activity AN Other 5 7-Sep 12-Sep
1.3.14 Activity AN Other 3 12-Sep 15-Sep
1.3.15 Activity AN Other 2 15-Sep 17-Sep

run date 8/7/2020