You are on page 1of 12

S.

No

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34

35
36
37
38
39
40
41
42
43
44
45
46
Activities

Surface perparation for Shotcrete Work - Phase 01


Surveying and level fixing for shotcrete work - Phase 01
Anti termite application - vertical - Phase 01
Scaffolding erection and dismantelling for shotcrete work - Phase 01
Curing of Shotcrete work - Phase 01
Final Excavation
Surface perparation for Shotcrete Work - Phase 02
Surveying and level fixing for shotcrete work - Phase 02
Anti termite application - vertical - Phase 02
Scaffolding erection and dismantelling for shotcrete work - Phase 02
Curing of Shotcrete work - Phase 02
Spacer block making at Mason yard
Surface perparation levelling for blinding work
Anti termite application - Horizontal
Pit side vertical concrete shuttering or Block work construction
Bliding Concrete work - powerfloat finishing
Curing for Bliding work
Concrete sample technican
Surface perparation for waterproofing - Horizontal & Vertical
Waterproofing- Horizontal @ Raft Bottom
Waterproofing- Vertical until Raft thickness
Raft Rebar fixing - Phase -01
Construction joint water stopper fixing @ Raft Phase -01
Construction joint water stopper fixing @ Raft to vertical retaining wall and core wall Phase -01
MEP cut out fixing @ Raft ( Collection Tank, Drive way drain , gully ) Phase -01
Raft Concrete - Phase 01
Raft Rebar fixing - Phase -02
Construction joint water stopper fixing @ Raft Phase -02
Construction joint water stopper fixing @ Raft to vertical retaining wall and core wall Phase -02
MEP cut out fixing @ Raft ( Collection Tank, Drive way drain , gully ) Phase -02
Raft Concrete - Phase 02
Scaffolding Erection and Dismantelling for Retaining wall rebar work - ( Area 1,2,3,4,5,6,7,8,9,10,11,12,etc)
Retaining wall Rebar fixing- ( Area 1,2,3,4,5,6,7,8,9,10,11,12,etc)
Shuttering for Retaining wall ( Area 1,2,3,4,5,6,7,8,9,10,11,12,etc)

Scaffolding Erection and Dismantelling for Retaining wall concrete work- ( Area 1,2,3,4,5,6,7,8,9,10,11,12,etc)
Scaffolding Erection and Dismantelling for Column and Corewall rebar work @ ( -B2 Level )
Column and Corewall rebar work @ ( -B2 Level ) Rebar fixing
Shuttering for Column and Corewall rebar work @ ( -B2 Level )
Scaffolding Erection and Dismantelling for Column and Corewall rebar work @ ( -B2 Level ) concrete work
AS AF
PS PF
Duration Actual Actual Qty Unit Foreman
Plan Start Plan Finsh
Start Finish
Chargehand Helper Carpenter Steel fixer
Scaffolder Mason Wlder Electrician
Rigger Banksman Remarks

You might also like