You are on page 1of 3

Structural Engineering International

ISSN: 1016-8664 (Print) 1683-0350 (Online) Journal homepage: https://www.tandfonline.com/loi/tsei20

The Tsukuhara Extradosed Bridge near Kobe

Atsuo Ogawa (Chief Eng.), Tetsuo Matsuda (Construction Mgr) & Akio Kasuga
(Chief Eng.)

To cite this article: Atsuo Ogawa (Chief Eng.), Tetsuo Matsuda (Construction Mgr) & Akio
Kasuga (Chief Eng.) (1998) The Tsukuhara Extradosed Bridge near Kobe, Structural Engineering
International, 8:3, 172-173, DOI: 10.2749/101686698780489199

To link to this article: https://doi.org/10.2749/101686698780489199

Published online: 23 Mar 2018.

Submit your article to this journal

Article views: 21

View related articles

Full Terms & Conditions of access and use can be found at


https://www.tandfonline.com/action/journalInformation?journalCode=tsei20
______

The Tsukuhara Extradosed Bridge near Kobe


Atsuo Ogawa, Chief Eng.
Tetsuo Matsuda, Construction Mgr
Japan Highway Public Corp., Kobe. Japan
Akio Kasuga, Chief Eng.
Sumitomo Construction Co.. Ltd. Tokyo, Japan

Girder
The Tsukuhara Bridge is constructed
with single-cell box girders instead of
the conventional two-cell girders. The
efficiency of erection was enhanced by
using form travellers, and by reducing
the dead weight of the girders. result-
ing in a slab span of 9 m. A finite
element analysis was used in the de-
sign to ensure durability similar to that
of a traditional prestressed concrete
slab deck with a 6 m span.
Twelve external tendons, comprising
19 strands 15.2 mm in diameter, are
placed inside the box girder at the cen-
ter span to resist positive bending mo-
ments. The internal tendons. which are
mainly used for cantilevering. are 12
strands of 12.7 mm diameter. More-
over, a single 28.6 mm strand after-
bond" system is used for transverse
Fig. 1: The Tsukuhara Bridge prestressing. which means that epoxy
resin inserted between the strands and
the polyethylene sheathing hardens af-
Background Design ter tensioning. Cement grouting is not
necessary in this system.
The concept of "extradosed" bridges, The Tsukuhara Bridge is a three-span
where the stay cables are functionally frame structure with a main span Pylons
similar to external post-tensioning ca- 180 m long (Fig.2). This clear span was
bles, was introduced by Jacques Mathi- needed to avoid disturbance of the Piers and pylons are V-shaped and stay
vat in 1988. The Tsukuhara Bridge lake it crosses, which is used for drink- cable forces can flow straight from top
(Fig. 1), part of a road network with ing water. In order to reduce the over- to bottom (Fig. 3). Cross beams be-
the Akashi-Kaikyo Bridge, is the sec- turning moment of the piers, a con- tween the pylons are not necessary be-
ond application of this technique by crete counterweight has been placed cause the pylon is shorter than for a
the Japan Highway Public Corp. A inside the box girder of each side span. comparable cable-stayed bridge. Sad-
decade ago, bridges with a 180 m cen- The ratio of the center span to the tow- dles are used at the top of the pylons to
ter span were mostly cable-stayed or er or girder height is the same as on simplify the installation of reinforce-
massive box-girder bridges, but the the Odawara bridge. ment.
extradosed concept can be applied to
such span lengths, resulting in lower 322 800
construction costs. -
5 400
T
180 000 — 76400

Originally the Tsukuhara Bridge was


planned as an arch bridge, but the
bridge type was changed because of
the success in Japan's first extradosed Al
bridge, the Odawara Blueway Bridge.
The extradosed design was also felt
to fit better visually with a nearby P2
cable-stayed pedestrian bridge. Finally, P1
seismic design was an important con-
sideration. Fig. 2: Elevation

172 Structures in Japan Structural Engineering International 3/98


Stay Cables greater than that of the Great Kanto 16800
Earthquake in 1923, the previous 2000 12800 2000
The stay cables of the Tsukuhara benchmark for seismic design in Japan.
Bridge form a replaceable external ca- A new set of provisional specifications
ble system. Each stay cable consists of for seismic design has subsequently
27 strands 15.2 mm in diameter, pro- been drawn up based on the 1995
tected against corrosion with a double quake. The Tsukuhara Bridge was de-
layer of polyethylene. As the maxi- signed according to these new specifi-
mum stress change in the stay cables cations because detail design started
due to live load is 3.7 kgflmm2, 0.6 fpu just after the 1995 earthquake. In or-
(fpu is the strength of the stay cables) der to simulate the behaviour of the
is adopted. as an allowable stress of bridge during earthquakes, nonlinear
stay cables. Therefore, there is no need seismic response analyses allowing for
for anchorages with high fatigue concrete cracking and yielding of rein-
strength. such as those used in cable- forcement were also carried out in
stayed bridges. both the longitudinal and transverse
The stay cables of extradosed bridges directions.
are functionally comparable to exter-
nal post-tensioning cables. As they are
located on the outside of the girders, Construction
adequate provision has to be made for
the damping of wind vibration. Vibrat- The girders are constructed by the free
ing stay cables not only are unsettling cantilevering method, using form trav-
to bridge users, but vibration may lead ellers (Fig. 4). An extra-large traveller
to actual breakage of the cables. The with a maximum block length of 7 m
dampers installed in the Tsukuhara was used for the critical P1 pier, in or-
Bridge use the high damping capacity der to shorten the construction sched-
of rubber for base isolation. This type ule. It was around twice the size of a
of damper is easy to maintain and its standard form traveller.
performance is relatively immune to
temperature variations. The dampers One of the advantages of the extra- Fig. 3: Pier and pylon
are designed to achieve more than a dosed structural scheme compared
0.03 logarithmic decrement, which is with cable-stayed bridges lies in the
necessary to suppress wind-rain-in- tensioning of the stay cables. No ad- in the form traveller. Moreover, the
duced vibration. justment for stay cable forces is need- low pylons can contribute to improve
ed and the stay cables are tensioned at the performance of both the pylons
the same time as the internal tendons. and the stay cables.
Seismic Design This means that a special device for
The magnitude of the January 1995 holding hydraulic jacks is not neces- Construction costs for the Tsukuhara
earthquake in the Kobe area was sary because the jacks can be housed Bridge were lower than for a similarly
sized cable-stayed bridge. Increased
understanding of the structural behav-
iour of this innovative bridge system
is needed to fully exploit its promising
characteristics.

SEI Data Block

Owner:
Japan Highway Public Corp.
Structural engineers. Contractors:
Sumitomo Construction Co. Ltd
Service date: April 1998

Deck surface (m2): 5980


Amount of steel (t): 2000
Volume of concrete (m3):
Structure 10800
Substructure 5600
Total: 16400
Total cost (USD millions): 44.2
Fig. 4: Erecting the girder with travellers

Structural Engineering International 3/98 Structures in Japan 173

You might also like