Through the scope of our real estate business and dealing with
the process of valuation on a daily basis, we put the stages of
the construction of a house consisting of a first floor (bear two
floors) according to what is customary locally:
m To describe the stage
1 Upon completion of setting the
rules
2 Upon completion of the
foundation works
3 Upon completion of the beam
work and**** the first floor
4 Upon completion of the bricks
works of the first floor
5 Upon completion of the casting of
the slab on grade
6 Upon completion of the roof
works
7 Upon completion of *****
8 Upon completion of the inside
plastering works
9 Upon completion of Ceramic of
bathrooms and kitchens
10 Upon completion of the outside
plastering works
11 Upon completion of Electrical
installations and waterproof for
bathrooms and kitchen
12 Upon completion of all slabs on
grade
13 Upon completion of primer and
putty works
14 Upon Installing the doors and
windows
15 Upon completion of Installation of
sanitary materials and electrical
lights
16 Upon completion of Sewage
works
17 Upon completion of Dyeing and
cleaning
18 operational works of home and
trial period
General Note:
In the field of construction, there are slight damages and other
heavy, the slight in no way does not affect the beyond such as
paint, doors and windows because they are called damage
specified.
There are damages that have consequences and effects of what
is coming and is called moving and movable damage, which
gradually move to the element that follows and adversely affect
the operation of the element's operation or may lose part of it.
Classification of stages:
Through the foregoing, the table will be referenced and the
classification of the stages to basic and secondary to determine
the accuracy of the utilization criteria.
m Description of the stage Classification
1 Upon completion of setting the basic
rules
2 Upon completion of the basic
foundation works
3 Upon completion of the beam basic
work and**** the first floor
4 Upon completion of the bricks basic
works of the first floor
5 Upon completion of the casting of basic
the slab on grade
6 Upon completion of the roof basic
works
7 Upon completion of ***** basic
8 Upon completion of the inside secondary
plastering works
9 Upon completion of Ceramic of secondary
bathrooms and kitchens
10 Upon completion of the outside secondary
plastering works
11 Upon completion of Electrical secondary
installations and waterproof for
bathrooms and kitchen
12 Upon completion of all slabs on secondary
grade
13 Upon completion of primer and secondary
putty works
14 Upon Installing the doors and secondary
windows
15 Upon completion of Installation of secondary
sanitary materials and electrical
lights
16 Upon completion of Sewage basic
works
17 Upon completion of Dyeing and secondary
cleaning
18 operational works of home and basic and
trial period secondary
The final value of the compensation for the non-utilization of the first and upper
floor of the entire project: (before the change order No: 1)
14,003 ×2191 = 30,680,573 (thirty million six hundred and eighty thousand
five hundred seventy three RO)
2/After the change order No2:
Throughout the aforementioned, the value of the single house after the change
order is RO 80,489 (eighty thousand four hundred and eighty nine RO)
The value of the non-utilization of the first and upper floor within the single
house after the change order No 1:
80,489 ×23 % =18,512 eighteen thousand five hundred and twelve RO)
The final value of the compensation for the non-utilization of the first and
second floor of the entire project: (after the change order No: 1)
18,512 ×2191 =40,559,792 (forty million five hundred fifty-nine thousand
seven hundred ninety-two RO).
Throughout all the aforementioned, the value of the average between the two
values before and after the change order can be calculated. The estimated
amount is:
35,000,000 thirty-five million RO-/
Signed and stamped by
Valuation Department