Makkah Arafat Project

21-27 March
Introduction

The Purpose of this prestation is to inform of


the ongoing renovation activates and to
provide an overview of activates completed
since the March 21.
Completed works:

1. Floor Slabs:
Work on the floors and pouring the entire area with a height of 7 cm with a full iron layer were completed.
Introduction
The restoration work started by the Professional Triangle on March 21 include
I. Civil Work
1. Demolition
2. Walls
3. Flooring
4. Ceilings
5. Doors
6. Paint
7. Construction

II. MEP
1. Fire alarm
2. HVAC
3. Power
4. Drainage & Water Supply
Toilet Demolition:

Demolitions have started in the


toilet on the ground and first floor,
including demolishing the celling
and taking measurements to install
the partitions and doors of the
new toilet.

Celling Demolition:
All roofs were demolished, the
electricity path was modified, and
new gypsum arrived at the site.
Recking Area:
All shelves in the recreation area
were dismantled in order to
modify the floors, and the
previous dimensions were taken
for easy re-installation.
Establishment of electricity:

Two floor boxes were established in


the control room and one in the small
meeting room, as shown in orange in
the drawing.

Establishment water drainage:

A water drain for the air conditioners


has been installed, as shown in red in
the drawing.
Work schedule for the second week 28 Mar to 4 April

1. Floor grinding
2. Electrical conduit and wires for toilest
3. Testing of ATS and Panel board
4. Cement oard and ceiling for toilets
5. Installation of ceiling for offices
6. Installation of ceiling for corridor
7. Installation of cable for generator
8. Installation of lighting fixtures for offices
9. Installation of lighting fixtures for corridor
10. Installation of sanitary fixtures
Thanks