Professional Documents
Culture Documents
21-27 March
Introduction
1. Floor Slabs:
Work on the floors and pouring the entire area with a height of 7 cm with a full iron layer were completed.
Introduction
The restoration work started by the Professional Triangle on March 21 include
I. Civil Work
1. Demolition
2. Walls
3. Flooring
4. Ceilings
5. Doors
6. Paint
7. Construction
II. MEP
1. Fire alarm
2. HVAC
3. Power
4. Drainage & Water Supply
Toilet Demolition:
Celling Demolition:
All roofs were demolished, the
electricity path was modified, and
new gypsum arrived at the site.
Recking Area:
All shelves in the recreation area
were dismantled in order to
modify the floors, and the
previous dimensions were taken
for easy re-installation.
Establishment of electricity:
1. Floor grinding
2. Electrical conduit and wires for toilest
3. Testing of ATS and Panel board
4. Cement oard and ceiling for toilets
5. Installation of ceiling for offices
6. Installation of ceiling for corridor
7. Installation of cable for generator
8. Installation of lighting fixtures for offices
9. Installation of lighting fixtures for corridor
10. Installation of sanitary fixtures
Thanks