Final Exam for advanced project management (for students outside Vietnam) • Part A: Student will performe the designated project - in the slides below, to perform the required steps in the below slides. • Part B: Student will find a small project in practice, to repeat the steps as in the exercise project. Student can use more pictures to illustrate the selected project activities. • Deadline for submission is....
• Note: You may not complete 100% of the project requirements.
However, the higher the completion level, the better the rating will be. The designated project • Febrina Soulisa Imp <febrina.soulisa.imp20@hcmut.edu.vn>, The project 1 • Poe Myatthu Imp poe.myatthu.imp20@hcmut.edu.vn- The project 1 • Ivan Dela Liana Marquez – ivan.marquez.imp20@hcmut.edu.vn- The project 2 • Justine Guanzon Imp <justine.guanzon.imp20@hcmut.edu.vn>, The project 2 • John Maano Imp <john.maano.imp20@hcmut.edu.vn>, The project 3 Final Exam for advanced project management (for students inside Vietnam) • Part A: Student performe the 3rd project in the slides below, to perform the required steps. The deadline for submission is 1 day before the paper test date. • Part B: Students will take the paper-based test. Exam time will be 90 minutes. The exam date will be announced by the Office for International Study Program. • Note: You may not complete 100% of the project requirements. However, the higher the completion level, the better the rating will be. EXERCISE PROJECTS Project 1 In this project, a two-level residential house is to be constructed. The following information is available for the project: a. The house plan is as follows:
b. All civil work is
supervised by Ahmed, electrical work, supervised by Majed and mechanical work, supervised by Samir. c. The project consists of 35 activities as follows, with a detailed description below: 1. Layout: The excavation perimeter is to be located for foundations, strip footings, sewage pipe trenches, and drainage well point for the suction pump and weeping tile. 2. Excavate Foundation & Utility Trenches: Includes the removal of the excavated soil. 3. Forms, Footing: The foundations are to be located on the site with the exact dimensions. 4. Reinforcing, Light, Footing: Steel reinforcement to be laid inside the footing forms considering the proper concrete cover. 5. Placing Concrete, Direct Chute: After checking the soundness of the concrete forms, concrete to be poured inside the forms with suitable vibration. 6. Removal of Forms, Footing: twenty-four hours after the concrete has been poured and cured, the forms can be removed. 7. Forms. Walls:Forms for the 200-mm thick concrete walls are to be erected. 8. Reinforcing, Light, Walls: Steel reinforcement to be laid inside the wall forms considering the proper concrete cover. 9. Placing Concrete, Walls: After checking the soundness of the wall forms, concrete to be poured inside the forms with suitable vibration. 10. Removal of Form, Walls: twenty-four hours after the concrete has been poured and cured, the forms can be removed. 11. Insulation and Waterproofing of Foundation & Walls:After curing, the water / damp proofing can be applied, the material to be used is bituminous base material (EXPSIV). Fiberglass can then be used as an insulation material for the walls. 12. Back Fill: After the weeping tile is laid around the foundations covered with pea gravel and concrete curing is completed, backfill can take place with the specified amount of compaction (normally 95%) using a dozer with vibratory roller. 13. Placing Concrete, Floor: With special protection for all drainage pipes and columns/walls and the soil compacted properly, the concrete floor takes place. 14. Wood Columns 100mm X 150mm: These columns are to support the beams for the main floor and the roofing frames. These columns are to be supported on the footings and the surrounded walls. Steel columns may also be used. 15. Stud Walls & Wooden: These studs work as a support for the drywall from both sides. The studs are supported by the floor beams. The studs also determine the door and window locations. 16. Floor Joists & Cross Bridges: The distances between beams are to be divided by the joists to fit the plywood dimensions. These joists need cross bridges to support them against lateral forces in the transverse direction. 17. Roof Trusses & Sheathing: The top covering system to the second floor is to be supported on columns at the two sides of the building. TIle sheathing consists of plywood covered by waterproofing material. 18. Subfloor 19-mm Thick: This is to be laid on the floor joists to support the following flooring items. 19. Ductwork: Install the duct for heating and air-conditioning all around the two levels of the house. 20. Exterior Walls Insulation: All the walls around the building through the two levels have to be insulated. 21. Electrical System: This activity progresses along the construction of other activities, where the main electric circuit breaker is installed while the basement construction is being done, then the internal (walls, floors) wiring is installed during the construction of these items. After completing the installation of the drywalls, the on! off switches and their covering is to be installed. 22. HVAC: This activity also progresses along the construction of other activities because it is extended through the two levels of the house. InstaLling the needed ducts and vents for the HVAC system has to be completed before the interior drywalls have been installed. 23. Install Plywood Underlay: This activity is a predecessor to all the finishing activities. 24. Install Stairs. 25. Plumbing Fixtures: This activity also progresses along the construction of other activities because it serves the two levels of the house. The main discharge for the sewage system is always found at the basement floor. The plumbing pipes and water supply pipes/ connections have to be installed before the installation of the drywalls. 26. Window Installation: Before the exterior or interior walls are finished, this activity has to take place. 27. Install Tiles & Ceramic: This activity applies to the washrooms and the kitchen and takes place after the installation of the subfloor. 28. Install Receptacles & Switches: This is the finishing stage of the electrical activity. For this particular project, we assume that “The daily material quantity needed for each method is always equal to the amount of daily production of the crew used. Project Requirements: 1. Contact your local contractors/ subcontractors/ suppliers/ developers and discuss the hourly rates of resources, crew formations, construction methods, and seasonal productivity factors. Make any necessary adjustments to available data. Also, discuss the project, modify the activities and the logic, and estimate quantity of work associated with each activity. Make reasonable assumptions of any missing data. 2. Proceed to the Excel system and enter the project data. Perform the following: a. Determine the project duration when all activities are at their cheapest option. Choose the three key resources (e.g., Ll02) and determine the maximum need of each. b. Optimize the bid proposal when project duration is limited to 80%of the duration in part a, key resources are 90%of the amount used in part a, cash flow needs to be minimized, no subcontractor credit is given, no mobilization payment is given by the owner, indirect cost is $300 per day, liquidated damages are $500per day, markup is 10%, invoices are submitted to owner every week, and seasonal productivity factors are used. c. What is the impact of weekly, biweekly, and monthly invoices on project cost? d. Discuss the results with the same people who helped you with project data and report your findings. e. Use the schedule in part a and use the BALprogram to schedule the work of constructing 10 houses. Project deadline is three times the duration inpart a. Report your findings. Project 2 • This is a highway bridge construction project. The structure to be erected is a 60-footlong single-spanned highway bridge. It is designed as a composite steel-concrete deck-girder type. The following figures show the profile and the cross section of the bridge. • The two abutment walls are made of reinforced concrete; each includes a breast wall and two wing walls. Each abutment wall sits on a concrete footing that is supported by 28, 40-foot-long H-shaped steel piles. The deck slab is lO- inch-thick reinforced concrete pavement supported by four W 36 X 150 steel girders. A steel guardrail is installed along each side of the bridge. All exposed concrete surfaces are to be given a rubbed finish, and specific surfaces are to be painted. • The entire construction project is broken down into 32 activities under three work-breakdown levels, as illustrated in the following figure, which also shows the personnel involved in the supervision of the project activities. John, Paul, and Steve supervise all site-work activities. Sam, Kile, Uma, and Zen supervise all processes related to abutments and footings. Niles and Jerry supervise the construction of the deck and the installation of the girders. Finally, Cramer and Eil supervise the finishing. The figure also shows the network of activity relationships in the project. Project Requirements • Follow requirement 1 under project 1 then conduct a cost estimate and a detailed schedule, select proper methods of construction, prepare optimum bid, and study the impact of seasonal productivity factors on project time and cost. Consider that the contractor has maximum resource limits of four of L12; one of E3, two of L6, and a maximum credit limit is $75,000. A project duration of 45 days is desirable. Discuss your findings. Project 3 • The following garage has been designed with reinforced concrete footings, concrete slab on grade, concrete block bearing walls, offices/lavatories, mezzanine over the offices, bar joists and steel deck, T&G roof, skylights, H.M. doors and frames, and overhead doors. Project Requirements 1. Contact your local contractors/ subcontractors/ suppliers/ developers and discuss the hourly rates of resources, crew formations, construction methods, and seasonal productivity factors. Make any necessary adjustments to available data. Also, discuss the project, define the activities and the logic, and estimate quantity of work associated with each activity. Make reasonable assumptions of any missing data. 2. Proceed to the Excel system and enter the project data. Perform the following: a. Determine the project duration when all activities are at their cheapest option. Choose the three key resources and determine the maximum need of each. b. Optimize the bid proposal when project duration is limited to 80%of the duration in (a), key resources are 90% of the amount used in (a), cash flow needs to be minimized, no subcontractor credit is given, no mobilization payment is given by the owner, indirect cost is $300 per day, liquidated damages are $500 per day, markup is 10%, invoices are submitted to owner every week, and seasonal productivity factors are used. c. What is the impact of weekly, biweekly, and monthly invoices on project cost? d. Discuss the results with the same people who helped you with project data and report your findings. Thank you!