Date : 29 Juli 2022

DAILY REPORT Location : Area Canteen


Page : 18
CANTEEN RENOVATION PROJECT
START DATE 12 Juli 2022
FINISH DATE 30 November 2022
WORK LOCATION/PLANT Area Extention & Temporary Canteen
PTS (M/U Dept.) PTS (General Affair Dept.) CV. RM (Engineer) CV. RM (Spv.)
PERSON IN CHARGE
Mr. Cholisuddin Mr. Indra Junor Ir. Yudi Yulianto A. Munaji

NUMBER OF WORKER SPV Foreman Safety Worker TOTAL


Pekerjaan Beton 1 1 4 6
Pek. Penutup Atap 1 3 4
Pek. Dinding Kalsiboard
Pek. Plafond

DAY SHIFT FROM : 8 AM TO : 5 PM

STATUS
TODAY ACTIVITIES, NEXT ACTIVITIES,
Item Pek. Ttl. Project
• Pek. Balok beton 5,00% 0,12% • Melanjutkan pekerjaan dinding partisi
• Pek. Penutup atap temporary canteen 15,00% 0,38% • Melanjutkan pekerjaan penutup atap
• Pek. Dinding partisi temporary canteen 10,00% 0,20% • Melanjutkan pekerjaan beton
• Pek. Pafond temporary canteen 20,00% 0,22%

Progress of today : 0,91%


Progress of until yesterday : 9,07%
TOTAL : 9,98%

Prepared by : Checked by : Approved by :

Sulistiyo Yudi Yulianto Ahmad Munaji M. Riefky Fakhruddin


(Engineering Spv.) (Production Spv.) (Project Manager)