ID Task Mode Task Name Duration Start Finish Predecessors Resource Names Feb 27, '21

S M

1 All first floor wall demolition and floor tile removal, including all required walls, rem 8 days Mon 3/01/21 Thu 3/11/21
oval of windows

2 Order electrical accessories, materials , plumbing/sanitary accessories, materials a 1 day Sat 3/13/21 Sun 3/14/21 1
nd AC access pipes

3 All Electrical works including removal, re routing, installation of new back boxes, co 7 days Sun 3/14/21 Tue 3/23/21 2
nduit, wiring - first floor

4 All Plumbing works including the removal of exisiting plumbing pipes, replacement b 7 days Sun 3/14/21 Tue 3/23/21 2
y new pipe - first floor, all toilets/wherever required as per contract

5 Order sand, cement for the plastering works 1 day Wed 3/24/21 Thu 3/25/21 4

6 Order tiles for the walls and floor area of first floor 1 day Wed 3/24/21 Thu 3/25/21 4

7 Start plastering works wherever required, make new design for all windows as per d 7 days Thu 3/25/21 Sun 4/04/21 5
rawings - first floor

8 Start and complete laying of wall tiles and floor tiles - first floor 10 days Thu 3/25/21 Thu 4/08/21 6

9 Start and completion of final fix items for electrical and plumbing units - first floor , a 2 days Thu 4/08/21 Mon 4/12/21 8
ll toilets/wherever required as per contract

10 Start and complete the painting works -first floor 5 days Mon 4/12/21 Mon 4/19/21 9

11 All ground floor wall demolition and floor tile removal, including all required walls, re 8 days Mon 4/19/21 Sat 5/01/21 10
moval of windows

12 Order electrical accessories, materials , plumbing accessories, materials and AC a 1 day Mon 4/19/21 Tue 4/20/21 10
ccess pipes

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: msproj11 Split External Tasks Inactive Summary Manual Summary Deadline
Date: 8/3/2020 9:44 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 1
ID Task Mode Task Name Duration Start Finish Predecessors Resource Names Feb 27, '21

S M

13 All Electrical works including removal, re routing, installation of new back boxes, co 7 days Tue 4/20/21 Sat 5/01/21 12
nduit, wiring - ground floor

14 All Plumbing works including the removal of exisiting plumbing pipes, replacement b 7 days Tue 4/20/21 Sat 5/01/21 12
y new pipe -ground floor ,all toilets/wherever required as per contract

15 Order sand, cement for the plastering works 1 day Sat 5/01/21 Sun 5/02/21 13

16 Order tiles for the walls and floor area of ground floor 1 day Sat 5/01/21 Sun 5/02/21 13

17 Start plastering works wherever required, make new design for all windows as per d 7 days Sat 5/01/21 Tue 5/11/21 14
rawings - ground floor

18 Start and complete laying of wall tiles and floor tiles - ground floor 10 days Sun 5/02/21 Mon 5/17/21 16

19 Start and completion of final fix items for electrical and plumbing units - ground floo 2 days Mon 5/17/21 Wed 5/19/21 18
r , all toilets/wherever required as per contract

20 Start and complete the painting works -ground floor 5 days Wed 5/19/21 Wed 5/26/21 19

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: msproj11 Split External Tasks Inactive Summary Manual Summary Deadline
Date: 8/3/2020 9:44 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only