SECTOR R2-BEAUMONDE,
REPORT DATE-05.04.2024
P ROJ ECT RC C S TATUS
BEFORE AFTER
BEFORE AFTER
BEFORE AFTER
Toilet Dado Work- 1st to 9th & 16th to 19th Floor Toilet Dado Work- 1st to 10th & 16th to 20th Floor
Completed, 10th & 15th Floor WIP. Completed, 11th & 15th Floor WIP.
TOWER - 01
BEFORE AFTER
Flat Flooring Work- 1st to 12th & 16th to 19th Flat Flooring Work- 1st to 12th & 14th to 21st
Floor Completed, 13th to 15th Floor WIP Floor Completed, 13th Floor WIP
TOWER - 01
BEFORE AFTER
Flat Gypsum Work- 1st to 21st Floor Completed, Flat Gypsum Work- 1st to 22nd Floor Completed,
TOWER - 02
BEFORE AFTER
BEFORE AFTER
Gypsum Work from 1st to 27th Floor Completed, Gypsum Work from 1st to 27th Floor Completed,
TOWER - 02
BEFORE AFTER
Flooring Work from 1st to 20th Floor Flooring Work from 1st to 23rd Floor Completed,
Completed, 21st Floor WIP. 24th Floor WIP.
TOWER - 02
BEFORE AFTER
- Toilet Tiling – 1st to 20th Floor Completed, 21st - Toilet Tiling – 1st to 23rd Floor Completed, 24th
Floor WIP Floor WIP
TOWER - 02
BEFORE AFTER
- Kitchen Otta- 1st to 16th Floor Completed, - Kitchen Otta- 1st to 16th Floor Completed,
17th to 18th Floor WIP 17th to 18th Floor WIP
TOWER - 03
BEFORE AFTER
BEFORE AFTER
Flat Gypsum – 1st to 20th Floor Completed, 21st Flat Gypsum – 1st to 24th Floor Completed,
to 22nd Floor WIP 25th to 27th Floor WIP
TOWER - 03
BEFORE AFTER
Kitchen Otta – 1st to 24th Floor Completed, Kitchen Otta – 1st to 24th Floor Completed,
25th Floor WIP 25th to 26th Floor WIP
TOWER - 03
BEFORE AFTER
Flat Flooring- 2nd to 5th Floor, 7th to 8th & Flat Flooring- 1st to 19th Floor Completed,
11th to 13th Floor Completed, 6th Floor WIP 20th Floor WIP
TOWER - 03
BEFORE AFTER
Toilet Tiling- 2nd to 7th & 11th to 17th Floor Toilet Tiling- 1st to 19th Floor Completed, 20th Floor
Completed, 8th to 9th Floor WIP WIP
TOWER - 04
BEFORE AFTER
- 20th Slab Pour 1 Casted - 20th Slab Pour 2 Casted, 21st Slab Pour 1 Casted,
- 20th Slab Pour 2 work in Progress. - 21st Slab Pour 2 work in Progress.
- Internal Walls of 17th Floor Completed - Internal Walls of 17th Floor Completed
TOWER - 06
BEFORE AFTER
BEFORE AFTER
- Flat Gypsum – 1st to 14th Floor 90% Completed - Flat Gypsum – 1st to 14th Floor 90% Completed
TOWER - 06
BEFORE AFTER
- Flat Flooring – 3rd to 7th Floor WIP - Flat Flooring – 3rd to 8th Floor WIP
R 2 - T R AN S F O RME R RO O M
BEFORE AFTER
TOWER - 06-PODIUM
THANK YOU!!!