VTP PEGASUS PROJECT

SECTOR R2-BEAUMONDE,

SITE PROGRESS PHOTOS-MAR.24

REPORT DATE-05.04.2024
P ROJ ECT RC C S TATUS

Sr. No. Tower No. Current Status


RCC Work Completed,
1 Tower No.01
Finishing Work in Progress
RCC Work Completed,
2 Tower No.02
Finishing Work in Progress
RCC Work Completed,
3 Tower No.03
Finishing Work in Progress
RCC & Finishing Work Completed, Flat Handing over
4 Tower No.04
Completed
RCC Work Completed,
5 Tower No.05 Finishing Work Completed, M/s. Knight Frank Snagging & De-
snagging WIP.
20th Slab Pour 2 Casted, 21st Slab Pour 1 Casted,
6 Tower No.06 21st Slab Pour 2 work in Progress.
Internal Walls of 17th Floor Completed
RCC & Finishing Work Completed, Flat Handing over
7 Tower No.07
Completed
RCC Work Completed,
8 Tower No.08 Finishing Work Completed, M/s. Knight Frank Snagging & De-
snagging WIP.
24th Slab Pour 1 & 2 Casted, , i.e. Terrace Slab,
9 Tower No.09 OHWT/LMR Bottom slab Completed, Walls WIP,
Internal Wall of 22nd Floor Units 100% Completed
RCC Work Completed,
10 Tower No.10
Finishing Work in Progress
RCC Work Completed,
11 Tower No.11
Finishing Work in Progress
RCC Work Completed,
12 Tower No.12
Finishing Work in Progress
1st, 2nd, 3rd, 4th, 5th, 6th slab 100% slab casted,
'Internal Blockwork, Gypsum, Waterproofing, Tiling Complete,
13 MLCP Building
Top Terrace Amenities WIP,
Basement Formation Completed,
TOWER - 01

RCC Work Completed,

Finishing Work in Progress


TOW E R - 01

BEFORE AFTER

RCC Work Completed, RCC Work Completed,


Finishing Work in Progress
Finishing Work in Progress
TOWER - 01

BEFORE AFTER

- Kitchen Otta- 1st to 13th & 16th to 20th Floor


- Kitchen Otta- 1st to 21st Floor Completed, 22nd Floor WIP
Completed, 14th to 15th Floor WIP
TOWER - 01

BEFORE AFTER

Toilet Dado Work- 1st to 9th & 16th to 19th Floor Toilet Dado Work- 1st to 10th & 16th to 20th Floor
Completed, 10th & 15th Floor WIP. Completed, 11th & 15th Floor WIP.
TOWER - 01

BEFORE AFTER

Flat Flooring Work- 1st to 12th & 16th to 19th Flat Flooring Work- 1st to 12th & 14th to 21st
Floor Completed, 13th to 15th Floor WIP Floor Completed, 13th Floor WIP
TOWER - 01

BEFORE AFTER

Flat Gypsum Work- 1st to 21st Floor Completed, Flat Gypsum Work- 1st to 22nd Floor Completed,
TOWER - 02

'RCC Work Completed,


Finishing Work in Progress
TOWER - 02

BEFORE AFTER

29th Slab Pour 1 & 2 Slab Casted, i.e.Terrace


Slab
'RCC Work Completed,
OHWT/LMR Bottom slab Casted,Top Slab
Complete, Finishing Work in Progress
Internal Wall of 27th Floor Units 100%
Completed
TOWER - 02

BEFORE AFTER

Gypsum Work from 1st to 27th Floor Completed, Gypsum Work from 1st to 27th Floor Completed,
TOWER - 02

BEFORE AFTER

Flooring Work from 1st to 20th Floor Flooring Work from 1st to 23rd Floor Completed,
Completed, 21st Floor WIP. 24th Floor WIP.
TOWER - 02

BEFORE AFTER

- Toilet Tiling – 1st to 20th Floor Completed, 21st - Toilet Tiling – 1st to 23rd Floor Completed, 24th
Floor WIP Floor WIP
TOWER - 02

BEFORE AFTER

- Kitchen Otta- 1st to 16th Floor Completed, - Kitchen Otta- 1st to 16th Floor Completed,
17th to 18th Floor WIP 17th to 18th Floor WIP
TOWER - 03

- 'RCC Work Completed,

- Finishing Work in Progress


TOWER - 03

BEFORE AFTER

- 29th Slab Pour 1 & 2 Slab Casted, i.e.Terrace Slab


- 'RCC Work Completed,
- OHWT/LMR Bottom slab Casted, Top Slab
Complete, - Finishing Work in Progress
- Internal Wall of 27th Floor Units 100% Completed
TOWER - 03

BEFORE AFTER

Flat Gypsum – 1st to 20th Floor Completed, 21st Flat Gypsum – 1st to 24th Floor Completed,
to 22nd Floor WIP 25th to 27th Floor WIP
TOWER - 03

BEFORE AFTER

Kitchen Otta – 1st to 24th Floor Completed, Kitchen Otta – 1st to 24th Floor Completed,
25th Floor WIP 25th to 26th Floor WIP
TOWER - 03

BEFORE AFTER

Flat Flooring- 2nd to 5th Floor, 7th to 8th & Flat Flooring- 1st to 19th Floor Completed,
11th to 13th Floor Completed, 6th Floor WIP 20th Floor WIP
TOWER - 03

BEFORE AFTER

Toilet Tiling- 2nd to 7th & 11th to 17th Floor Toilet Tiling- 1st to 19th Floor Completed, 20th Floor
Completed, 8th to 9th Floor WIP WIP
TOWER - 04

RCC & Finishing Work Completed, Flat Handing over Completed


TOWER - 05

RCC Work Completed,


Finishing Work Completed, M/s. Knight Frank Snagging & De-snagging WIP.
TOWER - 06

- 20th Slab Pour 2 Casted, 21st Slab Pour 1 Casted,

- 21st Slab Pour 2 work in Progress.

- Internal Walls of 17th Floor Completed


TOWER - 06

BEFORE AFTER

- 20th Slab Pour 1 Casted - 20th Slab Pour 2 Casted, 21st Slab Pour 1 Casted,
- 20th Slab Pour 2 work in Progress. - 21st Slab Pour 2 work in Progress.
- Internal Walls of 17th Floor Completed - Internal Walls of 17th Floor Completed
TOWER - 06

BEFORE AFTER

- Kitchen Otta – 3rd to 11th Floor Complete,


- Kitchen Otta – 3rd to 11th Floor Complete
12th Floor WIP
TOWER - 06

BEFORE AFTER

- Flat Gypsum – 1st to 14th Floor 90% Completed - Flat Gypsum – 1st to 14th Floor 90% Completed
TOWER - 06

BEFORE AFTER

- Flat Flooring – 3rd to 7th Floor WIP - Flat Flooring – 3rd to 8th Floor WIP
R 2 - T R AN S F O RME R RO O M

BEFORE AFTER
TOWER - 06-PODIUM