STATUS OF WORK PROGRESS OF OVERHEAD TANK AT KANPUR WATER SUPPLY PROJECT PHASE-II SR.NO. ZONE NO.

EW17 EW13 Sanigwan EW1 TW2 EW4 TW3 EW7 EW10 EW15 Sanigwan Naubasta East Hanspuram Pasupathi Nagar Yashoda Nagar East Yashoda Nagar West LOCATION Shyam Nagr Sujat Ganj Shyam NagarKDA Colony OHST Present Work Status Remarks

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

KL KL KL KL KL KL KL KL KL KL KL KL KL KL KL KL KL KL KL KL KL

800 1600 1100 800 1600 800 1600 1700 1700 1700 600 1700 1600 1300 1300 2100 800 800 1700 800 775

Top Dome Completed and Railing Work Completed. Bottom Dome Completed and Top Dome shuttering in progress. Bottom Dome Completed and Top Dome casting completed. Bottom Dome Completed. Bottom Dome Completed. Above Wall 4th lift completed. Bottom Dome shuttering in progress. Full Staging Completed . Bottom Dome Completed.Top dome completed. Full staging completed Top Dome Completed. Top Dome Completed and Testing completed,Painting Work in progress. Full staging completed Bottom Dome Completed. Bottom dome slab Shuttering in completed and steel in progress. Full staging completed . Bottom dome slab casted and Top dome shuttering in progress. Top Dome Completed and Pipe work completed. Top Dome Completed. Bottom dome slab casted and 2nd lift tank wall shuttering in progress. Excavation is started.(But Hold By Local Public) Top dome slab Completed and Pipe work Completed. Court stay Work Stop due to Court Stay

GW4
SW3 SW9 CW2

Chedising ka Purrwa(Barra)
Naubasta West Bingawan TW+ Barrage Saraimita Dabouli

CW1 GW3 GW1 SW4 Ratan Lal Nagar Gujjaini Colony Barra East-II Barra East-I Tiwaripur jaj mau north Kidwai nagar South Atwa

SR.NO.

ZONE NO.

LOCATION Kalyanpur Sukhnipur Karrahi Chandari Delhi Sujanpur Village Krishnanagar Basant Vihar Chakeri Sekhpur Barra West Safipur Safipur Harjinder nagar

OHST

Present Work Status

Remarks

22 23 24 25 26 27 28 29 30 31 32

KL KL KL KL KL KL KL KL KL KL KL

250 575 700 1700 900 1400 600 500 1400 1000 200

Top dome slab completed. Full staging completed and Bottom Dome salb Shuttering in progress Top Dome completed and Pipe work completed. Raft Completed and Work Completed up to 2nd brace. Top Dome completed and fittings completed. Half Staging Completed. Bottom Dome casting completed. RCC work completed up to GL and column up to second brace completed. Land Not cleared Land Not cleared location changed ,but new location yet not decided.

STATUS OF WORK PROGRESS OF CWR AT KANPUR WATER SUPPLY PROJECT PHASE-II


Sr.No. Location CAPACITY Present Work Status Remarks

SHYAMNAGAR KDA 1 COLONY 2 Shyamnagar Sujat Ganj 3 JAJMAU SOUTH 4 JAJMAU NORTH 5 EAST IPS PHOOL BAGH 6 CWR AT 200 MLD 7 KALYANPUR 8 GANDHIGRAM 9 BARRA EAST-II 10 BARRA GAON 11 Bingawan 12 Yashodanagar East 13 Yashodanagar West 14 Tiwaripur jajmau north 15 Delhi Sujanpur Village 16 IPS Juhi Gaushala 17 Usman pur 18 Gujaini 19 Naubasta east

1000KL 500KL 200KL 200KL 3700KL 4200KL 500KL 540KL 400KL 665KL 1000KL 1000KL 1000KL 1000KL 500KL 1700KL 1000KL 1200KL 1000KL

Third lift wall completed. Top Slab casted and railing work completed. Top Slab of CWR casted. Full wall completed Top Slab of CWR completed. Full wall completed and 80% Top Slab Casting Completed. Top Slab of CWR casted and Railing completed. full Wall Completed . Top Slab of CWR casted . Top Slab of CWR casted. Top Slab of CWR casted. Top Slab of CWR casted. Top Slab of CWR casted. Top Slab of CWR casted and Railing completed. Top Slab of CWR casted. Top Slab of CWR casted. Top Slab of CWR casted and Railing completed. Top Slab of CWR casted. Half Wall Completed

Sr.No.

Location

CAPACITY

Present Work Status

Remarks

20 Saraimita 21 Ompurwa 22 Sanigwan 23 Karhi(200KL) 24 Karhi (400KL) 25 Jarauli 26 Naubasta West 27 Krishna Nagar 28 Safipur Safipur Harijender 29 Nagar 30 Chandari 31 Pasupathi Nagar 32 Kidwai nagar South 33 Basant vihar 34 Barra West 35 Barra East-I 36 Dabouli 37 Ratan Lal Nagar
Chedising ka

1000KL 900KL 700KL 200KL 400KL 200KL 800KL 1000KL 600KL 1000KL 1000KL 900KL 500KL 900KL
800KL 400KL 800KL 800KL

Top Slab of CWR casted. Raft completed. Top Slab of CWR casted and Railing completed. Top Slab of CWR casted and Railing completed. Top Slab of CWR casted and Railing completed. Half Wall Completed Top Slab of CWR casted and Railing completed. Excavation completed. Land not Cleared Land not Cleared Land not Cleared Land not Cleared Land not Cleared CWR Cancelled. Land not Cleared Raft Completed and second lift wall completed. Full Wall Completed. Raft Completed and third lift wall completed. Court Stay Court Stay Court Stay

38 Purrwa(Barra) 39 Ravidas Puram

1000KL Land space problem 200KL

Land not Cleared

STATUS OF WORK PROGRESS OF PUMP HOUSE AT KANPUR WATER SUPPLY PROJECT PHASE-II
Sr.No. Location Area in Sqm Present Work Status Remarks

SHYAMNAGAR KDA 1 COLONY 2 Shyamnagar Sujat Ganj 3 JAJMAU SOUTH 4 JAJMAU NORTH 5 EAST IPS PHOOL BAGH 6 CWR AT 200 MLD 7 KALYANPUR 8 GANDHIGRAM 9 BARRA EAST-II 10 BARRA GAON 11 Bingawan 12 Yashodanagar East 13 Yashodanagar West

96 60 60 60 360 360 80 60 60 60 96 96 96

Work completed up to Plith level and plinth slab completed. Work Completed up to Raft . Work completed of roof slab and finishing work in progress. Old tube well in Area Work completed up to Plith level and plinth slab completed. Work complete up to Ground level. Work completed up to Roof slab. Work Completed up to Roof slab level Work Completed up to Roof slab level roof slab shuttering in progress. Work completed up to Raft level and 3rd lift Wall in progress. Work completed up to plinth slab in progress. Work completed up lintel level.

Sr.No.

Location

Area in Sqm

Present Work Status

Remarks

14 Tiwaripur jajmau north 15 Delhi Sujanpur Village 16 IPS Juhi Gaushala 17 Usman pur 18 Gujaini 19 Naubasta east 20 Saraimita 21 Ompurwa 22 Sanigwan 23 Karhi 24 Karhi 25 Jarauli 26 Naubasta West 27 Krishna Nagar 28 Safipur Safipur Harijender 29 Nagar 30 Chandari 31 Pasupathi Nagar 32 Kidwai nagar South 33 Basant vihar

96 60 250 96 96 96 96 96 60 60 60 60 60 96 60 96 96 96 60 96

Land problem due to OHT Work completed up lintel level. Work completed up to plinth level slab in progress. Work completed up Plinth level. Work completed of raft and lintel level completed. Work completed up to Raft level and 3rd lift Wall in progress. Plinth slab shuttering in progress. Filled up soil at site Excavation and PCC Completed and Raft completed and third lift in progress. Work completed lintel level Hindrance problem due to pipe Work will Start in month of August 2011. Work completed up lintel level. Filled up soil at site Land not Cleared Land not Cleared Court Stay Court Stay Court Stay Already pump house existing.

Sr.No.

Location

Area in Sqm

Present Work Status

Remarks

34 Barra West 35 Barra East-I 36 Dabouli 37 Ratan Lal Nagar


Chedising ka 38 Purrwa(Barra)

60 60 60 60 96 60

Land not Cleared Work completed up Raft level. Work will Start in month of August 2011. Work will Start in month of August 2011. Land Space problem Land not cleared.

39 Ravidas Puram

STATUS OF WORK PROGRESS OF HT ROOM AT KANPUR WATER SUPPLY PROJECT PHASE-II


Sr.No. Location Area in Sqm Present Work Status Remarks

SHYAMNAGAR KDA 1 COLONY 2 Shyamnagar Sujat Ganj 3 JAJMAU SOUTH 4 JAJMAU NORTH 5 EAST IPS PHOOL BAGH 6 CWR AT 200 MLD 7 KALYANPUR 8 GANDHIGRAM 9 BARRA EAST-II 10 BARRA GAON 11 Bingawan 12 Yashodanagar East 13 Yashodanagar West

22 22 22 22 22 22 22 22 22 22 22 22 22

Work Completed up to Roof slab and plaster completed. Work Completed up to Roof slab and plaster completed. Excavation statred Work Completed up to Roof level. Work Completed up to Roof level. Work will Start in month of August 2011. Work Completed up to slab level and door and windows completed. Work Completed up to Roof level. Work completed up to Roof Slab and plaster completed. Work Completed up to Roof slab level. Work Completed up to Roof slab level. Land space problem due to pump house Labour hutment problem

Sr.No.

Location

Area in Sqm

Present Work Status

Remarks

14 Tiwaripur jajmau north 15 Delhi Sujanpur Village 16 IPS Juhi Gaushala 17 Usman pur 18 Gujaini 19 Naubasta east 20 Saraimita 21 Ompurwa 22 Sanigwan 23 Karhi 24 Karhi 25 Jarauli 26 Naubasta West 27 Krishna Nagar 28 Safipur Safipur Harijender 29 Nagar 30 Chandari 31 Pasupathi Nagar 32 Kidwai nagar South 33 Basant vihar 34 Barra West

22 22 22 22 22 22 22 22 22 22 22 22 22 22 22 22 22 22 22 22 22

Land problem due to OHT Work Completed up to Roof slab and plaster completed. Work Completed up to Lintel level. Work completed up to roof slab level Land problem due to OHT Work Completed up to Raft. Work will Start in month of August 2011. Work Completed up to Roof slab and plaster completed. Work Completed up to Roof slab and plaster completed. Work completed up to plinth level Hindrance problem due to pipe Work will Start in month of August 2011. Work Completed up to Roof slab and plaster completed. Filled up soil at site Land not Cleared Land not Cleared Court Stay Court Stay Court Stay Work Completed up to Lintel level. Land not Cleared

Sr.No.

Location

Area in Sqm

Present Work Status

Remarks

35 Barra East-I 36 Dabouli 37 Ratan Lal Nagar


Chedising ka 38 Purrwa(Barra)

22 22 22 22 22

Excavation started Work Completed up to Roof slab . Work will Start in month of August 2011. Land Space problem Land not cleared.

39 Ravidas Puram

STATUS OF WORK PROGRESS OF LT ROOM AT KANPUR WATER SUPPLY PROJECT PHASE-II


Sr.No. Location Area in Sqm Present Work Status Remarks

SHYAMNAGAR KDA 1 COLONY 2 Shyamnagar Sujat Ganj 3 JAJMAU SOUTH 4 JAJMAU NORTH 5 EAST IPS PHOOL BAGH 6 CWR AT 200 MLD 7 KALYANPUR 8 GANDHIGRAM 9 BARRA EAST-II 10 BARRA GAON 11 Bingawan 12 Yashodanagar East 13 Yashodanagar West

16 16 16 16 16 16 16 16 16 16 16 16 16

Work Completed up to Roof slab and plaster completed. Work Completed up to Roof slab and plaster completed. Excavation statred Work Completed up to Roof level. Work Completed up to Roof level. Work will Start in month of August 2011. Work Completed up to slab level and door and windows completed. Work Completed up to Roof level. Work completed up to Roof Slab and plaster completed. Work Completed up to Roof slab level. Work Completed up to Lintel level. Land space problem due to pump house Labour hutment problem

Sr.No.

Location

Area in Sqm

Present Work Status

Remarks

14 Tiwaripur jajmau north 15 Delhi Sujanpur Village 16 IPS Juhi Gaushala 17 Usman pur 18 Gujaini 19 Naubasta east 20 Saraimita 21 Ompurwa 22 Sanigwan 23 Karhi 24 Karhi 25 Jarauli 26 Naubasta West 27 Krishna Nagar 28 Safipur Safipur Harijender 29 Nagar 30 Chandari 31 Pasupathi Nagar 32 Kidwai nagar South 33 Basant vihar 34 Barra West

16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16

Land problem due to OHT Work Completed up to Roof slab level. Excavation completed. Work completed up to roof slab level Land problem due to OHT Excavation completed. Work will Start in month of August 2011. Work Completed up to Roof slab and plaster completed. Work Completed up to Roof slab. Work will Start in month of August 2011. Hindrance problem due to pipe Work will Start in month of August 2011. Work Completed up to Roof slab. Filled up soil at site Land not Cleared Land not Cleared Court Stay Court Stay Court Stay Excavation completed. Land not Cleared

Sr.No.

Location

Area in Sqm

Present Work Status

Remarks

35 Barra East-I 36 Dabouli 37 Ratan Lal Nagar


Chedising ka 38 Purrwa(Barra)

16 16 16 16 16

Excavation started Work Completed up to Roof slab . Work will Start in month of August 2011. Land Space problem Land not cleared.

39 Ravidas Puram

STATUS OF WORK PROGRESS OF METER ROOM AT KANPUR WATER SUPPLY PROJECT PHASE-II
Sr.No. Location Area in Sqm Present Work Status Remarks

SHYAMNAGAR KDA 1 COLONY 2 Shyamnagar Sujat Ganj 3 JAJMAU SOUTH 4 JAJMAU NORTH 5 EAST IPS PHOOL BAGH 6 CWR AT 200 MLD 7 KALYANPUR 8 GANDHIGRAM 9 BARRA EAST-II 10 BARRA GAON 11 Bingawan 12 Yashodanagar East 13 Yashodanagar West

9 9 9 9 9 9 9 9 9 9 9 9 9

Work Completed up to Roof slab and plaster completed. Work Completed up to Roof slab and plaster completed. Excavation statred Work Completed up to Roof level. Work Completed up to Roof level. Work will Start in month of August 2011. Work Completed up to slab level and door and windows completed. Work Completed up to Roof level. Work completed up to Roof Slab and plaster completed. Work Completed up to Roof slab level. Work Completed up to Lintel level. Land space problem due to pump house Labour hutment problem

Sr.No.

Location

Area in Sqm

Present Work Status

Remarks

14 Tiwaripur jajmau north 15 Delhi Sujanpur Village 16 IPS Juhi Gaushala 17 Usman pur 18 Gujaini 19 Naubasta east 20 Saraimita 21 Ompurwa 22 Sanigwan 23 Karhi 24 Karhi 25 Jarauli 26 Naubasta West 27 Krishna Nagar 28 Safipur Safipur Harijender 29 Nagar 30 Chandari 31 Pasupathi Nagar 32 Kidwai nagar South 33 Basant vihar 34 Barra West

9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9

Land problem due to OHT Work Completed up to Roof slab level. Excavation completed. Work completed up to roof slab level Land problem due to OHT Excavation completed. Work will Start in month of August 2011. Work Completed up to Roof slab and plaster completed. Work Completed up to Roof slab. Work will Start in month of August 2011. Hindrance problem due to pipe Work will Start in month of August 2011. Work Completed up to Roof slab. Filled up soil at site Land not Cleared Land not Cleared Court Stay Court Stay Court Stay Excavation completed. Land not Cleared

Sr.No.

Location

Area in Sqm

Present Work Status

Remarks

35 Barra East-I 36 Dabouli 37 Ratan Lal Nagar


Chedising ka 38 Purrwa(Barra)

9 9 9 9 9

Excavation started Work Completed up to Roof slab . Work will Start in month of August 2011. Land Space problem Land not cleared.

39 Ravidas Puram

STATUS OF CHAUKIDAR HUT AT KANPUR WATER SUPPLY PROJECT PHASE-II


Sr.No. Location No.s Area Work Status Remarks

Jajmau South (EW-9)

1
Jajmau North (EW-14)

NO. NO.
Shyamnagar Sujat ganj

10 10 10 10 10 10 10 10 10 10 10 10

Location changed by jal sansthan(new layout drawing to be submitted) Work completd up to lintel level.

2 3
Ompurwa

NO. NO.
Gandhigram

Work will Start in month of August 2011. RCC of Roof Slab Completed . Work will Start in month of August 2011. Work will Start in month of August 2011. court Stay for land Work will Start in month of August 2011. Land Space problem Land Space problem Work will Start in month of August 2011. Work will Start in month of August 2011.

4 5
Shyamnagar KDA

NO. NO.
Pashupati nagar

6 7
Kalyan pur

NO. NO.
Yashodanagar East

8 9
Naubasta East

NO. NO.
Naubasta West

10 11
Bingawan TW+ Barrage

NO. NO.

12

Sr.No.

Location

No.s

Area

Work Status

Remarks

Sanigwan

13
Yashodanagar West

NO. NO.
Barra East-II

10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10

Work will Start in month of August 2011. Work will Start in month of August 2011. RCC of Roof Slab Completed and plaster completed. RCC of Roof Slab Completed . Work Completed up to Lintel level. Work Completed up to Lintel level. RCC of Roof Slab Completed . Work will Start in month of August 2011. Work Completed up to roof slab level. RCC of Roof Slab Completed and plaster completed. RCC of Roof Slab Completed and plaster completed.
Filled up soil Land not cleared Land not cleared Land space problem due to OHT. Court Stay for land

14 15
Barra Gaon

NO. NO.
Saraimita

16 17
Jarauli

NO. NO.
Usmanpur Ratanlalnagar Dabouli

18 19 20 21
Karhi-1

NO. NO. NO. NO. NO.

22
Karhi-2

23 24 25 26 27 28 29
Krishna Nagar Safipur Safipur Harijender Nagar Tiwari pur Jajmou North Chandari East IPS Phool baug

NO. NO. NO. NO. NO. NO.

Land Problem due to Pump house

Sr.No.

Location

No.s

Area

Work Status

Remarks

30 31 32 33 34 35 36 37 38 39 40

Hanspuram Delhi Sujanpur KDA Colony Kidwai Nagar South South IPS - JUHI GAUSHALA Basant Bihar Sanigwan Chedising ka Purrwa(Barra) Barra West Barra East-I Gujjaini Colony Ravidas Puram

NO. NO. NO. NO. NO. NO. NO. NO. NO. NO. NO.

10 10 10 10 10 10 10 10 10 10 10

To be finalised by UP Jal nigam

Work will Start in month of August 2011.


Land not cleared

Work will Start in month of August 2011. Work will Start in month of August 2011. Work will Start in month of August 2011.
Land Space problem Land not cleared

Work will Start in month of August 2011.


Space problem due to OHT Land not cleared

STATUS OF WORK PROGRESS OF TUBE WELL AT KANPUR WATER SUPPLY PROJECT PHASE-II
Sr.No. Location Present Work Status Remarks

1 Hanspuram(tadakpur) 2 Bingawan(Asha Devi temple) 3 Bingawan(Primary School) 4 Hanspuram (OHST site) 5 Sanigwan-II 6 Bingawan 7 Tulsiapur(Bingawan) 8 Sukhnipur 9 Chakeri,Atwa 10 Chakeri,Atwa-II 11 Chaeri khajuria-2 12 Chakeri Sekhpur

Bore Completed and Pipe Casing Completed and Wash of Water completed. Bore Completed and Pipe Casing Completed and Wash of Water completed. Bore Completed and Pipe Casing Completed and Wash of Water completed. Bore Completed and Pipe Casing Completed and Wash of Water completed. Bore Completed and Pipe Casing Completed and Wash of Water completed. Boring work not started due to Passage problem Location cancelled Boring Completed and Pipe lowering completed. Final Testing completed and Civil work of Pump house started. Final Testing completed and Civil work of Pump house started. Boring Completed and Pipe lowering completed. Boring Completed and Pipe lowering completed.

STATUS OF WORK PROGRESS OF TUBE WELL PUMP M AT KANPUR WATER SUPPLY PROJECT PHASE-II
Sr.No. Location Present Work Status Remarks

1 Bingawan(ashadevi temple) 2 Hanspuram (todak pur) 3 Hanspuram 4 Chakeri kulgaon 5 Ckakeri Sukhnipur 6 Ckakeri Trilok pur 7 Chakeri Sekhpur 8 Chaeri khajuria-2 9 Bingawan(primary school) 10 Sanigawan-II 11 Bingawan 12 Tulsiapur(Bingawan)

Finishing(painting) completed. RCC Slab Completed and Plaster completed and handover completed to UP jal nigam RCC Slab Completed and Plaster completed and handover completed to UP jal nigam Finishing(painting) completed. Boring work in progress Finishing(painting) completed. Boring work completed. Work completed up to slab level. Finishing(painting) completed. RCC Slab Completed and Plaster work completed. Finishing(painting) completed. Location cancelled

STATUS OF RESIDENTIAL BUILDING AT KANPUR WATER SUPPLY PROJECT PHASE-II


Sr.No. Zone Location No.s Area Work Status Remarks

Jajmau South (EW-9)

1
Jajmau North (EW-14)

NO. NO.
Shyamnagar Sujat ganj

34.2 34.2 34.2 34.2 34.2 34.2 34.2 34.2 34.2 34.2 34.2 34.2 34.2

Finishing completed Finishing completed Finishing completed Roof slab completed. Finishing completed Finishing under progress Finishing completed Finishing completed Finishing completed Finishing completed Finishing completed Finishing completed Finishing completed

2 3
Ompurwa

NO. NO.
Gandhigram

4 5
Shyamnagar KDA

NO. NO.
Pashupati nagar

6 7
Kalyan pur

NO. NO.
Yashodanagar East

8 9
Naubasta East

NO. NO.
Naubasta West

10 11
Bingawan TW+ Barrage

NO. NO.
Sanigwan

12 13

NO.

Sr.No.

Zone

Location

No.s

Area

Work Status

Remarks

Yashodanagar West

14
Barra East-II

NO. NO.
Barra Gaon

34.2 34.2 34.2 34.2 34.2 34.2 34.2 34.2 34.2 34.2 34.2 34.2 34.2 34.2 34.2 34.2 34.2 34.2 34.2 34.2

Finishing completed Finishing completed Finishing completed Finishing completed Finishing completed Finishing completed Finishing completed Finishing completed Finishing completed Finishing completed
Work completed up to roof slab level Land not cleared Land not cleared Land space problem due to OHT. Court Stay for land

15 16
Saraimita

NO. NO.
Jarauli

17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33
Usmanpur Ratanlalnagar Dabouli Karhi-1 Karhi-2 Krishna Nagar Safipur Safipur Harijender Nagar Tiwari pur Jajmou North Chandari Hanspuram Kidwai Nagar South South IPS - JUHI GAUSHALA Basant Bihar Sanigwan

NO. NO. NO. NO. NO. NO. NO. NO. NO. NO. NO. NO. NO. NO. NO. NO.

Work will Start in month of August 2011.


Land not cleared

Work will Start in month of August 2011. Work will Start in month of August 2011. Work will Start in month of August 2011.

Sr.No.

Zone

Location

No.s

Area

Work Status

Remarks

34 35 36 37 38 39 40

Chedising ka Purrwa(Barra) Delhi sujanpur Gujjaini Colony Ravidas Puram Chakeri kalyanpur Chakeri Atwa Chakeri sekhpur

NO. NO. NO. NO. NO. NO. NO.

34.2 34.2 34.2 34.2 34.2 34.2 34.2

Land Space problem Work Completed up to roof slab level excavation completed. Land not cleared Work Completed up to lintel level Work Completed up to roof slab level Work completed up to lintel level

STATUS OF BOUNDARY WALL AT KANPUR WATER SUPPLY PROJECT PHASE-II


SR.NO. LOCATION Work Status Remarks

Shayamnagar KDA 1 Chakeri Atwa(kulgaon) 2 Chakeri Atwa(trilokpur) 3 Chakeri Kalyanpur 4 Chakeri Atwa 5 Shyanagar Sujatganj 6 Gandhigram 7 Pashupatinagar 8 9 10 11 12 Hanspuram Naubasta East Sanigwan Yashodanagar West Bk work up to coping about 219 RM is completed Bk work up to coping about 149 RM is completed Bk work up to coping about 60 RM is completed Bk work up to coping about 145 RM is completed Bk work up to coping about 210 RM is completed Bk work up to coping about 110 RM is completed Bk work up to coping about 222 RM is completed Bk work up to coping about 133 RM is completed Bk work up to coping about 112 RM is completed Bk work up to coping about 52 RM is completed Bk work up to coping about 85 RM is completed Bk work up to coping about 189 RM is completed

13

Yashodanagar East Ganga Barrage

Bk work up to coping about 172 RM is completed

14 15 Barragaon 16 Saraimita 17 Barra East-II

Bk work up to coping about 119.50 RM is completed Bk work up to coping about 260 RM is completed Bk work up to coping about 357 RM is completed Bk work up to coping about 240 RM is completed

SR.NO.

LOCATION

Work Status

Remarks

18 Karhi-1 19 Dabouli 20 Chakeri Sekhpur (khujria) 21 Gujaini

Bk work up to coping about 370 RM is completed Bk work up to coping about 70 RM is completed Bk work up to coping about 45 RM is completed Bk work up to coping about 70 RM is completed

STATUS FOR GA DRAWINGS AND STRUCTURAL DRAWINGS FOR 200 MLD WTP & INTAKE
Sr. No. Drawing No Description Sheet Revision Design & Drawing Work in progress Remarks

RIL/09-01/R0/09/WTP200/civil -102

Inlet Works

01 nos

Approved fm IIT

Silt Excluder With Raft and Columns up to Base Slab Completed and Inlet Channel Footings and Plinth Beam And Column Completed 2 No's Clarifiers ready for errection,3rd clarifier only 10% Work remaning,4th Clarifier Launder base Slab casting in progress. RCC Work up to header base Channel Completed and Filter bed Casting in progress.

RIL/09-01/R0/09/WTP200/civil -103

Clariflocculator

01 nos

Approved fm IIT

RIL/09-01/R0/09/WTP200/civil -104 RIL/09-01/R0/09/WTP200/civil -105 RIL/09-01/R0/09/WTP200/civil -105 RIL/09-01/R0/09/WTP200/civil -106 RIL/09-01/R0/09/WTP200/civil -107 RIL/09-01/R0/09/WTP200/civil -108 RIL/09-01/R0/09/WTP200/civil -109

Filter House

04 nos

Approved fm IIT

Clear Water Reserviours

01 nos

Approved fm IIT

Top Slab of CWR Casting completed Work completed up to ground Floor Slab .

Pump House for 4200KL

01 nos

Approved fm IIT

Chlorine Tonner Shed.

01 nos

Approved fm IIT

Brick masonary and Roof Shed Completed and Plaster work Completed RCC of First Floor and Slab Completed and Second floor Slab Shuttering in progress Excavation and PCC,RaftCompleted of one tank . About 119 Rm is completed up to coping

7 8 9 10

Chemical House Settling Tank with pump huose

01 nos 01 nos

0 0 0

Approved fm IIT Approved fm IIT Approved fm IIT

HT, LT Transformer room 01 nos Boundry wall with piles Boundry wall without piles 120 Rm 500 Rm

Received from Jal Nigam Received from Jal Nigam

STATUS FOR GA DRAWINGS AND STRUCTURAL DRAWINGS FOR INTAKE


Sr. No. Drawing No Description Sheet Revision Work in progress

RIL/09-01/R0/09/WTP200/civil -101

Intake for 200 MLD

02 nos

Approved fm IIT

Ground Floor Slab Completed and Columns Completed up to Bracket level ,Brick masonry in progress

Sr. No.

Drawing No

STATUS FOR GA DRAWINGS AND STRUCTURAL DRAWINGS FOR 28.5 MLD WTP Description Sheet Revision Remarks First Clarifier is ready for Errection, Second Clarifier only 10% Work remaining for Errection Approved fm IIT 1 0 Approved fm IIT Work Completed up to Slab Bottom and Slab Shuttering in progress

1 2

RIL/09-01/R0/09/WTP- Clariflocculator 01 nos 28.5/civil -101 Inlet / Outlet Plan for Clariflocculator 01 nos RIL/09-01/R0/09/WTP28.5/civil -102 RIL/09-01/R0/09/WTP28.5/civil -103 RIL/09-01/R0/09/WTP28.5/civil -104 RIL/09-01/R0/09/WTP28.5/civil -105

Filter House

04 nos

Approved fm IIT

RCC Work Completed up to Filter Bed and Wall Above filter bed in progress Top roof Slab Casted. Bk masonary completed up to First slab. RCC Wall Completed up to Top of One settling Tank and Recirculation pump House Raft Completed

4 5 6

Chemical House Settling Tank with pump huose HT, LT Transformer room

01 nos 01 nos

0 0 0

Approved fm IIT Approved fm IIT

RAMKY INFRA STRUCTURE LIMITED KANPUR WATER SUPPLY PROJECT Pipe Laying Status Date:- 25.10.2011
SR NO Description of Pipe BOQ Quantity Quantity Received Laying Completed Remarks

PSC Pipes
1 2 3 4 5 6 7 8 9 10 11 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm 1100 mm 1400 mm 1500mm Total 3846 2342 530 1600 6881 5226 2750 970 350 6000 9075 1100 40670 16385 5835 3972 26192 26026 1929 1086 1249 687 551 332 106 55 32021 7160 3600 10760 35100 40373 22227 17822 10736 3424 1767 532 131981 841492 43136 19244 903872 3990.0 2695.0 590.0 1350.0 6880.0 5210.0 2750.0 740.0 270.0 5560.0 8140.0 1100 39275.0 16385 5835 3972 26192 26005.5 1929 1134 1247 685.5 539 328.5 102 54 32024.5 7160 3600 10760 35080 40360 22227 17810 10720 3424 1767 532 131920 818961 43136 19244 881341 3100 1415 320 0 4125 4290 2267 545 255 1500 2250 950 21017 5872 3452 3816 13140 2104.5 1003.5 808 1096 657 530 50 100 0 6349 3028 3085 6113 26878 28168 21254 9743 4945 1959 1454 60 94461 743937 32954 13177 790068 201315 1845 1280 204440

GRP Pipes
12 13 14 350 mm 400 mm 450 mm Total

DI Pipes (K-7)
15 16 17 18 19 20 21 22 23 100 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm Total

DI Pipes (K-9)
24 25 250 mm 300 mm Total

AC Pipes
26 27 28 29 30 31 32 33 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm Total

PVC Pipes
34 35 36 110 mm 140 mm 160 mm Total

STATUS FOR GA DRAWINGS AND STRUCTURAL DRAWINGS FOR 200 MLD WTP & INTAKE
Sr. No. Drawing No Description Sheet Revision Design & Drawing Work in progress

RIL/09-01/R0/09/WTP200/civil -102

Inlet Works

01 nos

Approved fm IIT

RIL/09-01/R0/09/WTP200/civil -103 RIL/09-01/R0/09/WTP200/civil -109 RIL/09-01/R0/09/WTP200/civil -104 RIL/09-01/R0/09/WTP200/civil -105 RIL/09-01/R0/09/WTP200/civil -105 RIL/09-01/R0/09/WTP200/civil -106 RIL/09-01/R0/09/WTP200/civil -107 RIL/09-01/R0/09/WTP200/civil -108 RIL/09-01/R0/09/WTP200/civil -109

Clariflocculator

01 nos

Approved fm IIT

4 5 6 7

Inlet / Outlet Plan for Distribution Chamber/ Filter House Clear Water Reserviours

01 nos 04 nos 01 nos

0 1 1

Approved fm IIT Approved fm IIT Approved fm IIT

Pump House for 4200KL

01 nos

Approved fm IIT

7 8 9

Chlorine Tonner Shed. Chemical House Settling Tank with pump house HT, LT Transformer room Boundry wall with piles Boundry wall without piles

01 nos 01 nos 01 nos

0 0 0

Approved fm IIT Approved fm IIT Approved fm IIT

10 11

01 nos 120 Rm 500 Rm

Approved fm IIT Received from Jal Nigam Received from Jal Nigam

Sr. No. 1 2

STATUS FOR GA DRAWINGS AND STRUCTURAL DRAWINGS FOR 28.5 MLD WTP Description Sheet Revision Clariflocculator 01 nos 1 Inlet / Outlet Plan for RIL/09-01/R0/09/WTPApproved fm IIT Clariflocculator 01 nos 0 28.5/civil -101 Drawing No RIL/09-01/R0/09/WTP28.5/civil -102 RIL/09-01/R0/09/WTP28.5/civil -103 RIL/09-01/R0/09/WTP28.5/civil -104 RIL/09-01/R0/09/WTP28.5/civil -105

Remarks

3 4 5

Filter House Chemical House

04 nos 01 nos

1 0 0

Approved fm IIT Approved fm IIT Approved fm IIT

Settling Tank with pump 01 nos huose HT, LT Transformer room

STATUS OF OVERHEAD TANK DESIGN DRAWING AT KANPUR WATER SUPPLY PROJECT PHASE-II
SR.NO.ZONE NO. LOCATION OHST Design & Drawings of OHST Remarks

TW1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

Chakeri OHST

EW2 EW3 EW5 EW11 EW17 EW13 EW16 EW1 TW2 EW4 TW3 EW7 EW8 EW10 EW15 SW1 SW3 SW9 CW2 CW1 GW3 GW4 GW1 GW2 GW5 SW4 SW6

Atwa Krishna Nagar Safipur Safipur Harijender Nagar Tiwari pur Jajmou North Shyam Nagr Sujat Ganj Shyam NagarKDA Colony Chandari Sanigwan Sanigwan Naubasta East Hanspuram Pasupathi Nagar Delhi Sujanpur Village Yashoda Nagar East Yashoda Nagar West Kidwai Nagar South Naubasta West Bingawan TW+ Barrage Saraimita Dabouli Ratan Lal Nagar Chedising ka Purrwa(Barra) Gujjaini Colony Barra West Barra East-I Barra East-II Karrhi 1
Total OHT Total Land Cleared Not cleared land Land Cleared But Public Hindrance no space for OHT Total Drawings Approved

500 250 575 775 1200 1000 200 1700 800 1600 1700 1100 800 1600 800 1600 900 1700 1700 800 600 1700 1600 1300 1300 1700 2100 1400 800 800 700
31 25 4 1 1 26

In progress Approved From IIT Delhi Approved From IIT Delhi Approved From IIT Delhi In progress

Approved From IIT Delhi on 30.04.2010 Approved From IIT Delhi on 15.03.2010 Approved From IIT Delhi on 15.03.2010 Approved From IIT Delhi( TO BE REVISED) Approved From IIT Delhi Approved From IIT Delhi Approved From IIT Delhi on 30.04.2010 Approved From IIT Delhi on 30.04.2010 Approved From IIT Delhi on 30.04.2010 Approved From IIT Delhi Approved From IIT Delhi on 30.04.2010 Approved From IIT Delhi on 30.04.2010 Approved From IIT Delhi Approved From IIT Delhi Approved From IIT Delhi on 30.04.2010 Approved From IIT Delhi on 30.04.2010 Approved From IIT Delhi on 30.04.2010 Approved From IIT Delhi on 30.04.2010 Approved From IIT Delhi Approved From IIT Delhi Land Not Cleared Approved From IIT Delhi Approved From IIT Delhi on 30.04.2010 Approved From IIT Delhi

STATUS OF CWRS DESIGN DRAWING AT KANPUR WATER SUPPLY PROJECT PHASE-II


LOCATION SR.NO.ZONE NO. CWR Design & Drawings of CWR Remarks

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

EW2 EW3 EW5 EW11 EW17 EW13 EW16 EW06 EW09 EW12 EW14

Krishna Nagar Safipur Safipur Harijender Nagar Tiwari pur Jajmou North Shyam Nagr Sujat Ganj Shyam NagarKDA Colony Chandari Ompurwa Jajmou South Gandhi Gram Jajmau North East IPS Phool baug

NO. NO. NO. NO. KL KL NO. NO. KL KL KL KL NO. KL KL NO. KL KL

1000 600 1000 1000 500 1000 1000 900 200 540 200 3700 700 1000 900 500 1000 1000 Approved From IIT Delhi Approved From IIT Delhi on 30.04.2010 Approved From IIT Delhi on 30.04.2011 Approved From IIT Delhi on 30.04.2010 Approved From IIT Delhi on 15.03.2010 Approved From IIT Delhi Approved From IIT Delhi Approved From IIT Delhi Approved From IIT Delhi Approved From IIT Delhi Approved From IIT Delhi Approved From IIT Delhi Approved From IIT Delhi on15.03.2010 Approved From IIT Delhi on 15.03.2010

EW1 EW4 EW7 EW8 EW10 EW15

Sanigwan Naubasta East Pasupathi Nagar Delhi Sujanpur village Yashoda Nagar East Yashoda Nagar West

19 20 21 22 23 24 25 26 27

SW1 SW3

Kidwai Nagar South Naubasta West South IPS - JUHI GAUSHALA Cw pump House at Barrage IPS Juhi Gaushala

NO. NO. NO. KL KL KL KL NO. KL

500 800 1700 4200 1700 500 1000 900 1000 Approved From IIT Delhi Approved From IIT Delhi Approved From IIT Delhi Approved From IIT Delhi on 27.03.2010 Approved From IIT Delhi Approved From IIT Delhi on 15.03.2010 Approved From IIT Delhi Public Hindrance for

CW3 SW9 SW2 CW2

Kalyanpur Bingawan TW+ Barrage Basant Bihar Saraimita Dabouli

28 29 30 31 32 33

CW1 GW3 GW4 GW1 GW2 GW5 Ratan Lal Nagar Chedising ka Purrwa(Barra) Gujjaini Colony Barra West Barra East-I Barra East-II

KL NO. NO. KL NO. NO.

800 800 1000 1200 800 400

Approved From IIT Delhi

Approved From IIT Delhi Approved From IIT Delhi

34 35 36

SW4 SW6 SW5 Karrhi 1 Karrhi 2

KL KL KL

400 400 200

Approved From IIT Delhi Approved From IIT Delhi Approved From IIT Delhi

Usmanpur 37 38 39 40 GW6 SW7 SW10 SW8 Barra Gaon Ravidas Puram Jarauli Total CWR Total Land Cleared Not cleared land Land Cleared But Public Total Drawings Approved KL KL KL KL NO. NO. NO. NO. NO. 1000 665 200 200 40 31 5 4 31 Approved From IIT Delhi Approved From IIT Delhi Approved From IIT Delhi Approved From IIT Delhi

STATUS OF HINDRANCES OF AT KANPUR WATER SUPPLY PROJECT PHASE-II

BARRAGE DIVISION
PART-1(OVERHEAD TANK)
SR.NO. ZONE NO.
1 2

LOCATION
CHAKERI-1(Sekhpur) Safipur

CAPACITY
500 KL 1000 kL

LAND STATUS
Land Not Cleared. Land Not Cleared. Location changed But in new location Still Land not cleared

Remarks
Not Cleared By KDA No New Land Identified

TW1 EW3

Safipur Harjinder Nagar


3

200 KL

Public Hindrance

PART-2 (CLEAR WATER RESERVOIR)


1 2

EW3 EW5

Safipur Safipur Harijender Nagar

600KL 1000KL

Land Not Cleared. Land Not Cleared.

No New Land Identified Public Hindrance

PART-3 ( PIPELINE) PARTICULARS HINDRANCE


All the areas of Chakeri Atwa,Sukhnipur,Sekhpur,Gandhigram, Harjindernagar,Safipur,Chandari,krishnnagar Pipeline laying Permision still not received from UP Jal Nigam PSC Pipeline Laying Permission From Phoolbagh to Power house ,Power house to Rama Devi Still permission not Received From PWD and UP Jal Nigam Land not Cleared for Sekhpur Tube well . Approach road to Take Driiling Machine for one location Sukhnipur Tubewell is not possible.

PVC AND AC PIPE LINE PSC PIPE LINE

Tubewell
3

Tubewell 4
5

Road Crossing (Rama Devi Churaha)

Rail Crossing
6

SafipurZPS Land Clearance still not recived From UP Jal Nigam as we Have completed already Four Road Crossing out of Five Crossing , so this Crossing is pending only due to land Clearance. We have got Land Clearance and Design and Drawing Approval From Railway Authority for Jaipuria Crossing But Still We not able to start due To deposit amount for lease still not paid by UP Jal Nigam

STATUS OF HINDRANCES OF AT KANPUR WATER SUPPLY PROJECT PHASE-II


CONSTRUCTION DIVISION PART-1(OVERHEAD TANK)
SR.NO. 1 ZONE NO. GW2 LOCATION Barra West CAPACITY 1400 KL LAND STATUS Land Not Cleared. Remarks Public Hindrance

PART-2 (CLEAR WATER RESERVOIR)


1 2 3 4 GW3 GW4 GW2 Ratan Lal Nagar Chedising ka Purrwa(Barra) Barra West Ravidaspuram 800KL 1000KL 800KL 200KL Land Space Problem Land Space Problem Land Not Cleared. Land Not Cleared. Public Hindrance Public Hindrance(sukram singh yadav)

PART-3 ( PIPELINE)
PARTICULARS
PVC AND AC PIPE LINE 1 PSC PIPE LINE 2 PSC PIPE LINE 3

HINDRANCE
Bitumen and Cement Road is not allowed by Local Public & nagar Nigam in all areas. PSC Pipeline Laying Permission Still Not Received From UP Jal Nigam.(nagarnigam,PWD,NHAI,KDA) Barragaon,ravidaspuram,karahi,saraimita for all areas Indian oil Corporation permission still required

PART-4 ( 28.5MLD WTP ) PARTICULARS


1 LAND CLEARANCE

HINDRANCE
Continue Water Leakage from Exsiting Filter house ,so it is very hard to work

CONSTRUCTION DIVISION- III


PART-1(OVERHEAD TANK) SR.NO. ZONE NO.
1 2 SW1

LOCATION
Kidwai Nagar South Pashupatinagar

CAPACITY
800 KL 1600KL

LAND STATUS
Land Not Cleared. Land Not Cleared.

Remarks
Public Hindrance Court Stay

PART-2 (CLEAR WATER RESERVOIR)


1 2 SW1 Kidwai Nagar South Pashupatinagar 500KL 1000KL Land Not Cleared. Land Not Cleared. Public Hindrance Court Stay

PART-3 ( PIPELINE) PARTICULARS KDA AREA (SANIGWAN,BINGAWAN,NAUBASTA WEST)


Delhi sujanpur,Sanigwan-I,Yashodanagar East,west,Naubasta west,Kidwainagar south 2

HINDRANCE
KDA did not allow to lay PVC,AC Line (around 8 km)

PWD and NHAI did not allow to lay PSC,AC,PVC pipe for these areas

SOCIETY AREA (BASANT BIHAR,YASHODANAGAR WEST) Feeder Main Line

Local public and Parshad did not allow to lay PVC,AC Pipe. PSC Pipeline Laying Permission Still Not Received From UP Jal Nigam.(nagar nigam,PWD,NHAI,KDA)

4 Tube well(Near Asha temple) (Bingawan in front of Bharghav Residence)

Approach road to Take Driiling Machine for that location of Tubewell is not possible.

STATUS OF HINDRANCES OF AT KANPUR WATER SUPPLY PROJECT PHASE-II CONSTRUCTION DIVISION- III PART-1(OVERHEAD TANK) SR.NO. ZONE NO.
1

LOCATION Kidwai Nagar South

CAPACITY

LAND STATUS
Land Not Cleared.

Remarks Public Hindrance

SW1

800 KL

PART-2 (CLEAR WATER RESERVOIR)


1 2 SW1 SW2 Kidwai Nagar South Basant Bihar

500KL Land Not Cleared. 900KL Land Not Cleared. PART-3 ( PIPELINE)
HINDRANCE

Public Hindrance Public Hindrance

PARTICULARS
1

KDA AREA (SANIGWAN,BINGAWAN,NAUBASTA WEST)

KDA did not allow to lay PVC,AC Line (around 8 km) Awas Vikas did not allow to lay PVC,AC Line (around 25 km) PWD stopped work of PSC Pipe Laying From Naubasta Churaha to Juhi Gaushala Local public and Parshad did not allow to lay PVC,AC Pipe.

2 3

AWASVIKAS NIGAM(HANSPURAM,NAUBASTA EAST) PSC PIPE

SOCIETY AREA (BASANT BIHAR,YASHODANAGAR WEST)

STATUS OF HINDRANCES OF AT KANPUR WATER SUPPLY PROJECT PHASE-II


CONSTRUCTION DIVISION PART-1(OVERHEAD TANK)
SR.NO. 1 ZONE NO. GW2 LOCATION Barra West CAPACITY 1400 KL LAND STATUS Land Not Cleared. Remarks Public Hindrance

PART-2 (CLEAR WATER RESERVOIR)


1 2 3 4 GW3 GW4 GW2 Ratan Lal Nagar Chedising ka Purrwa(Barra) Barra West Ravidaspuram 800KL 1000KL 800KL 200KL Land Space Problem Land Space Problem Land Not Cleared. Land Not Cleared. Public Hindrance Public Hindrance(sukram singh yadav)

PART-3 ( PIPELINE)
PARTICULARS
PVC AND AC PIPE LINE 1 PSC PIPE LINE 2 PSC PIPE LINE 3

HINDRANCE
Bitumen and Cement Road is not allowed by Local Public & nagar Nigam in all areas. PSC Pipeline Laying Permission Still Not Received From UP Jal Nigam.(nagarnigam,PWD,NHAI,KDA) Barragaon,ravidaspuram,karahi,saraimita for all areas Indian oil Corporation permission still required