Assigned To Painter Complete - 09/01/20 Final task Paintwork, scheduled week commencing 13/01/20
NO.12 - TARMAC DRIVE + RELAY UNEVEN SLABS
Assigned To Ground worker I’m aware tarmac work is sub-contracted
Relaying slabs can be carried out when 3 Friday Lane, B92 0HY is completed.
NO.19 - KITCHEN REPLACEMENT
Assigned To Kitchen Fitter Pictures forwarded Awaiting update
NO.15 - PLASTER 2X CEILINGS
Assigned To Plasterer Stripped + Prepared for Colin from MJR to plaster 13/01/20 Second bedroom stripped,awaiting home owner to remove goods before work commence although we are hoping his is able to carry out works the next working day. NO.14 - ROOF VOID Assigned To Multi skilled worker Inspection Complete
NO.11 - MASONARY BUILT STORE
Assigned To Bricklayer Colin has spoken with homeowner and has agreed to replace with brickwork as oppose to window. Final tasks stated below