Subject: Concerns
Ground Floor:
- Cutting of excess mezzanine floor for glass door at lobby
- Approved RCP at lobby
- Final Layout of Sprinkler
- Cover of insulation
- Tiles for CR
2nd floor & 3rd floor:
- Approved RCP at function room and service corridor
- Tiles for function room, comfort room, service corridor
- Wall partition at fire exit (to determine the termination at ceiling layout)
- Tiles for CR
5th-9th floor:
- Installation of bathub at unit 9 & 18
- Wifi at hallway
th
7 floor:
- Provision of valve at bathub verify JT (mataas)
8th floor:
- Detail of drywall partition at unit 4 (8th floor)
9th floor:
- RCP @ business lounge
- RCP @ meeting rooms
- Tiles at business lounge