2014 Health WASH PROJECT Rural Health Posts Construction of Hand Dug Well and Pipe laying Replacement

Summery Cost Sheet and Status Report


List of Health Post Contractor amount Paid Amont (ETB) UnPaid Amont (ETB) Performance Status
So no name Type of Scheme Name of Contractor with Vat 15% With VAT 15% With VAT 15% %

1 Aweberkhadele Rural pipe System(RPS) Ahmed Mohammod Ahmed GC 203,550.00 203,550.00 100%

2 Erer Dodota Hand dug well Nejah Yusuf B.C 175,404.87 103,106.15 72,298.72 55%

3 Deretayera Hand dug well Jami and Hayat GC 192,770.48 192,770.48 8%


4 Miyaya Hand dug well Gosa Balayenashe GC 152,029.56 32,144.62 119,884.94 35%

5 Abubaker Muti Hand dug well Shakib Oumar and Friends GC 152,761.03 152,761.03 75%

Grand Total Price 876,515.94 338,800.77 537,715.17

Performance Work Indictors for Each Activity by %


Earth Work 40%
Concrete Ring work 35%
Masonary Work 10
Concrete Slab 10
Finishing Work 5%
Total 100%
mery Cost Sheet and Status Report

Remark

Completed

Excavation of 20m, Water


Sources is found in the Well and
Concrete ring work
Excavation of earth

Excavation of Earth and Found


Hard rock formation no water
Excavation of 20m ,Water
Sources is found in the Well and
Concrete ring work