Professional Documents
Culture Documents
Construction Equipment
CENG-5201
Lecture Three
Eyob Tesfamariam
Eyob.tesfamariam@aastu.edu.et
Chapter Three: Construction Equipment
3.1 Introduction
3.2 Earth Work Equipment
3.2.1 Excavating and Loading Equipment
3.2.2 Hauling and Hoisting Equipments
3.4 Compacting and Finishing Equipments
3.5 Others
3.1 Introduction
Based on the activities of earth work which includes some of the
following activities;
Excavating, Construction equipments can be further
Hauling, classified as;
• Earth Work Equipments
Loading, • Hauling and Hoisting Equipments
Placing(damp & spread), • Pumping Equipments
• Others types
Grading,
Compacting and
Final Finishing
3.2 Earth Work Equipment
Earth work equipment are broadly classified into earth moving
and compaction equipments.
Earthmoving equipment
1 2 3
4 5 6
4.BACK HOE
5.SHOVEL 6.PILE DRIVER
1.CRANE (HOOK)
• A crane is a type of machine, generally equipped with a hoist rope, wire
ropes or chains, and sheaves, that can be used both to lift and lower
materials and to move them horizontally. It is mainly used for lifting
heavy things and transporting them to other places. The device uses one
or more simple machines to create mechanical advantage and thus move
loads beyond the normal capability of a human.
• Cranes are commonly employed in the transport industry for the
loading and unloading of freight, in the construction industry for the
movement of materials, and in the manufacturing industry for the
assembling of heavy equipment.
Tower crane
Gantry crane
Vehicle crane
2.CLAMSHELL
Clamshells are used primarily for holding and releasing materials such
as sand, gravel, crushed stone, coal, etc. and for removing materials from
inside cofferdams, pier foundations, sewer manholes, sheet‐lined
trenches, etc.
• They are specially suited to vertically lifting materials from one
location to another, as in charging hoppers and overhead bins.
• The limits of vertical movements may be relatively large when they
are used with long crane booms.
• By the use of different attachments shovel families can be versatile.
3.DRAGLINE
Draglines are used to excavate earth and load it into hauling units,
such as trucks or tractors‐pulled wagons, or deposit it into levees,
dams and spoil banks near the pits from which it was excavated.
Dragline Excavator
DRAGLINE cont.…….
The output of a dragline vary with the following factors:
Class of material,
Depth of cut
angle of swing,
job conditions,
Management conditions,
size of hauling units,
skill of operator and
physical condition of the shovel
6. PILE DRIVER
• Pile driver is a device used to drive piles in to a soil to provide
foundation support for buildings or other structure
Hydraulic Excavators
Hydraulic excavators replaced the cable operated crane shove family
because of the advantage :
• Faster cycle time,
• higher bucket penetrating force,
• more precise digging and
• easier operator control
In addition to that many attachments can be
made to increase the versatility of the
equipments.
Augers: Drills holes for poles, posts, soil sampling and ground
improvement activities
Jack Hammer: vibratory hammer used to break up concrete and rock.
Bucket Ripper: The bucket sides and bottom are lined with ripper teeth
to break up hard soil or soft rock.
Thumb Bucket: attached to bucket to provide a hook capacity.
Auger Drill
Jack hammer
Excavation
Bucket Ripper
Excavation Thumb
Bucket
Loaders
A tractor equipped with a front – end bucket is called a loader, front end
loader or bucket loader.
These equipments are primarily used to load excavated materials to a
hauling unit, excavate soft to medium materials, loading hoppers,
stockpiling materials, backfilling ditches, and moving concrete and
other construction materials.
Both track and wheel loaders are available.
Attachments available for the loader include augers, backhoes,
crane booms, dozer and forklifts.
Some models of wheel loaders are
designed as a combination of a backhoe
and loader and often
Auger mounted Loader Crane booms mounted Loader
Once the equipment needs for an activity have been identified, the
next step is to conduct an equipment productivity analysis to select
the optimum size.
The objective is to determine the number of units and the size of
equipment that would permit the contractor to accomplish the
activity with a duration resulting in the lowest cost possible.
Productivity of an equipment can be classified as peak or theoretical
and actual;
Peak (Theoretical) Productivity is the theoretical productivity
governed by design limitations only.
Actual Productivity on the other hand is the productivity of an
equipment after due consideration of the differently influencing
factors
Where
Qa = Actual Productivity
Qth = Theoretical Productivity
f1,f2 ………….. Factors influencing the theoretical productivity
From productivity concept equipments and how they can operate can be
broadly classified into two;
I) Cyclic Operating or
II) Continuously Operating
I. Cyclic Operating Equipments
These are machines which are intentionally or unintentionally influenced
by their operators. The theoretical productivity can be computed from
Where
II Continuously Operating Equipments
These are machines that continuously operate like pumps, conveyer belts,
etc. For these kinds of machines:
Productivity of Shovel Family and Excavators
The actual productivity of the shovel family is dependent on the actual
volume per cycle and the cycle time. Thus, to compute the actual
productivity one should be able to make a good estimate of the actual
bucket capacity (which depends on the soil characteristics) and the
cycle time.
The actual productivity of these equipments can be estimated from the
following expression;
Since bucket ratings for the cable shovel, dragline, and cable backhoe
are based on struck volume, it is often assumed that the heaping of the
buckets will compensate for the swell of the soil. That is, a 5m3 bucket
would be assumed to actually hold 5 bank m3 of material.
A better estimate of the volume of material in one bucket load will be
obtained by multiplying the nominal bucket volume with a bucket fill
factor or bucket efficiency factor.
Suggested values of bucket fill factor for common soils are given in
Table 2.2,
The most accurate estimate of bucket load is obtained by multiplying
the heaped bucket volume (loose measure) by the bucket fill factor.
Bucket load = heaped bucket volume* bucket fill factor
If desired, the bucket load may be converted to bank volume by
multiplying its loose volume by the soil’s load factor. This procedure is
illustrated with the following examples
Productivity of excavator
Production of a hydraulic excavator then can be estimated by using the
following equation together with Tables 2.2 through which have been
prepared from manufacturers’ data,
Volume correction
1
= =
1+𝑠𝑤𝑒𝑙𝑙
Production----------------------------------------------------------------- Qa
Q---------------------------------------------------------------------Vn
Cycle time /hr-----------------------------------------------no
F-----------------------------------------------------B
AS:D------------------------------------S
E/60min =
Volume correction factor is used to covert loose volume in to bank volume
Example
A crawler hoe having a 3½-cy bucket is being considered for use on a
project to excavate very hard clay from a borrow pit. The clay will be
loaded into trucks having a loading height of 9.75 ft. Soil- boring
information indicates that below 9 ft, the material changes to an
unacceptable silt material. What is the estimated production of the hoe in
cubic yards bank measure, if the efficiency factor is equal to 50-min/hour?
Solution
3600 𝑠𝑒𝑐∗3.5𝑐𝑦∗0.80 50 1
Production = ∗ ∗( )
22𝑠𝑒𝑐 60 0.741
hourly out put (cy/hr or m3 /hr) can be calculated from the following formula
The above figures are for crawler type of tractor shovel, however for wheel
shovels, bucket factor is about 10% lesser than those mentioned above.
Example
A hydraulic front shovel excavating common earth has a heaped capacity
of 1.5 cyd. Its maximum digging height is given by the manufacturer as
7m. the average angle of swing 120 degree. the average height of cut is
2.94m. What is the hourly rate of production in bm3/hr, if the shovels
cycle time is 19 sec? Take the shovel‘s optimum height of cut as equal to
30% of its maximum digging height. Assume the job efficiency and bucket
load factor to be 50min/hr and 0.8 respectively.
Productivity of Dragline
A dragline excavator is especially useful when there is need for
extended reach in excavating or when material must be
excavated from under water.
The load that a blade will carry can be estimated by several methods:
Field measurements
Cycle time
The sum of the time required for pushing, backtracking, and
maneuver into position to push represents the complete dozer
cycle. The time required to push and back track can be calculated
for each dozing situation considering the travel distance and
obtaining a speed from the machine‘s performance chart.
For distances less than 100 ft, the operator cannot get the machine
past the second gear.
Example A power-shift crawler tractor has a rated blade capacity of
7.65Lm3. The dozer is excavating loose common earth and pushing a
distance of 200ft (61m) with speed of 4km/hr. Maximum reverse speed in
third range is 8 km/hr. Estimate the production of the dozer, if job
efficiency is 50 min/hr.
Productivity of Loaders
Loader production can be estimated as the product of average bucket
multiplied by cycles per hour .
Basic cycle time for a loader includes the time required for
Loading to the bucket
Traveling to the dump truck, (short time usually not more than 5m)
dumping from loaders bucket (loading to dump truck)
Travel time Back to material expected to be loaded ,
• The important aspect is determining the actual travel time. Travel times
shall be determined from manufacturer’s performance curves.
Cycle time =
load to the bucket +
travel to dump truck+ load to dump truck
Return to stock material
The production rate for wheel loader will depend on the:
1. Fixed cycle time required to load the bucket, maneuver with four
reversals of direction and dump the load.
2. Time required travelling from the loading to the dumping position.
3. Time required returning to the loading position.
4. Volume of material hauled on each cycle.
Table A-1 Bucket fill factors for wheel and truck loader
Productivity of Graders
Grader production is usually calculated on a linear basis (kilometers
completed per hour) for a road way projects and on an area basis (square
meters per hour) for general construction projects. The time required to
complete a roadway may be estimated as follows
In the majority of the cases, as the grader has multiple applications, the
computation of its productivity is not always possible. It can, however, be
estimated, case by case.
Average actual productivity for leveling and spreading can be
computed as follow
Qa = B x L x fN x fZ x 60/T [m2/hr]
Where,
B = width per strip with due consideration of over lapping
B = l* cos(A) and Qa = average actual productivity
l = length of blade
A = Angle of blade with respect to the axis (refer Table 4.1)
L = lift thickness after compaction
fN= factor to take care of site conditions, operator effectiveness (refer
Table 4.2) * fZ= time factor (refer Table 4.3)
T = Cycle time, T = 0.06⅀ P/v * P = number of passes
V = forward and back ward average speed
Grader production is also calculated as area covered by motor
grader per hour.
A = B x Vav x η
Where,
• B = width per strip (m) = 0.8 * l * cos A
• l = length of blade
• A = Angle with respect to axis
• Vav = Average speed (m/hr)
• η = efficiency
• Time required to complete a roadway project can be calculated by
𝟔∗𝟐𝟓 𝟏
(𝟕∗𝟐+𝟖∗𝟐+𝟏𝟎∗𝟐) *
𝟔
𝟎.𝟖
22.5hr
Example
A Volvo G740B motor grader with a 3.2m blade is to be used to knock
down dirt on a 15m wide X 2250m long road base area. The effective
grading width is 2.77m. The average speed will be around 6km/hr. If the
number of passes required to reach the desired density of the earth is two,
answer the following questions.
a. What is the work hour productivity of the grader based on area
method, if the operator works 50 min per 60-min?
b. How long will it take to grade the road base?
Solution: