1 Excavation at Station 3500 Cum (as per 3MRP) 3888 Cum 111% 111%
2 Vent shaft Roof slab 73 Sqm (33 Cum) 33 Cum 100% 100%
3 Head Wall @ South Shaft (20 Rm) 20 Rm 0 Rm On going
4 Mezzanine slab Gr: 2.5-4 22 Rm (as per 3MRP) 0 Rm On going (Rebar)
Report Card-planned for October month
S. No Activities Committed Achieved Achieved Overall (%) Current
(in numbers) (in numbers) (%) month progress
1. Permanent works
Target in Oct-20 Target date Progress as on date Planned for Remarks %
this month achieved
Mezzanine slab G: 13/10/2020 As per CJV 15days plan Casting done 100.00%
2.5-4 casting to be 5/10/2020
Base Slab G: 21.5- 16/10/2020 As per plan Casting done 100.00%
23.5
Temporary Works:
1. Rock bolt & Shotcrete
2. Excavation work at Station box, as per three months programme CJV planned (800cum) & 15 days programme CJV planned
(2000cum).As per site condition weekly basis excavation quantity achieved (1182cum)
3. Ancillary Building Micro piling work in progress
4. Rock anchor stressing work in progress
5. Retrofitting work at Laxmi building in progress.