Professional Documents
Culture Documents
Plan Produce
Phase 1 Phase 2 Phase 3 Execute Phase 4 F
Conceive (C) Develop (D) (E) (F)
Period of
Opportunity and risk highest risk
Increasing Risk
impact
t
i mpac
d r isk
m bi ne
Co
Amount at stake
Time
roduce
Phase 4 Finish
(F)
riod of
ghest risk
pact
$ Value
IEEN-5303 Risk Management
Assignment II
Syed Mujtaba Ahmed
K00469233
Units in $1,000
Activity Jan Feb Mar Apr May Jun
Staffing 8 7
Blueprinting 4 6
Prototype Dev. 2 8
Full Design 3 8 10
Construction 2 30
Transfer
Punch List 15
Total
Monthly Plan 8 7 6 17 10 55
Cumulative 8 15 21 38 48 103
Monthly Actual 8 11 8 11 10 30
Cumulative Actual 8 19 27 38 48 78
29.6% 28.9% 20.8% 38.5%
Note: original plan was to complete in July, but actual time frame is 17.5. It means it needs about 11 more mo
Note: original planned cost was $118,000, but estimated as $224,487.80. So it is a significant cost overrun.
1. c) The project was supposed to be completed by the end of June with budget of $78,000
If the project was evaluated at the end of March, the project would have and efficiency
Thus giving us the lesson that the project should be evaluated from time to time becau
2. a) As a project manager I would evaluate the project on regular basis so as to reduce finis
I would use expert advice and plan accordingly for the future months.
2. b) The lesson learned in this case is that projects should be evauated on timely basis, if no
more months and cost a lot more than the assigned budget or the project might fail as
t
15
118
h budget of $78,000 but due to lack in vision and delayed in evaluation the projet will take round 11 months
d have and efficiency of 76% and saved 2 months in time and there wold be cost overturn of $90,000.
m time to time because if we evaluate late then there might be highest risk of impact.
so as to reduce finish the project on time within the assigned budget. If there are any deviations due to unfo
ths.
on timely basis, if not so there might be highest risk of imapct if evalued further during the end of the projec
project might fail as well. So earlier the realization earlier we can take the steps to reduce the cost and time
take round 11 months more to complete with increase in budget of $106,487.80.
urn of $90,000.
deviations due to unforseen circumstances
g the end of the project causing the project to extend for few
duce the cost and time require.
Evaluate the project at the end of May.
Units in $1,000
Activity Jan Feb Mar Apr May Jun Jul
Staffing 8 7
Blueprinting 4 6
Prototype Dev. 2 8
Full Design 3 8 10
Construction 2 30
Transfer 10
Punch List 15 5
Total
Monthly Plan 8 7 6 17 10 55 15
Cumulative 8 15 21 38 48 103 118
Monthly Actual 8 11 8 11 10
Cumulative Actual 8 19 27 38 48
Units in $1,000
Activity Jan Feb Mar Apr May Jun Jul
Staffing 8 7
Blueprinting 4 6
Prototype Dev. 2 8
Full Design 3 8 10
Construction 2 30
Transfer 10
Punch List 15 5
Total
Monthly Plan 8 7 6 17 10 55 15
Cumulative 8 15 21 38 48 103 118
Monthly Actual 8 11 8 11
Cumulative Actual 8 19 27 38
Units in $1,000
Activity Jan Feb Mar Apr May Jun Jul
Staffing 8 7
Blueprinting 4 6
Prototype Dev. 2 8
Full Design 3 8 10
Construction 2 30
Transfer 10
Punch List 15 5
Total
Monthly Plan 8 7 6 17 10 55 15
Cumulative 8 15 21 38 48 103 118
Monthly Actual 8 11 8
Cumulative Actual 8 19 27
Units in $1,000
Activity Jan Feb Mar Apr May Jun Jul
Staffing 8 7
Blueprinting 4 6
Prototype Dev. 2 8
Full Design 3 8 10
Construction 2 30
Transfer 10
Punch List 15 5
Total
Monthly Plan 8 7 6 17 10 55 15
Cumulative 8 15 21 38 48 103 118
Monthly Actual 8 11
Cumulative Actual 8 19