Professional Documents
Culture Documents
1. A partially solved PERT problem is detailed in the table below. Times are given in weeks.
Optimistic Probable Pessimistic Expected
Activity Preceding Variance
Time Time Time Time
A -- 7 10 19
B A 2 2 8
C A 8 12 16
D A 3 5 10
E B 4 6 8
F B 6 8 10
G C, F 2 3 4
H D 2 2 8
I H 6 8 16
J G, I 4 6 14
K E, J 2 5 8
a. Calculate the expected time and variance for each activity. Enter these values in the
appropriate columns in the table above.
b. Which activities form the critical path?
c. What is the estimated time of the critical path?
d. What are the project variance and the project standard deviation?
e. What is the probability of completion of the project before week 42?
f. If the Project Manager request a range for complete the project with 95% of confidence; what
will be?
g. True or False: In PERT analysis, the identification of the critical path can be incorrect if a
noncritical activity takes substantially more than its expected time?
h. True or False: Variation in activities that are not on the critical path cannot affect the overall
project completion time? Why?
i. True or False: The standard deviation of project duration is the average of the standard
deviation of all activities on the critical path? Why?
j. True or False: We can use a Gaussian distribution in PERT analysis to calculate expected
activity times and variances. after all, the theorem of limit central is used here? Why?
Para ganar hay que poner toda la fuerza en movimiento. Carl Von Clausewitz
Carlos Javier Carranza Baez I PfMP PgMP PMP CCP PSP PRMP CPEM MBA Página 1 de 2
Planning & Scheduling (PSP) Código Revisión: RA
Compound Questions # 2 Fecha 10-Sep-22
CCM and PERT Method Pagina Pág. 2 de 2
Para ganar hay que poner toda la fuerza en movimiento. Carl Von Clausewitz
Carlos Javier Carranza Baez I PfMP PgMP PMP CCP PSP PRMP CPEM MBA Página 2 de 2