International Islamic University Chittagong

Department of Business Administration


Program: BBA
Final Examination, Autumn-2018
Project Management (FIN4705)
Time:2.5 Hours Full Marks:50
Answer any five (5) from the following questions:
Question:01 (3+4+3)
a. Who is a project manager? Differentiate between functional manager and project manager.
b. Identify the different stages of career path of a project manager. Interpret the different role of a project
manager within a project.
c. Identify the different stages of team building in project management.
Question:02(3+3+4)
a. Discuss the term “Project Financing”. Briefly explain the four basic rights of a equity shareholder.
b. Identify the different methods of raising equity capital.
c. Suppose the peoples of Kumira have taken an initiative to establish a digital library. They have collected
Tk.120000 from the user of the library, The Upazilla chairman of Sitakunda has donated Tk.85000,
Subsidy from the government of Bangladesh was received Tk.95000.Tk.175000 was received from the
UNDP fund. Expenditure for the project are as follows: Establishing the Library building Tk.100000,
Purchasing Books Tk.50000, Purchase of computer Tk.90000, Purchase of Router(Wi-fi devise)
Tk.7500, Purchase of Shelf, Chair, Table etc Tk.70000.Repairing a Road towards the library building
Tk.25000. Calculate the dependency and sustainability index and explain your answer.
Question:03(2.5+2.5+5)
a. Discuss the term-“Scheduling”. Write the objectives of scheduling.
b. Distinguish between PERT and CPM.
c. A project consist of eight activities with the following relevant information:
Activity Immediate Predecessor Estimated Duration (Days)

Optimistic Most Likely Pessimistic


A --- 1 1 7
B --- 1 4 7
C --- 2 2 8
D A 1 1 1
E B 2 5 14
F C 2 5 8
G DE 3 6 15
H FG 1 5 3
Required
(a) Draw the PERT network and find out the expected project completion time.
(b) What duration will have 95% confidence for project completion?
(c) What will be the probability of the project completion on or before 27 days?
Question:04(3+7)
a. What is meant by sensitivity analysis? Illustrate the concept of Risk Management of a project.
b. ABC Corporation is considering an electricity generating project, which has the following forecasted
annual cash flows. The project is in 37% tax bracket with discount rate of 9% per year.
Cash Flow Forecast for a Power Generation Project

Y0 Y 1-10 each

1. Initial cost in Tk 11,50,000 -

2. Power Generation in KWh 10,50,000

3. Operating cost in Tk 55,000

4. Selling price in Tk 0.30 / KWh

5. Depreciation in Tk 1,50,000

Required:
1. Do sensitivity analysis of NPV assuming 10% change in all factors i.e. life, operating cost,
power generation, selling price and tax rate.
2. Comment on major risk areas in the Project.
Question:05(5+5)
a. What is meant by final report of a project? Explain the contents of final report.
b. Define the term “Project termination”. Explain the fundamentals reasons for a project may be
terminate.
Question:06(5+5)
a. Assess the historical background of project management of Bangladesh.
b. Interpret the termination process of a project. Categorize the Project in the context of
Bangladesh.
Question:07(2.5 x 4)
Write short note on the following:
i. ECNEC
ii. Project Termination by Addition
iii. IPO, Seasoned Offering
iv. Qualities of a Successful Project manager.