C O N S T R U C T I O N U P D AT E

SEP- 2023
CONTENT
• Key update – Construction ban impact for 2022

• Birla Navya – The Masterplan

• Amoda I
• Block Masterplan
• Progress update
• Amoda II
• Block Masterplan
• Progress update

• Drisha 1A & 1B
• Block Masterplan
• Progress update

• Anaika
• Block Masterplan
• Progress update
• Avik
• Block Masterplan
• Progress update
PAGE 2
CONSTRUCTION BAN IMPACT - 2022
• The National Green Tribunal (NGT) in 2022 mandated an air quality linked dynamic pollution management process

• Under this the Government constituted a Commission for Air Quality Management (CAQM) – which implements ban
on various activities which lead to deterioration of air quality during the winter season. These ban’s are linked to the
Air Quality Index (AQI)

• The CAQM in year 2022 implemented multiple ban’s on construction activities linked to the AQI. In total your project
was impacted by 36 days of absolute ban. Frequent ban’s also impact labour and material mobility. Cumulatively your
project was impacted by ~ 3 months
1. From 30th Oct 22 to 14th Nov 22 | 16 Days
2. From 04th Dec 22 to 7th Dec 22 | 4 Days
3. From 30th Dec 22 to 4th Jan 23 | 6 days
4. From 6th Jan 23 to 15th Jan 23 | 10 days

• Despite this the team has successfully completed structures for 70 plots (viz 280 units). We are also progressing on
finishing activities at a rapid pace, to ensure timely delivery as per our commitments

PAGE 3
BIRLA NAVYA – THE MASTERPLAN

Drisha Anaika

Amoda I
Avik
Amoda II

PAGE 4
AMODA I - MASTERPLAN

Floor 15

Amoda
1
(Pocket
-D) ESS

PAGE 5
AMODA I – CONSTRUCTION PROGRESS
Amoda 1 {Plot: 1 to 7}

Amoda 1 (Pocket-D)
{Plot: 1 to 14}

a) Terrace Slab : 100% Completed


b) Blockwork : 100% Completed
c) Internal Plaster (Flat) : WIP
d) External Plaster : WIP
e) Marble Flooring : WIP
Floor 15
f) Plumbing Works : WIP
g) Toilet Flooring : WIP
h) Door Windows : WIP
i) External Stone Cladding : WIP

PAGE 6
AMODA I – CONSTRUCTION PROGRESS
Amoda I {Plot: 8 to 10} Amoda I {Plot: 11 to 14}

Floor 15

PAGE 7
AMODA II - MASTERPLAN

Floor 15

PAGE 8
AMODA II – CONSTRUCTION PROGRESS

Amoda II
{Plot: 19,31,32,33,34,35,36}

a) Marble Flooring : 100% Completed


b) Internal Flat Wiring : 100% completed
c) Door Windows : 100% completed
d) External Primer : 100% Completed
Floor 15 e) Glass Railing : 100% Completed
f) Lift Installation : 100% Completed
g) Lift Lobby Flooring : 100% Completed
h) Modular Kitchen : WIP
i) Lift Lobby Cladding : WIP
j) Entrance Glazing : WIP

PAGE 9
AMODA II – CONSTRUCTION PROGRESS
Amoda II
{Plot: 37,38,39,40,41,42,43,44,45}

a) External Plaster : 100% Completed


b) Marble Flooring : 100% Completed
c) External Primer : 100% Completed
d) Internal Flat Wiring : 100% Completed
e) Door Window : 100% Completed
f) Lift Lobby Flooring : 100% Completed
Floor 15 g) Lift Installation : 100% Completed
h) Lift Lobby Cladding : WIP
i) Glass Railing : WIP
j) Modular Kitchen : WIP

PAGE 10
AMODA II – CONSTRUCTION PROGRESS

Amoda II
{3B, Plot: 10, 12, 14, 16, 21, 23, 25, 27, 29}

a) Blockwork (Flat) : 100% Completed


b) Internal Plaster (Flat) : 100% Completed
c) Marble Flooring : 100% Completed
d) External Plaster : 100% Completed
e) Toilet flooring : 100% Completed
f) Glass Railing : WIP
g) Lift Lobby Flooring : WIP
h) Lift Installation : 100% Completed

PAGE 11
AMODA II – CONSTRUCTION PROGRESS

Amoda II
{3A, Plot: 11, 12a, 15, 20, 22, 24, 26, 28, 30}

a) Blockwork (Flat) : 100% Completed


b) Internal Plaster (Flat) : 100% Completed
c) Marble Flooring : 100% Completed
d)External Plaster : 100% Completed
Floor 15 e)Toilet Flooring : 100% Completed
f) Door & Window : 100% Completed
g) Lift Installation : WIP
h)Glass Railing : WIP
i) Lobby Flooring : WIP

PAGE 12
AMODA II – CONSTRUCTION PROGRESS

Amoda II
{3C, Plot: 1,2,3,4,5,6,7,8,9}

a) Terrace Floor Slab : 100% Completed


b) External Stone Cladding : 100% Completed
c) Blockwork : 100% Completed
d) Internal Plaster : 100% Completed
e) External Plaster : 100% Completed
f) Marble Flooring : WIP
g) Toilet Flooring : WIP
h) Door & Window : WIP

PAGE 13
DRISHA 1A & 1B - MASTERPLAN

Floor 15

PAGE 14
DRISHA 1A – CONSTRUCTION PROGRESS
Drisha 1 A {Plot: 1 to 9}

Drisha 1 A {Plot: 1 to 9, 14 to 20, 12a, 24}

a) Stilt Floor Slab : 89% Completed


b) First Floor Slab : 78% Completed
c) Second Floor Slab : 72% Completed
d) Third Floor Slab : 61% Completed
e) Fourth Floor Slab : 61% Completed
Floor 15 f) Terrace Floor Slab : 61% Completed
g) Blockwork : WIP

PAGE 15
DRISHA 1A – CONSTRUCTION PROGRESS
Drisha 1 A {Plot: 12a to 17} Drisha 1 A {Plot: 18-20,24}

Floor 15

PAGE 16
DRISHA 1B – CONSTRUCTION PROGRESS

Drisha 1B {Plot: 10 to 12, 21 to 23, 25-30}

a) Excavation : 100% Completed


b) Foundation : 83% Completed
c) Stilt Slab : 42% Completed

Floor 15

PAGE 17
DRISHA 1B – CONSTRUCTION PROGRESS
Drisha 1B {Plot: 25-30}

Floor 15

PAGE 18
ANAIKA – MASTERPLAN

Floor 15

PAGE 19
ANAIKA - CONSTRUCTION PROGRESS

Anaika {Plot: 1 to 17, 18-19, 21-31}

a) Excavation : 100% Completed


b) Foundation : 53% Completed
c) Stilt Floor : 30% Completed
Floor 15 d) 1st Floor Slab : 23% Completed

PAGE 20
ANAIKA – CONSTRUCTION PROGRESS

Anaika (Plot 1-9) Anaika (Plot 18-31)

Floor 15

PAGE 21
AVIK – MASTERPLAN

Floor 15

PAGE 22
AVIK - CONSTRUCTION PROGRESS

Avik (22 Plots) {Plot: 8-8a,10,11to15,46-


50,6a,6b,6c,7a,
7b,16,17,24a,24b,24c}

a) Excavation : 64% Completed


b) Foundation : 32% Completed
Floor 15 c) Stilt Floor : 9% Completed

PAGE 23
AVIK – CONSTRUCTION PROGRESS

Avik (Plot 11-15) Avik (Plot 6a,6b,6c,7a,7b)

Floor 15

PAGE 24
Nos. of
S No Pocket Plot Nos. Progress
Plots
• Terrace Floor Slab : 100% Completed
• Blockwork : WIP
1 Amoda 1 14 1 to 14 • Internal Plaster (Flat) : WIP
• Marble Flooring : WIP
• Toilet Flooring : WIP
• Lift Lobby Flooring : 100% Completed
19,31,32,33,34,35,
2 7 • Lift Installation : 100% Completed
36 • Entrance Glazing : WIP
• Lift Installation : 100% Completed
• Lift Lobby Flooring : 100% Completed
3 9 37 to 45 •


Glass Railing
Modular Kitchen
Lift Installation
: WIP
: WIP
: 100% Completed
PROJECT
Amoda 2
9 (3B)
10, 12, 14, 16, 21, 23, 25, •
27, 29 •

Toilet Flooring
Glass Railing
Lift Lobby Flooring
: 100% Completed
: WIP
: WIP
PROGRESS
4 • Marble Flooring : 100% Completed
9 (3A)
11, 12a, 15, 20, 22, 24, 26, •
28, 30 •

External Plaster
Toilet Flooring
Glass Railing
: 100% Completed
: 100% Completed
: WIP
SNAPSHOT
• Blockwork : 100% Completed
• External Plaster : 100% Completed
5 9 (3C) 1 to 9 • Internal Plaster : 100% Completed
• Marble Flooring : WIP
• Stilt Slab : WIP
• First Floor Slab : WIP
• Second Floor Slab : WIP
6 Drisha 1A 18 1 to 9, 12a, 14 to 20, 24 • Third Floor Slab : WIP
• Fourth Floor Slab : WIP
• Terrace Floor Slab : WIP
• Blockwork : WIP
• Excavation : 100% Completed
7 Drisha 1B 12 10 to 12, 21 to 23, 25-30 • Foundation : WIP
• Stilt Slab : WIP
• Excavation : 100% Completed
1 - 19, 21-31
8 Anaika 30 • Foundation : WIP
• Stilt Floor : WIP

8-8a,10,11to15,46- • Excavation : WIP


9 Avik 22 50,6a,6b,6c,7a,7b,16,17,2 • Foundation : WIP
4a,24b,24c • Stilt Floor : WIP
Image for reference purposes only
T H A N K Y O U !

RERA Registration -
Birla Navya (Amoda I and II) - RC/REP/HARERA/GGM/390/122/2020/06 OF 2020; Birla Navya (Drisha 1A) - RC/REP/HARERA/GGM/391/123/2020/07 OF 2020. www.haryanarera.gov.in
The Project is being developed by Avarna Projects LLP (“Developer”). Birla Estates Private Limited and Anant Raj Limited are partners in the Developer LLP. The sale of Unit/Flat/Apartment/ Floor is
subject to the terms and conditions of the Application Form and Agreement to Sale. The Project is being developed on plots acquired by the Developer in a residential plotted colony forming part