Professional Documents
Culture Documents
2. DAILYDEPLOYMENT
PLANT,VEHICLESANDEQUIPMENT
S/N TRADE No. DESCRIPTION N REMARKS
S/N o
a) Site engineer 1 a Concrete 1 Not so bad
) mixer
b) Foreman 1 b Pick up 1
)
c) Mason(s) 12 c
)
d) Carpenter(s) 3 d
)
e) Steelbenders 0 e
)
f) WELDERS 7
g) PAINTERS 11
e) Electricians 4
F) Helpers 20
g) PLUMBERS 4
3. MATERIALS ON SITE
S/N DESCRIPTION UNIT QT DESCRIPTION UNIT QTY
Y
a) Cement Bags 30 Concrete blocks Pc 200
0
b) Aggregates M3 4 Timbers Pc 0
c) Sand M3 6 Hardcore Trip 0
C) Steel T8 0 Clay bricks Pc 2000
T20 0 Maxpans Pc 0
T10 0
61 Concrete louvers
T12 Pc 0
T16 0
T25 0
4. PHOTOS
General Painting of Building First Sample of Glasses(Inside Part)
Foundation of Top Slab of Soco-pit Slab of the soco-pit
5. OBSERVATIONS
2.THE PROJECT CAN'T BE DONE 100% UP TO 18TH JULY BECAUSE THE CONTRACTOR IS NOT
WILLING TO DO ANY EXTRA WORK WITHOUT ADDITIONAL TIME BECAUSE EVEN NOW HE
FEELS AS IF HE WAS PENALISED ILLEGALLY.
PHILBERT NZISABIRA
C.O.W