SITE REPORT FROM 29TH JUNE to 25TH JULY 2020


PROJECT : KITCHEN, DININGAND ASSEMBLY HALL H.C.L.V.SSS

MONTH: JULY 2020 WEATHER


DATE: DAY: WEATHE SUNNY RAINNY
SATURDAY R FROM: MORNIN FRO
25/07/2020 G M:
TO: EVENING TO:
HRS HRS
PRELIMINARIES
S/N ITEM REMARKS
a) Site Office COMPLETE
b) Power/Electricity AVAILABLE
c) HSE NOT YET
d) Temporary Sheds COMPLETED
e) Protection of Person and WATCHMAN IN USE
Property
f) Removal of plant, rubbish NOT YET
1. DESCRIPTIONOFWORKSUNDERTAKEN
PROG PROGRES
RESS S
SCREEDING FOR ASSEMBLY HALL 0% ROOFING FOR THE WASHING AREA 100 %

WELDING TRUSSES FOR ASSEMBLY HALL 100 % PAINTING OF DINNING LEVEL 1 95 %


ROOFING SHADE FOR WORKERS 100 IRON SHEETS OF THE KICTHEN 100 %
%
FIXING GUTTERS FOR ASSEMBLY HALL 97 % SCREEDING FOR SECOND FLOOR 97 %
DINING
PAINTING SECOND FLOOR DINING 85 % CONSTRUCTION OF STOVES 75 %

PAINTIG SOFITE OF MEZZANINE 65 % STONE PITCHING TO THE ENTRENCE 95 %


OF DINING SECOND FLOOR
ROOFING DINING AND CAVERING WITH 100 % CONSTRUCTION OF CONCRETE 100 %
IRON SHEETS LEVEL 2 LOUVERS FOR STAIRCASES
SPLASH APRON OF THE KITCHEN 80% EXCAVATION FOR STOM WATER 75%

2. DAILYDEPLOYMENT
PLANT,VEHICLESANDEQUIPMENT
S/N TRADE No. DESCRIPTION N REMARKS
S/N o
a) Site engineer 1 a Concrete 1 Not so bad
) mixer
b) Foreman 1 b Pick up 1
)
c) Mason(s) 12 c
)
d) Carpenter(s) 3 d
)
e) Steelbenders 0 e
)
f) WELDERS 7
g) PAINTERS 11
e) Electricians 4
F) Helpers 20
g) PLUMBERS 4
3. MATERIALS ON SITE
S/N DESCRIPTION UNIT QT DESCRIPTION UNIT QTY
Y
a) Cement Bags 30 Concrete blocks Pc 200
0
b) Aggregates M3 4 Timbers Pc 0
c) Sand M3 6 Hardcore Trip 0
C) Steel T8 0 Clay bricks Pc 2000
T20 0 Maxpans Pc 0
T10 0
61 Concrete louvers
T12 Pc 0
T16 0
T25 0

4. PHOTOS
General Painting of Building First Sample of Glasses(Inside Part)
Foundation of Top Slab of Soco-pit Slab of the soco-pit

Connection of the two buildings Tiling washing area

Excavation of the soco pit. Protection of the retaining wall.

5. OBSERVATIONS

1. LACK OF COMMUNICATION IN EXTENSION OF TIME MAY BRING PROBLEMS IF NOTHING IS


DONE FOR THE BEST OF THE PROJECT.

2.THE PROJECT CAN'T BE DONE 100% UP TO 18TH JULY BECAUSE THE CONTRACTOR IS NOT
WILLING TO DO ANY EXTRA WORK WITHOUT ADDITIONAL TIME BECAUSE EVEN NOW HE
FEELS AS IF HE WAS PENALISED ILLEGALLY.

PHILBERT NZISABIRA
C.O.W