Daily project update report Name of Project: INMAS, MYMENSINGH Date: 01.10.2023 SL Description Unit Quantity Remarks No. 1 Manpower Update: Office staff Nos 6
Leave (staff) Nos 0
Security guard Nos 2
Leave (Security guard) Nos 0
2 Sub-Contractor labour: Nos 13 Inside Building i)plaster Boundary wall Civil Master Drain i)BRICK WORK Sub-station building i) PLASTER WORK
Sanitary Nos 4 inspection pit finishing
Electrical Nos 4 cable work Earth work Nos Paint Nos 8 i) Wall and Ceiling ii) outside paint iii) grill paint
Aluminum and Thai Nos 4 Aluminium thai section cutting and fixing
Tiles and Marble Nos 9 i)marble work-inside room ii)stair
Fire Nos Lift Nos SS Railing Nos - 3 Daily Labour Curing, House keeping Nos 1 4 Problems: Need Materials supply as per indent i) toilet tiles urgently needed
Need Sub-contactor manpower Nos i) Need hydraulic lift manpower
ii) Need Solar work manpower Need Sub-contactor to start work
i) Curtain wall section-Size (not fixed)
ii) Permission of Starting Communication Road iii) Bondary wall Problems-informed to GM sir Decision Pending Nos iv) Culvert work stopped (ohedul sir) v)Decission changed (ohedul sir): One stair marble work changed to tiles work