DSS 04 july

Activities Location Manpower


External Paint(conmix) Building C west 5

Plaster work for parapet mezzanine roof 4

External plaster (unlmtd power) Building D north 6

block work mezzanine ac pads 4

Waterproofing membrane in wet areas mezzanine 1

Scaffolding erection shops 7

windows(howail) Building A & B 7

Internal Paint Ground floor+electrical room 6

Granite work Building A 2

marble for elevator shaft Building A 3

Metal door fixing Building A 5

Porcelain tiles Mezzanine 2

Terrazzo tile Building B roof 4

Miscellaneous Building D 2

Bathroom Door making Building A 4

Curing in building 1

Security Ground floor 1

Loading in Crane Ground floor 5

Ac sleeves shops 5

water tank testing Ground floor 2

rope pullying Building D 2

preparation of flats for water testing Building B 2

ducting laundry(muzaffar) Building C 2

Fire hose cabinet installation(qusaibi) Shops 2

wiring from cable tray to pump ground floor


6
Exhaust duct fan wiring shops
90