Practical No.23 e
0.1 Title : Use the relevant software to prepare Detailed estimate of Septic Tank.

0.2 Course Outcome:

Use relevant software for estimating the quantities and cost of items of work.

0.3 New Concepts:

Proposition 1: Septic tank:


Collection of sewage from building/ Hostel / Hospital.

Detailed drawing of Listing items of Calculation of


Total cost of septic
septic tank work quantity of items in
tank Calculation in
measurement sheet

0.4 General Abstract Sheet or Face sheet:

Septic Tank

Sr
Particulars Amount
no.
Estimate Cost of abstract sheet: Rs. 12886.87

Add 5% of contingencies: Rs. 644.3435


D Add 2% work charged establishment: Rs. 257.7374
Total estimate cost of the project: Rs. 13788.9509
Mcasurement Shet
Name of work:Estimate for Septic Tank
Sr no. Description of item of work No. length breadth |Depth Quantity Total Quantity

1 Earthwork In Excavation 1 3.30 2.60 1.50 12.87


excavation for foundation in soil of
earth in all type sand gravel and soft
murum including removing excavated
material upto a distance of 50m beyond
the building and strucking and
spreading as directed dewatering pre
painting the bed for foundation and
necessary backfilling ramming,
watering, including shoring and
struting etc.

a) Excavation upto 1.5m

septic tank 1.8+2*0.5+2*0.75=3.90

2 Burnt Brick Masonry

masonry providing in cement mortar


1:6 using brick for external walls
including boiling out water manually
striking joints an unexposed faces
watering sample using 2nd class burmt
brick

a) Septic tank

1) 0.50 m wide
7.80 0.50 0.4 1.56

L= 2*2.30+2*1.6 7.80m

2) 0.40m wide

L = 2*2.20+2*1.5 = 7.40 7.40 0.40 0.30 0.89

3) 0.30m wide

L 2*2.10421.40 7m 7.00 0.30 0.60 1.26

3.1
8 )

RCC Work

Providing and casting in slty and


cement concrete of grade of
trap/granite/gniess/metal for R.C.C.
slab as per detail design or drying as
directed including centering formwork
of steel compaction newly laid by
gunny bags, plastic the formed are with
cement mortar 1:3 for sufficient
minimum thickness of given smooth
surface or roughing if special finish is
to be provided and curing etc. complete
the cement mortar 1:2 plaster is
considered for rendering uneven and
honey combing surface only wooden
planks/ shuttering will not be allowed.

a) slab on tank 2.40 1.60 0.125 0.48


b) Slab on pit

A= (T/4)*1.50^2 = 1.78 sq.m


1.0 1.78 0.125 0.225
c)RCC pardi 1.10 0.075 1.0 0.083

d) Deduction for manhole 0.60 0.45 1.25 0.034

0.822
4 Cement concrete in bottom:- 1.80 i.10 0.075 0.150 0.150

Providing and laying in site cement


concrete in 1:4:8 of trap/ granitel
gniess metal for foundation and
beeding including boiling water
manually formed conmpacting covering
newly laid (by gunny bags or turplin,
curing etc) wooden planks shuttering
will not be allowed
Inside plaster

Providing internal wall cement plaster


20mm thick in coats in cm 1:5 without
to concrete brick surface including
scaffolding and curing

a) Septic tank

2(1.8* 1.1) = 5.8 5.8 1.3 7.54

2.36 1.0 2.35


b)RCC pardi
1.8 1.1 1.98
c) ceiling
d) soak pit

P 2TR 2*r*0.6 = 3.769 3.7769 1.675 6.313

Deduction for manhole 0.6 0.45 0.27


16.913
Soak pit:

Providing and constructing soak pit of


specified size as per detailed drawing
including excavated hollow brickwork
filling with bats etc.

544 1.8 4.580


a)Excavation
A = n/4"(1.8^2)=2.544

b)Brickwork 1.413 1.675 366


A T/4*(1.8*1.2)^2 = 1.413

6.946
Abstract sheet
Name ofwork: Estimate for Septic Tank

Item no. Particulars of items Unit Rate Per Amount Rs.


Quantity Ps.
Rs. Ps.

Excavation:- excavation for


foundation in earth soil ofall types,
sand, gravel and murum including
removing the excavation material up
to a distance of 50m beyond the
building area and staking and
spreading as directed dewatering
preparing the bed for foundation and
necessary back- filling ramming8
watering including shorting and
starting etc.Complete with lift up to
1.5 m

a) septic tank 643.5


12.37 Cubic 50 Cubic meter
meter
b) pipe line

2 1.72 cement concrete providing and laying Cubic 1090 Cubic meter 1874.8
in situ cement concrete in 1:4:8 of meter

trap/ granite/ quartrite gneiss metal


of foundation in bedding including
boiling out water manually formwork
compacting covering newly laid
concrete by gunny bag plastering of
turpuline, curing etc. complete (
wooden planks/ shuttering will not be
allowed) specification no.bd
e.l p.g 27

3.71 brick masonry providing brick Cubic 1375 Cubic meter 5101.25
masonry in cement mortar 1:6 using meter
second class burnt brick in

superstructure including straking


joint, watering and scaffolding
comptete
(1

0.819 RCC work: providing and costing in | Cubic 2840 Cubic meter 2005.04
situ cement concrete of m20 grade of meter

trap granite/ quartrite gneiss metal for|


rcc beams and lintel as per directed
including centering , formwork of
plywood/ steel compaction covering
newly laid concrete by gunny bags
plastic or turpline finishing the form
surface with cement mortor 1:3 of a
sufficient minimum thickness to give
a smooth and even surface or
roughing its special finish is to b
provided and curing etc complete (
excluding reinforcement ) the cemet
mortor 1:3 plaster is considered for
rendering uneven and honeycomb
surface only wooden shuttering will
not be allowed.

0.15 cement concrete providing and laying| Cubic 1090 Cubic meter 163.5
in situ cement concrete in 1:4:8 of meter

trap/ granite/quartzite gneiss metal


of foundation in bedding including
boiling out water manually formwork
compacting covering newly laid
concrete by gunny bag plastering of
turpuline, curing etc. complete (
wooden planks / shuttering will not be
allowed)

Inside plaster - providing internal Sq. meter| 69 Sq.meter 1166.997


cement plaster 20 mm thick in two
coats in cement mortar 1:5 with out
neeru finish to face in all position
incuding scaffolding and curing
complete sec.no.Bd 1.4 pg no. 363.

neat cement filling providing fine


cement reinforcement cement
concrete over 10 cm thick over
manhole and inspection chamber
including MS reinforcement etc
60Cmx60x 1Ocm
manhole providing and fixing fine No. 105 No. 105
cement finish 11.5 thick over green
plaster surface including scaffolding
curing etc. complete additional item
spec.no.as directed by engineer
incharge.

4.58 soak pit:- providing and constructing Cubic 273 Cubic meter 1250.34
soak pit of specified sizre as per meter

detailed drawing including excavation


hollow brick masonry filling with the
brick- bats etc. Complete spec.no.
Rd.v.46 pg 576.

10 2.5 Pipe (0.15m diameter pipe) providing meter 137 meter 342.5
and laying 150 mm diameter concrete
pipes ofIS np2 class in proper line.
Level and slope including necessaryy
collars excavation, laying fixing with
collars in cement mortar 1:1 and rein
filling the trench complete spec.no.
Bc/v41.pg 573.
total cost-

Total = 12886.187

P P T Si30
DETAIL DRAWING OF SEPTIC TANK AND SOACKPIT

Mn holo aov
0.60%0.45

0.1U n druuncter S,W. q

L20

PLAN

R.C.C.lut

R.C.C. prdi
0.07S. tuc.
0 40

Bnck bua
iausycomb
ickwa
g220.39

SECTION
-23
Practical No. 4
0.1 Title: Use the relevant software to prepare Detailed estimate of Well.

0.2 Course Outcome:

Use relevant software for estimating the quantities and cost of items of work.

0.3 New Concepts:

Proposition 1: Coramunity well:


It is the source of water for community.

Detailed drawing of Listing items of Calculation of


Total cost of
community well work quantity of items in
community well by
measurement sheet

0.4 General Abstract Sheet or Face sheet:

Community Well

Sr Amount
Particulars
no.

Estimate Cost of abstract shet: Rs. 808398.08

Add 5% of contingencies: Rs. 40419.90


Add 2 work charged establishment: Rs. 16167.96
Total estimate cost of the project: Rs. 864985.94
Measurement Sheet
Name of work: Estimate for Community Well

Sr no. Description of item of work No. length breadth Depth Quantity Total Quantity
Excavation in soft soil for lead 30m 0.7853 (9.6)^2 1.5 108.57 108.57
and lift 1.5m below ground level upto
i.Sm

2 Excavation in soft soil , below ground 0.7853 (9.6)^2 1.5 108.57 108.57
level from 1.5 to 3 m

Excavation in murum, from 3 to 4.5 m 0.7853 (9.6)*2 1.5 108.57 108.57

excavation in hard murum, from 3 to 0.7853 (9.6)^2 1.5 108.57 108.57


4.5m

Excavation in soft rock, from 6 to 7.5m 0.7853 (9.6)^2 1.5 108.57 108.57

Excavation in softrock, from 7.5 to 9m1 0.7853 (9.6)^2 1.5 |108.57 108.57

Excavation in Hard rock, from 9 to 0.7853 (8.4)^2 1.5 83.126 83.126


10.5m

Excavation in Hard rock, from 10.5 to 0.7853 (8.4)^2 1.5 83.126 83.126
12m

9 U.C.R masonry cmc (1:3) 0.7853 (9.6)^2- 2.7 45.8 45.8


(8.4)2

10 U.C.R masonry cmc (1:3) 0.7853 (9.6)2- 97.9 97.9


(8.4)2

11 R.C.C ring beam 0.7853 (9.6)2- 0.5 5.09 S.09


(8.4)2
2 C.C coping 0.7853 (9.6)^2- 0.5 | 2.1 | 2.1
(8.4)2

13 Cement pointing 3.14 8.4 9.7 255.9 255.9

14 Flooring 0.7853 (11.4)^2- 32.69 32.69


(9.4) 2

| Providing two water wheel |2 Nos


Abstract sheet
Name of work: Estimate for Community Well

Particulars of items Unit Rate Per Amount Rs.


Item no. Quantity Rs. Ps. Ps.

Cubic meter 14114.1


108.57
Excavation in soft soil for lead 30m Cubic 130

meter
and lift 1.5m below ground level upto
1.5m

Cubic 140 Cubic meter 15199.8


108.57 Excavation in soft soil , below
meter
ground level from 1.5 to 3 m

Excavation in munum, from 3 to 4.5 Cubic 160 Cubic meter 17371.2


108.57
meter
m

Cubic 165 Cubic meter 17914.05


excavation in hard murum, trom 3 to
4 108.57
meter
4.Sm

Cubic 425 Cubic meter 46142.25


5 108.57 Excavation in soft rock, from 6 to
7.5m meter

Cubic meter 46685.1


108.57 Excavation in soft rock, from 7.5 to Cubic 430
9m meter

83.126 Excavation in Hard rock, from 9 to Cubic 840 Cubic meter 69825.84
10.5m meter

83.126 Excavation in Hard rock, from 10.5 Cubic 840 Cubic meter 69825.84
to 12m meter

U.C.R masonry cme (1:3) Cubic 3300 Cubic mcter 15l140


9 45.8
meter
10 97.9 U.C.R masonry cmc (1:3) Cubic 3300 Cubic meter 323070
mcter
R.C.C ring beam Cubic 6900 Cubic meter 35121
5.09
meter
C.C coping Cubic 5370 Cubic meter 11277
meter
13 255.9 Cement pointing Cubic 100 Meter sq. 25590
meter
Cubic 300 Meter sq. 9807
14 32.69 Flooring
mcter
two water wheel Cubic 1000 Nos. 2000
Providing
meter

Total SO8398.08

PP Siso
- O9 6000

- 09.6000

09.401D
O114

C8.4138

PLAN
-GG. COPNG (1:4:3)

cEMENT FI OORING (13)


0000

14
1.0000

u.CR MASONRY SO CM THICK


J0000

- U . C R MASONRY 60 CM THCX

RCC.RING BEAM (1.4:)


a.3000-

0000
TRIAL PIT
SOIL 3 M FROM G.L.
HARD MURUM -3 M TO 6M

-L4000-
SOFT ROCK -6 M TO 9M
HARD ROCK 9M TO 12 M