Location:- Ward No. 1
Estimate Amount:- 110000 Only(Rupees One lakh Ten Thousand Only)
Detail Estimate
Item No:1/9.1 Excavation for Structures
Earthwork in excavation for foundation of structures upto 3 m depth as per drawing and
technical specification Clause 1104includding setting out, construction of shoring and bracing,
removal
of stumps and other deleterious matter, dressing of sides and bottom and backfilling with
approved material.
a. Head Wall 2 3.5 2.1 1.55 22.79 Cum
b. Culvert Area 1 2.5 2.8 1.6 11.20 Cum
Total volume 33.99 Cum
Item No:3/9.3 Providing and Laying Reinforced Cement Concrete Pipe NP3 as per design in Single
Row
Providing and laying reinforced cement concrete pipe NP3 for culverts on first class
bedding of granular material in single row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works, backfilling, concrete and
masonry
works in head walls and parapets Clause 1106.
1000mm
Culvert 2 2.5 5.00 m
Plain Cement Concrete M10 (1:3:6 nominal mix) in levelling course cum 5216.60
Item No:4/9.7 below open foundation of Head walls as per drawings & Technical
Specification Clause 1109
Head wall 1st lift 2 2.8 0.922 0.65 3.36 Cum
Plain Cement Concrete M10 (1:3:6 nominal mix) in levelling course cum 5216.60
Item No:5/9.7 below open foundation of Head walls as per drawings & Technical
Specification Clause 1109
Head wall 2nd lift 2 2.8 0.944 1.4 7.40 Cum
Detail Estimate
Item No:1/9.1 Excavation for Structures
Earthwork in excavation for foundation of structures upto 3 m depth as per drawing and
technical specification Clause 1104includding setting out, construction of shoring and
bracing, removal
of stumps and other deleterious matter, dressing of sides and bottom and backfilling with
approved material.
a. Head Wall 2 3 2.1 1.55 19.53 Cum
b. Culvert Area 1 1.5 2.6 1.6 6.24 Cum
Total volume 25.77 Cum
Item No:3/9.3 Providing and Laying Reinforced Cement Concrete Pipe NP3 as per design in Single
Row
Providing and laying reinforced cement concrete pipe NP3 for culverts on first class
bedding of granular material in single row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works, backfilling, concrete and
masonry
works in head walls and parapets Clause 1106.
600mm
Culvert 2 2.5 5.00 m
Plain Cement Concrete M10 (1:3:6 nominal mix) in levelling course cum 5216.60
Item No:4/9.7 below open foundation of Head walls as per drawings & Technical
Specification Clause 1109
Head wall 1st lift 2 2.5 0.922 0.65 3.00 Cum
Plain Cement Concrete M10 (1:3:6 nominal mix) in levelling course cum 5216.60
Item No:5/9.7 below open foundation of Head walls as per drawings & Technical
Specification Clause 1109
Head wall 2nd lift 2 2.5 0.944 1.4 6.61 Cum
Detail Estimate
Item No:1/9.1 Excavation for Structures
Earthwork in excavation for foundation of structures upto 3 m depth as per drawing and
technical specification Clause 1104includding setting out, construction of shoring and bracing,
removal
of stumps and other deleterious matter, dressing of sides and bottom and backfilling with
approved material.
a. Head Wall 2 3.5 2.1 1.55 22.79 Cum
b. Culvert Area 1 2.5 2.8 1.6 11.20 Cum
Total volume 33.99 Cum
Item No:3/9.3 Providing and Laying Reinforced Cement Concrete Pipe NP3 as per design in Single
Row
Providing and laying reinforced cement concrete pipe NP3 for culverts on first class
bedding of granular material in single row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works, backfilling, concrete and
masonry
works in head walls and parapets Clause 1106.
1200mm
Culvert 2 2.5 5.00 m
Plain Cement Concrete M10 (1:3:6 nominal mix) in levelling course cum 5216.60
Item No:4/9.7 below open foundation of Head walls as per drawings & Technical
Specification Clause 1109
Head wall 1st lift 2 2.5 1.247 0.65 4.05 Cum
Plain Cement Concrete M10 (1:3:6 nominal mix) in levelling course cum 5216.60
Item No:5/9.7 below open foundation of Head walls as per drawings & Technical
Specification Clause 1109
Head wall 2nd lift 2 2.8 0.944 1.4 7.40 Cum