AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
01/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
1 0 26 3 17 0 47

Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 10 10 1811 10 0 10 0 0 2 12
9M A 2 2 345 2 0 93 0 0 83 176
9M T 2 2 113 2 0 20 0 0 10 30
12M S 16 16 1666 4 0 4 10 0 10 14
12M A 2 2 230 2 0 64 0 0 8 72
12M T 0 0 1 0 0 4 0 0 0 4
14M S 0 0 116 0 0 5 0 0 17 22
14M A 2 2 26 1 0 25 0 0 0 25
14M T 0 0 0 0 0 0 0 0 0 0
Total 34 34 4308 21 0 225 10 0 130 355
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 0.00 14.82 405.18 Good Medium Fault Monthly Yearly
Gravel [m3] 0.00 20.04 276.96 9M S 10 0 0 0 0
Cement [T] 0.00 12.59 153.41 9M A 2 0 0 0 0
Admixture [Kg] 0.00 76.08 14463.92 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 14 0 2 2 7
Diesel [L] 0.00 30 120 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 756.16 9,743.840 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 1,024.000 14M S 0 0 0 0 1
Cold drawn wire (2.8mm) [Kg] 0.00 94.40 8,605.600 14M A 1 0 1 1 1
D-Bar (14mm) [Kg] 0.00 63.42 1,236.580 14M T 0 0 0 0 0
Tie-wire (1mm) [Kg] 0.00 0.00 500.0
EDC (KWH) Generator (300KVA) (Litters)
Daily Monthly Yearly
Daily Monthly Yearly
Hours Litters Hours Litters Hours Litters
124 124 190466 5:06 0 5.1 0 501.93 7580
3
Delivery Ready Mixed Concrete Delivery (M )
Items / Specification Daily Monthly Yearly
Daily Plan Monthly Yearly
Description 20-40-12 0 0 0.4
9M S 0 0 0 2193 25-15-12 0 0 52
9M A 0 0 0 326 25-21-12 1 1 300.5
9M T 0 0 0 92 Total 1 1 352.9
12M S 0 0 0 1670
12M A 0 0 0 214 Concrete Pipe
12M T 0 0 0 20 Type Daily Monthly Yearly Out Balance
14M S 0 0 0 109 Ø300 1 1 111 0 182
14M A 0 0 0 0 Total 1 1 111 0 182
14M T 0 0 0 0
Total 0 0 0 4624
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 10 1740 0 0 0
9m-A 93 320 0 0 0
9m-T 20 150 0 0 0
12m-S 4 101 0 0 0
12m-A 64 70 0 0 0
14m-S 5 0 0 0 0
Total 196 2381 0 0 0

Yearly Balance
9537 9537

In 2011 Out 2011


5229 4529

29

5.1
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
02/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
6 3 30 4 16 6 65

Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 10 20 1821 10 0 20 0 0 2 22
9M A 2 4 347 2 0 95 0 0 83 178
9M T 2 4 115 2 0 22 0 0 10 32
12M S 16 32 1682 6 0 10 10 0 20 30
12M A 2 4 232 2 0 66 0 0 8 74
12M T 0 0 1 0 0 4 0 0 0 4
14M S 0 0 116 0 0 5 0 0 17 22
14M A 2 4 28 2 0 27 0 0 0 27
14M T 0 0 0 0 0 0 0 0 0 0
Total 34 68 4342 24 0 249 10 0 140 389
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 0.00 13.89 391.29 Good Medium Fault Monthly Yearly
Gravel [m3] 60.00 19.31 320.65 9M S 10 0 0 0 0
Cement [T] 31.84 12.27 172.98 9M A 2 0 0 0 0
Admixture [Kg] 0.00 73.98 14389.94 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 16 0 0 2 7
Diesel [L] 0.00 120 - 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 756.16 8,987.680 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 1,024.000 14M S 0 0 0 0 1
Cold drawn wire (2.8mm) [Kg] 0.00 94.40 8,511.200 14M A 2 0 0 1 1
D-Bar (14mm) [Kg] 0.00 63.42 1,173.160 14M T 0 0 0 0 0
Tie-wire (1mm) [Kg] 0.00 0.00 500.0
EDC (KWH) Generator (300KVA) (Litters)
Daily Monthly Yearly
Daily Monthly Yearly
Hours Litters Hours Litters Hours Litters
138 262 190604 5:00 90 10.1 90 506.93 7700
3
Delivery Ready Mixed Concrete Delivery (M )
Items / Specification Daily Monthly Yearly
Daily Plan Monthly Yearly
Description 20-40-12 0 0 0.4
9M S 0 0 0 2193 25-15-12 0 0 52
9M A 0 0 0 326 25-21-12 0 1 300.5
9M T 0 0 0 92 Total 0 1 352.9
12M S 0 0 0 1670
12M A 0 0 0 214 Concrete Pipe
12M T 0 0 0 20 Type Daily Monthly Yearly Out Balance
14M S 0 0 0 109 Ø300 1 2 112 0 183
14M A 0 0 0 0 Total 1 2 112 0 183
14M T 0 0 0 0
Total 0 0 0 4624
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 20 1740 0 0 0
9m-A 95 320 0 0 0
9m-T 22 150 0 0 0
12m-S 10 101 0 0 0
12m-A 66 70 0 0 0
14m-S 5 0 0 0 0
Total 218 2381 0 0 0

Yearly Balance
9571 9571

In 2011 Out 2011


5229 4529

29

5.1
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
03/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
6 3 31 4 13 6 63

Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 10 30 1831 10 0 30 0 0 2 32
9M A 2 6 349 2 0 97 0 0 83 180
9M T 2 6 117 2 0 24 0 0 10 34
12M S 16 48 1698 6 0 16 10 0 30 46
12M A 2 6 234 2 0 68 0 0 8 76
12M T 0 0 1 0 0 4 0 0 0 4
14M S 0 0 116 0 0 5 0 0 17 22
14M A 2 6 30 2 0 29 0 0 0 29
14M T 0 0 0 0 0 0 0 0 0 0
Total 34 102 4376 24 0 273 10 0 150 423
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 53.79 16.70 428.38 Good Medium Fault Monthly Yearly
Gravel [m3] 0.00 21.99 298.66 9M S 10 0 0 0 0
Cement [T] 0.00 13.34 159.64 9M A 2 0 0 0 0
Admixture [Kg] 0.00 78.88 14311.06 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 16 0 0 2 7
Diesel [L] 0.00 180 120 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 880.02 8,107.660 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 1,024.000 14M S 0 0 0 0 1
Cold drawn wire (2.8mm) [Kg] 0.00 113.08 8,398.120 14M A 2 0 0 1 1
D-Bar (14mm) [Kg] 0.00 78.12 1,095.040 14M T 0 0 0 0 0
Tie-wire (1mm) [Kg] 0.00 0.00 500.0
EDC (KWH) Generator (300KVA) (Litters)
Daily Monthly Yearly
Daily Monthly Yearly
Hours Litters Hours Litters Hours Litters
52 314 190656 6:44 150 16.83 240 513.66 7850
3
Delivery Ready Mixed Concrete Delivery (M )
Items / Specification Daily Monthly Yearly
Daily Plan Monthly Yearly
Description 20-40-12 0 0 0.4
9M S 0 0 0 2193 25-15-12 4 4 56
9M A 0 0 0 326 25-21-12 0 1 300.5
9M T 0 0 0 92 Total 4 5 356.9
12M S 0 0 0 1670
12M A 0 0 0 214 Concrete Pipe
12M T 0 0 0 20 Type Daily Monthly Yearly Out Balance
14M S 0 0 0 109 Ø300 1 3 113 0 184
14M A 0 0 0 0 Total 1 3 113 0 184
14M T 0 0 0 0
Total 0 0 0 4624
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 30 1740 0 0 0
9m-A 97 320 0 0 0
9m-T 24 150 0 0 0
12m-S 16 101 0 0 0
12m-A 68 70 0 0 0
14m-S 5 0 0 0 0
Total 240 2381 0 0 0

Yearly Balance
9605 9605

In 2011 Out 2011


5229 4529

29

6.7333333333
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
04/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
6 3 30 4 16 5 64

Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 10 40 1841 10 0 40 0 0 2 42
9M A 2 8 351 2 0 99 0 0 83 182
9M T 2 8 119 2 0 26 0 0 10 36
12M S 16 64 1714 6 0 22 10 0 40 62
12M A 2 8 236 2 0 70 0 0 8 78
12M T 0 0 1 0 0 4 0 0 0 4
14M S 0 0 116 0 0 5 0 0 17 22
14M A 2 8 32 2 0 31 0 0 0 31
14M T 0 0 0 0 0 0 0 0 0 0
Total 34 136 4410 24 0 297 10 0 160 457
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 26.56 14.64 440.30 Good Medium Fault Monthly Yearly
Gravel [m3] 63.00 19.96 374.70 9M S 10 0 0 0 0
Cement [T] 30.74 12.48 177.90 9M A 2 0 0 0 0
Admixture [Kg] 0.00 98.96 14212.10 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 16 0 0 2 7
Diesel [L] 300.00 180 240 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 756.16 7,351.500 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 1,024.000 14M S 0 0 0 0 1
Cold drawn wire (2.8mm) [Kg] 0.00 94.40 8,303.720 14M A 2 0 0 1 1
D-Bar (14mm) [Kg] 0.00 63.42 1,031.620 14M T 0 0 0 0 0
Tie-wire (1mm) [Kg] 0.00 0.00 500.0
EDC (KWH) Generator (300KVA) (Litters)
Daily Monthly Yearly
Daily Monthly Yearly
Hours Litters Hours Litters Hours Litters
140 454 190796 5:34 150 22.39 390 519.22 8000
3
Delivery Ready Mixed Concrete Delivery (M )
Items / Specification Daily Monthly Yearly
Daily Plan Monthly Yearly
Description 20-40-12 0 0 0.4
9M S 0 0 0 2193 25-15-12 0 4 56
9M A 0 0 0 326 25-21-12 0 1 300.5
9M T 0 0 0 92 Total 0 5 356.9
12M S 0 0 0 1670
12M A 0 0 0 214 Concrete Pipe
12M T 0 0 0 20 Type Daily Monthly Yearly Out Balance
14M S 0 0 0 109 Ø300 1 4 114 0 185
14M A 0 0 0 0 Total 1 4 114 0 185
14M T 0 0 0 0
Total 0 0 0 4624
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 40 1740 0 0 0
9m-A 99 320 0 0 0
9m-T 26 150 0 0 0
12m-S 22 101 0 0 0
12m-A 70 70 0 0 0
14m-S 5 0 0 0 0
Total 262 2381 0 0 0

Yearly Balance
9639 9639

In 2011 Out 2011


5229 4529

29

5.5666666667
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
05/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
0 0 27 2 17 0 46

Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 9 49 1850 9 0 49 0 0 2 51
9M A 2 10 353 2 0 101 0 0 83 184
9M T 2 10 121 2 0 28 0 0 10 38
12M S 18 82 1732 8 0 30 10 0 50 80
12M A 2 10 238 2 0 72 0 0 8 80
12M T 0 0 1 0 0 4 0 0 0 4
14M S 0 0 116 0 0 5 0 0 17 22
14M A 2 10 34 2 0 33 0 0 0 33
14M T 0 0 0 0 0 0 0 0 0 0
Total 35 171 4445 25 0 322 10 0 170 492
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 107.60 17.41 530.49 Good Medium Fault Monthly Yearly
Gravel [m3] 58.50 22.72 377.48 9M S 9 0 0 0 0
Cement [T] 30.37 13.74 194.52 9M A 2 0 0 0 0
Admixture [Kg] 0.00 80.00 14132.10 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 18 0 0 2 7
Diesel [L] 0.00 30 210 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 983.46 6,368.040 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 1,024.000 14M S 0 0 0 0 1
Cold drawn wire (2.8mm) [Kg] 0.00 124.84 8,178.880 14M A 2 0 0 1 1
D-Bar (14mm) [Kg] 0.00 82.92 948.700 14M T 0 0 0 0 0
Tie-wire (1mm) [Kg] 0.00 0.00 500.0
EDC (KWH) Generator (300KVA) (Litters)
Daily Monthly Yearly
Daily Monthly Yearly
Hours Litters Hours Litters Hours Litters
140 454 190796 5:30 0 27.89 390 524.72 8000
3
Delivery Ready Mixed Concrete Delivery (M )
Items / Specification Daily Monthly Yearly
Daily Plan Monthly Yearly
Description 20-40-12 0 0 0.4
9M S 0 0 0 2193 25-15-12 5 9 61
9M A 0 0 0 326 25-21-12 0 1 300.5
9M T 0 0 0 92 Total 5 10 361.9
12M S 0 0 0 1670
12M A 0 0 0 214 Concrete Pipe
12M T 0 0 0 20 Type Daily Monthly Yearly Out Balance
14M S 0 0 0 109 Ø300 1 5 115 0 186
14M A 0 0 0 0 Total 1 5 115 0 186
14M T 0 0 0 0
Total 0 0 0 4624
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 49 1740 0 0 0
9m-A 101 320 0 0 0
9m-T 28 150 0 0 0
12m-S 30 101 0 0 0
12m-A 72 70 0 0 0
14m-S 5 0 0 0 0
Total 285 2381 0 0 0

Yearly Balance
9674 9674

In 2011 Out 2011


5229 4529

29

5.5
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
06/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
1 0 26 2 15 0 44

Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 18 67 1868 18 0 67 0 0 2 69
9M A 2 12 355 2 0 103 0 0 83 186
9M T 2 12 123 2 0 30 0 0 10 40
12M S 18 100 1750 8 0 38 10 0 60 98
12M A 2 12 240 2 0 74 0 0 8 82
12M T 0 0 1 0 0 4 0 0 0 4
14M S 0 0 116 0 0 5 0 0 17 22
14M A 2 12 36 2 0 35 0 0 0 35
14M T 0 0 0 0 0 0 0 0 0 0
Total 44 215 4489 34 0 356 10 0 180 536
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 0.00 46.76 483.73 Good Medium Fault Monthly Yearly
Gravel [m3] 0.00 50.85 326.63 9M S 18 0 0 0 0
Cement [T] 0.00 27.46 167.06 9M A 2 0 0 0 0
Admixture [Kg] 0.00 134.40 13997.70 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 18 0 0 2 7
Diesel [L] 0.00 210 - 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 816.54 5,551.500 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 1,024.000 14M S 0 0 0 0 1
Cold drawn wire (2.8mm) [Kg] 0.00 105.08 8,073.800 14M A 2 0 0 1 1
D-Bar (14mm) [Kg] 0.00 73.40 875.300 14M T 0 0 0 0 0
Tie-wire (1mm) [Kg] 0.00 0.00 500.0
EDC (KWH) Generator (300KVA) (Litters)
Daily Monthly Yearly
Daily Monthly Yearly
Hours Litters Hours Litters Hours Litters
140 454 190796 8:56 150 36.82 540 533.65 8150
3
Delivery Ready Mixed Concrete Delivery (M )
Items / Specification Daily Monthly Yearly
Daily Plan Monthly Yearly
Description 20-40-12 0 0 0.4
9M S 0 0 0 2193 25-15-12 0 9 61
9M A 0 0 0 326 25-21-12 52.5 53.5 353
9M T 0 0 0 92 Total 52.5 62.5 414.4
12M S 0 0 0 1670
12M A 0 0 0 214 Concrete Pipe
12M T 0 0 0 20 Type Daily Monthly Yearly Out Balance
14M S 0 0 0 109 Ø300 1 6 116 0 187
14M A 0 0 0 0 Total 1 6 116 0 187
14M T 0 0 0 0
Total 0 0 0 4624
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 67 1740 0 0 0
9m-A 103 320 0 0 0
9m-T 30 150 0 0 0
12m-S 38 101 0 0 0
12m-A 74 70 0 0 0
14m-S 5 0 0 0 0
Total 317 2381 0 0 0

Yearly Balance
9718 9718

In 2011 Out 2011


5229 4529

29

8.9333333333
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
07/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
6 3 31 4 18 3 65

Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 18 85 1886 18 0 83 0 4 0 83
9M A 2 14 357 2 0 105 0 0 83 188
9M T 2 14 125 2 0 32 0 0 10 42
12M S 18 118 1768 8 0 46 10 7 63 109
12M A 2 14 242 2 0 76 0 1 7 83
12M T 0 0 1 0 0 4 0 0 0 4
14M S 0 0 116 0 0 5 0 0 17 22
14M A 0 12 36 0 0 35 0 0 0 35
14M T 0 0 0 0 0 0 0 0 0 0
Total 42 257 4531 32 0 386 10 12 180 566
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 26.56 12.97 497.32 Good Medium Fault Monthly Yearly
Gravel [m3] 40.00 17.47 349.16 9M S 18 0 0 0 0
Cement [T] 0.00 11.13 155.94 9M A 2 0 0 0 0
Admixture [Kg] 0.00 67.24 13930.46 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 18 0 0 2 7
Diesel [L] 300.00 240 60 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 816.54 4,734.960 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 1,024.000 14M S 0 0 0 0 1
Cold drawn wire (2.8mm) [Kg] 0.00 105.08 7,968.720 14M A 0 0 0 1 1
D-Bar (14mm) [Kg] 0.00 73.40 801.900 14M T 0 0 0 0 0
Tie-wire (1mm) [Kg] 0.00 0.00 500.0
EDC (KWH) Generator (300KVA) (Litters)
Daily Monthly Yearly
Daily Monthly Yearly
Hours Litters Hours Litters Hours Litters
140 454 190796 4:37 150 40.98 690 538.26 8300
3
Delivery Ready Mixed Concrete Delivery (M )
Items / Specification Daily Monthly Yearly
Daily Plan Monthly Yearly
Description 20-40-12 0 0 0.4
9M S 4 0 4 2197 25-15-12 0 9 61
9M A 0 0 0 326 25-21-12 0 53.5 353
9M T 0 0 0 92 Total 0 62.5 414.4
12M S 7 0 7 1677
12M A 1 0 1 215 Concrete Pipe
12M T 0 0 0 20 Type Daily Monthly Yearly Out Balance
14M S 0 0 0 109 Ø300 1 7 117 0 188
14M A 0 0 0 0 Total 1 7 117 0 188
14M T 0 0 0 0
Total 12 0 12 4636
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 83 1740 0 0 0
9m-A 105 320 0 0 0
9m-T 32 150 0 0 0
12m-S 46 101 0 0 0
12m-A 76 70 0 0 0
14m-S 5 0 0 0 0
Total 347 2381 0 0 0

Yearly Balance
9760 9760

In 2011 Out 2011


5229 4529

29

4.6166666667
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
08/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
6 3 31 4 20 2 66

Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 18 103 1904 0 0 0 18 150 -49 -49
9M A 2 16 359 2 0 107 0 0 83 190
9M T 2 16 127 2 0 34 0 0 10 44
12M S 18 136 1786 8 0 54 10 0 73 127
12M A 2 16 244 2 0 78 0 0 7 85
12M T 0 0 1 0 0 4 0 0 0 4
14M S 0 0 116 0 0 5 0 0 17 22
14M A 0 12 36 0 0 35 0 0 0 35
14M T 0 0 0 0 0 0 0 0 0 0
Total 42 299 4573 14 0 317 28 150 141 458
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 79.92 12.91 564.33 Good Medium Fault Monthly Yearly
Gravel [m3] 40.00 17.35 371.81 9M S 18 0 0 0 0
Cement [T] 0.00 11.03 144.91 9M A 2 0 0 0 0
Admixture [Kg] 0.00 67.12 13863.34 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 18 0 0 2 7
Diesel [L] 0.00 0 60 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 11903.00 858.27 15,779.690 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 1,024.000 14M S 0 0 0 0 1
Cold drawn wire (2.8mm) [Kg] 0.00 110.02 7,858.700 14M A 0 0 0 1 1
D-Bar (14mm) [Kg] 2007.90 75.78 2,734.020 14M T 0 0 0 0 0
Tie-wire (1mm) [Kg] 0.00 0.00 500.0
EDC (KWH) Generator (300KVA) (Litters)
Daily Monthly Yearly
Daily Monthly Yearly
Hours Litters Hours Litters Hours Litters
140 454 190796 5:02 0 46.01 690 543.29 8300
3
Delivery Ready Mixed Concrete Delivery (M )
Items / Specification Daily Monthly Yearly
Daily Plan Monthly Yearly
Description 20-40-12 0 0 0.4
9M S 150 0 154 2347 25-15-12 0 9 61
9M A 0 0 0 326 25-21-12 0 53.5 353
9M T 0 0 0 92 Total 0 62.5 414.4
12M S 0 0 7 1677
12M A 0 0 1 215 Concrete Pipe
12M T 0 0 0 20 Type Daily Monthly Yearly Out Balance
14M S 0 0 0 109 Ø300 1 8 118 0 189
14M A 0 0 0 0 Total 1 8 118 0 189
14M T 0 0 0 0
Total 150 0 162 4786
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 0 1740 0 0 0
9m-A 107 320 0 0 0
9m-T 34 150 0 0 0
12m-S 54 101 0 0 0
12m-A 78 70 0 0 0
14m-S 5 0 0 0 0
Total 278 2381 0 0 0

Yearly Balance
9802 9802

In 2011 Out 2011


5229 4529

29

5.0333333333
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
09/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
2 0 28 3 20 0 53

Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 18 121 1922 0 0 0 18 0 -31 -31
9M A 2 18 361 2 0 109 0 0 83 192
9M T 2 18 129 2 0 36 0 0 10 46
12M S 18 154 1804 8 0 62 10 15 68 130
12M A 2 18 246 2 0 80 0 0 7 87
12M T 0 0 1 0 0 4 0 0 0 4
14M S 0 0 116 0 0 5 0 0 17 22
14M A 0 12 36 0 0 35 0 0 0 35
14M T 0 0 0 0 0 0 0 0 0 0
Total 42 341 4615 14 0 331 28 15 154 485
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 132.50 11.65 685.18 Good Medium Fault Monthly Yearly
Gravel [m3] 0.00 18.16 353.65 9M S 18 0 0 0 0
Cement [T] 30.59 11.05 164.45 9M A 2 0 0 0 0
Admixture [Kg] 0.00 57.48 13795.86 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 18 0 0 2 7
Diesel [L] 300.00 210 150 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 846.70 14,932.990 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 1,024.000 14M S 0 0 0 0 1
Cold drawn wire (2.8mm) [Kg] 0.00 105.24 7,753.460 14M A 0 0 0 1 1
D-Bar (14mm) [Kg] 0.00 73.22 2,660.800 14M T 0 0 0 0 0
Tie-wire (1mm) [Kg] 0.00 0.00 500.0
EDC (KWH) Generator (300KVA) (Litters)
Daily Monthly Yearly
Daily Monthly Yearly
Hours Litters Hours Litters Hours Litters
140 454 190796 4:19 150 50.32 840 547.6 8450
3
Delivery Ready Mixed Concrete Delivery (M )
Items / Specification Daily Monthly Yearly
Daily Plan Monthly Yearly
Description 20-40-12 0 0 0.4
9M S 0 0 154 2347 25-15-12 0 9 61
9M A 0 0 0 326 25-21-12 0 53.5 353
9M T 0 0 0 92 Total 0 62.5 414.4
12M S 15 0 22 1692
12M A 0 0 1 215 Concrete Pipe
12M T 0 0 0 20 Type Daily Monthly Yearly Out Balance
14M S 0 0 0 109 Ø300 1 9 119 0 190
14M A 0 0 0 0 Total 1 9 119 0 190
14M T 0 0 0 0
Total 15 0 177 4801
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 0 1740 0 0 0
9m-A 109 320 0 0 0
9m-T 36 150 0 0 0
12m-S 62 101 0 0 0
12m-A 80 70 0 0 0
14m-S 5 0 0 0 0
Total 292 2381 0 0 0

Yearly Balance
9844 9844

In 2011 Out 2011


5229 4529

29

4.3166666667
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
10/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
6 3 29 4 19 2 63

Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 18 139 1940 0 0 0 18 18 -31 -31
9M A 2 20 363 2 0 111 0 2 81 192
9M T 2 20 131 2 0 38 0 0 10 48
12M S 18 172 1822 8 0 70 10 0 78 148
12M A 2 20 248 1 0 81 1 0 8 89
12M T 0 0 1 0 0 4 0 0 0 4
14M S 0 0 116 0 0 5 0 0 17 22
14M A 0 12 36 0 0 35 0 0 0 35
14M T 0 0 0 0 0 0 0 0 0 0
Total 42 383 4657 13 0 344 29 20 163 507
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 0.00 15.03 670.15 Good Medium Fault Monthly Yearly
Gravel [m3] 0.00 19.55 334.00 9M S 18 0 0 0 0
Cement [T] 0.00 12.14 0.10 9M A 2 0 0 0 0
Admixture [Kg] 0.00 71.98 152.31 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 13,724 12M S 18 0 0 2 7
Diesel [L] 0.00 60 90 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 816.54 14,116.450 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 1,024.000 14M S 0 0 0 0 1
Cold drawn wire (2.8mm) [Kg] 0.00 105.08 7,648.380 14M A 0 0 0 1 1
D-Bar (14mm) [Kg] 0.00 73.40 2,587.400 14M T 0 0 0 0 0
Tie-wire (1mm) [Kg] 0.00 0.00 500.0
EDC (KWH) Generator (300KVA) (Litters)
Daily Monthly Yearly
Daily Monthly Yearly
Hours Litters Hours Litters Hours Litters
140 454 190796 4:56 0 55.25 840 552.53 8450
3
Delivery Ready Mixed Concrete Delivery (M )
Items / Specification Daily Monthly Yearly
Daily Plan Monthly Yearly
Description 20-40-12 0 0 0.4
9M S 18 0 172 2365 25-15-12 0 9 61
9M A 2 0 2 328 25-21-12 3.5 57 356.5
9M T 0 0 0 92 Total 3.5 66 417.9
12M S 0 0 22 1692
12M A 0 0 1 215 Concrete Pipe
12M T 0 0 0 20 Type Daily Monthly Yearly Out Balance
14M S 0 0 0 109 Ø300 1 10 120 0 191
14M A 0 0 0 0 Total 1 10 120 0 191
14M T 0 0 0 0
Total 20 0 197 4821
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 0 1740 0 0 0
9m-A 111 320 0 0 0
9m-T 38 150 0 0 0
12m-S 70 101 0 0 0
12m-A 81 70 0 0 0
14m-S 5 0 0 0 0
Total 305 2381 0 0 0

Yearly Balance
9886 9886

In 2011 Out 2011


5229 4529

29

4.9333333333
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
11/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
6 3 30 4 19 1 63

Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 18 157 1958 0 0 0 18 1 -14 -14
9M A 2 22 365 2 0 113 0 0 81 194
9M T 2 22 133 2 0 40 0 0 10 50
12M S 18 190 1840 8 0 78 10 0 88 166
12M A 2 22 250 2 0 83 0 0 8 91
12M T 0 0 1 0 0 4 0 0 0 4
14M S 0 0 116 0 0 5 0 0 17 22
14M A 0 12 36 0 0 35 0 0 0 35
14M T 0 0 0 0 0 0 0 0 0 0
Total 42 425 4699 14 0 358 28 1 190 548
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 0.00 21.36 648.79 Good Medium Fault Monthly Yearly
Gravel [m3] 40.00 26.30 347.80 9M S 18 0 0 0 0
Cement [T] 30.82 15.19 167.94 9M A 2 0 0 0 0
Admixture [Kg] 0.00 107.14 13616.74 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 18 0 0 2 7
Diesel [L] 0.00 90 - 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 816.54 13,299.910 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 1,024.000 14M S 0 0 0 0 1
Cold drawn wire (2.8mm) [Kg] 0.00 105.08 7,543.300 14M A 0 0 0 1 1
D-Bar (14mm) [Kg] 0.00 73.40 2,514.000 14M T 0 0 0 0 0
Tie-wire (1mm) [Kg] 0.00 0.00 500.0
EDC (KWH) Generator (300KVA) (Litters)
Daily Monthly Yearly
Daily Monthly Yearly
Hours Litters Hours Litters Hours Litters
140 454 190796 5:37 60 60.86 900 558.14 8510
3
Delivery Ready Mixed Concrete Delivery (M )
Items / Specification Daily Monthly Yearly
Daily Plan Monthly Yearly
Description 20-40-12 0 0 0.4
9M S 1 0 173 2366 25-15-12 0 9 61
9M A 0 0 2 328 25-21-12 13.5 70.5 370
9M T 0 0 0 92 Total 13.5 79.5 431.4
12M S 0 0 22 1692
12M A 0 0 1 215 Concrete Pipe
12M T 0 0 0 20 Type Daily Monthly Yearly Out Balance
14M S 0 0 0 109 Ø300 1 11 121 0 192
14M A 0 0 0 0 Total 1 11 121 0 192
14M T 0 0 0 0
Total 1 0 198 4822
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 0 1740 0 0 0
9m-A 113 320 0 0 0
9m-T 40 150 0 0 0
12m-S 78 101 0 0 0
12m-A 83 70 0 0 0
14m-S 5 0 0 0 0
Total 319 2381 0 0 0

Yearly Balance
9928 9928

In 2011 Out 2011


5229 4529

29

5.6166666667
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
12/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
6 2 29 4 20 3 64

Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 18 175 1976 0 0 0 18 0 4 4
9M A 2 24 367 2 0 115 0 0 81 196
9M T 2 24 135 2 0 42 0 0 10 52
12M S 18 208 1858 8 0 86 10 0 98 184
12M A 2 24 252 2 0 85 0 0 8 93
12M T 0 0 1 0 0 4 0 0 0 4
14M S 0 0 116 0 0 5 0 0 17 22
14M A 0 12 36 0 0 35 0 0 0 35
14M T 0 0 0 0 0 0 0 0 0 0
Total 42 467 4741 14 0 372 28 0 218 590
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 0.00 65.27 583.52 Good Medium Fault Monthly Yearly
Gravel [m3] 79.79 69.01 358.58 9M S 18 0 0 0 0
Cement [T] 0.00 36.21 131.73 9M A 2 0 0 0 0
Admixture [Kg] 0.00 199.20 13417.54 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 18 0 0 2 7
Diesel [L] 300.00 210 90 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 816.54 12,483.370 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 1,024.000 14M S 0 0 0 0 1
Cold drawn wire (2.8mm) [Kg] 0.00 105.08 7,438.220 14M A 0 0 0 1 1
D-Bar (14mm) [Kg] 0.00 73.40 2,440.600 14M T 0 0 0 0 0
Tie-wire (1mm) [Kg] 0.00 0.00 500.0
EDC (KWH) Generator (300KVA) (Litters)
Daily Monthly Yearly
Daily Monthly Yearly
Hours Litters Hours Litters Hours Litters
84 538 190880 8:55 180 69.77 1080 567.05 8660
3
Delivery Ready Mixed Concrete Delivery (M )
Items / Specification Daily Monthly Yearly
Daily Plan Monthly Yearly
Description 20-40-12 0 0 0.4
9M S 0 0 173 2366 25-15-12 0 9 61
9M A 0 0 2 328 25-21-12 81 151.5 451
9M T 0 0 0 92 Total 81 160.5 512.4
12M S 0 0 22 1692
12M A 0 0 1 215 Concrete Pipe
12M T 0 0 0 20 Type Daily Monthly Yearly Out Balance
14M S 0 0 0 109 Ø300 1 12 122 0 193
14M A 0 0 0 0 Total 1 12 122 0 193
14M T 0 0 0 0
Total 0 0 198 4822
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 0 1740 0 0 0
9m-A 115 320 0 0 0
9m-T 42 150 0 0 0
12m-S 86 101 0 0 0
12m-A 85 70 0 0 0
14m-S 5 0 0 0 0
Total 333 2381 0 0 0

Yearly Balance
9970 9970

In 2011 Out 2011


5229 4529

29

8.9166666667
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
13/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
0 0 1 0 0 0 1

Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 0 175 1976 0 0 0 0 0 4 4
9M A 0 24 367 0 0 115 0 0 81 196
9M T 0 24 135 0 0 42 0 0 10 52
12M S 0 208 1858 0 0 86 0 0 98 184
12M A 0 24 252 0 0 85 0 0 8 93
12M T 0 0 1 0 0 4 0 0 0 4
14M S 0 0 116 0 0 5 0 0 17 22
14M A 0 12 36 0 0 35 0 0 0 35
14M T 0 0 0 0 0 0 0 0 0 0
Total 0 467 4741 0 0 372 0 0 218 590
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 0.00 17.11 260.18 Good Medium Fault Monthly Yearly
Gravel [m3] 97.83 22.65 135.48 9M S 0 0 0 0 0
Cement [T] 0.00 13.70 43.24 9M A 0 0 0 0 0
Admixture [Kg] 0.00 0.00 14560.86 9M T 0 0 0 0 1
Mold oil [Kg] 0.00 80.06 820 12M S 0 0 0 2 7
Diesel [L] 0.00 90 - 12M A 0 0 0 0 0
PC wire (5mm) [Kg] 0.00 816.54 16,144.590 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 1,024.000 14M S 0 0 0 0 1
Cold drawn wire (2.8mm) [Kg] 0.00 105.08 9,395.960 14M A 0 0 0 1 1
D-Bar (14mm) [Kg] 0.00 73.40 2,100.000 14M T 0 0 0 0 0
Tie-wire (1mm) [Kg] 0.00 0.00 1,150.0
EDC (KWH) Generator (300KVA) (Litters)
Daily Monthly Yearly
Daily Monthly Yearly
Hours Litters Hours Litters Hours Litters
112 650 190992 0:00 0 69.77 1080 567.05 8660
3
Delivery Ready Mixed Concrete Delivery (M )
Items / Specification Daily Monthly Yearly
Daily Plan Monthly Yearly
Description 20-40-12 0 0 0.4
9M S 0 0 173 2366 25-15-12 0 9 61
9M A 0 0 2 328 25-21-12 0 151.5 451
9M T 0 0 0 92 Total 0 160.5 512.4
12M S 0 0 22 1692
12M A 0 0 1 215 Concrete Pipe
12M T 0 0 0 20 Type Daily Monthly Yearly Out Balance
14M S 0 0 0 109 Ø300 0 12 122 0 193
14M A 0 0 0 0 Total 0 12 122 0 193
14M T 0 0 0 0
Total 0 0 198 4822
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 0 1740 0 0 0
9m-A 115 320 0 0 0
9m-T 42 150 0 0 0
12m-S 86 101 0 0 0
12m-A 85 70 0 0 0
14m-S 5 0 0 0 0
Total 333 2381 0 0 0

Yearly Balance
9970 9970

In 2011 Out 2011


5229 4529

29

8.9166666667
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
14/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
0 0 28 3 17 0 48

Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 18 193 1994 0 0 0 18 0 22 22
9M A 2 26 369 2 0 117 0 0 81 198
9M T 2 26 137 2 0 44 0 0 10 54
12M S 18 226 1876 8 0 94 10 0 108 202
12M A 2 26 254 2 0 87 0 0 8 95
12M T 0 0 1 0 0 4 0 0 0 4
14M S 0 0 116 0 0 5 0 0 17 22
14M A 0 12 36 0 0 35 0 0 0 35
14M T 0 0 0 0 0 0 0 0 0 0
Total 42 509 4783 14 0 386 28 0 246 632
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 0.00 20.89 562.63 Good Medium Fault Monthly Yearly
Gravel [m3] 0.00 25.20 333.38 9M S 18 0 0 0 0
Cement [T] 30.49 14.65 147.57 9M A 2 0 0 0 0
Admixture [Kg] 0.00 104.98 13312.56 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 18 0 0 2 7
Diesel [L] 300.00 210 180 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 816.54 11,666.830 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 1,024.000 14M S 0 0 0 0 1
Cold drawn wire (2.8mm) [Kg] 0.00 105.08 7,333.140 14M A 0 0 0 1 1
D-Bar (14mm) [Kg] 0.00 73.40 2,367.200 14M T 0 0 0 0 0
Tie-wire (1mm) [Kg] 0.00 0.00 500.0
Generator (300KVA) (Litters)
Daily Monthly Yearly
Daily Monthly Yearly
Hours Litters Hours Litters Hours Litters
129 779 191121 4:43 150 74.48 1230 571.76 8810
3
Delivery Ready Mixed Concrete Delivery (M )
Items / Specification Daily Monthly Yearly
Daily Plan Monthly Yearly
Description 20-40-12 0 0 0.4
9M S 0 0 173 2366 25-15-12 0 9 61
9M A 0 0 2 328 25-21-12 12 163.5 463
9M T 0 0 0 92 Total 12 172.5 524.4
12M S 0 0 22 1692
12M A 0 0 1 215 Concrete Pipe
12M T 0 0 0 20 Type Daily Monthly Yearly Out Balance
14M S 0 0 0 109 Ø300 1 13 123 0 194
14M A 0 0 0 0 Total 1 13 123 0 194
14M T 0 0 0 0
Total 0 0 198 4822
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 0 1740 0 0 0
9m-A 117 320 0 0 0
9m-T 44 150 0 0 0
12m-S 94 101 0 0 0
12m-A 87 70 0 0 0
14m-S 5 0 0 0 0
Total 347 2381 0 0 0

Yearly Balance
10012 10012

In 2011 Out 2011


5229 4529

29

4.7166666667
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
15/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
0 0 28 3 18 0 49

Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 18 211 2012 0 0 0 18 0 40 40
9M A 2 28 371 2 0 119 0 0 81 200
9M T 2 28 139 2 0 46 0 0 10 56
12M S 18 244 1894 8 0 102 10 0 118 220
12M A 2 28 256 2 0 89 0 0 8 97
12M T 0 0 1 0 0 4 0 0 0 4
14M S 0 0 116 0 0 5 0 0 17 22
14M A 0 12 36 0 0 35 0 0 0 35
14M T 0 0 0 0 0 0 0 0 0 0
Total 42 551 4825 14 0 400 28 0 274 674
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 0.00 12.59 550.04 Good Medium Fault Monthly Yearly
Gravel [m3] 20.00 17.21 336.17 9M S 18 0 0 0 0
Cement [T] 31.17 10.96 167.78 9M A 2 0 0 0 0
Admixture [Kg] 0.00 64.74 13247.82 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 18 0 0 2 7
Diesel [L] 0.00 30 150 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 816.54 10,850.290 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 1,024.000 14M S 0 0 0 0 1
Cold drawn wire (2.8mm) [Kg] 0.00 105.08 7,228.060 14M A 0 0 0 1 1
D-Bar (14mm) [Kg] 0.00 73.40 2,293.800 14M T 0 0 0 0 0
Tie-wire (1mm) [Kg] 0.00 0.00 500.0
EDC (KWH) Generator (300KVA) (Litters)
Daily Monthly Yearly
Daily Monthly Yearly
Hours Litters Hours Litters Hours Litters
137 916 191258 3:36 0 78.08 1230 575.36 8810
3
Delivery Ready Mixed Concrete Delivery (M )
Items / Specification Daily Monthly Yearly
Daily Plan Monthly Yearly
Description 20-40-12 0 0 0.4
9M S 0 0 173 2366 25-15-12 0 9 61
9M A 0 0 2 328 25-21-12 0 163.5 463
9M T 0 0 0 92 Total 0 172.5 524.4
12M S 0 0 22 1692
12M A 0 0 1 215 Concrete Pipe
12M T 0 0 0 20 Type Daily Monthly Yearly Out Balance
14M S 0 0 0 109 Ø300 1 14 124 0 195
14M A 0 0 0 0 Total 1 14 124 0 195
14M T 0 0 0 0
Total 0 0 198 4822
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 0 1740 0 0 0
9m-A 119 320 0 0 0
9m-T 46 150 0 0 0
12m-S 102 101 0 0 0
12m-A 89 70 0 0 0
14m-S 5 0 0 0 0
Total 361 2381 0 0 0

Yearly Balance
10054 10054

In 2011 Out 2011


5229 4529

29

3.6
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
16/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
0 0 29 3 19 0 51

Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 18 229 2030 0 0 0 18 0 58 58
9M A 2 30 373 2 0 121 0 0 81 202
9M T 2 30 141 2 0 48 0 0 10 58
12M S 18 262 1912 8 0 9 10 0 229 238
12M A 2 30 258 2 0 91 0 0 8 99
12M T 0 0 1 0 0 4 0 0 0 4
14M S 0 0 116 0 0 5 0 0 17 22
14M A 0 12 36 0 0 35 0 0 0 35
14M T 0 0 0 0 0 0 0 0 0 0
Total 42 593 4867 14 0 313 28 0 403 716
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 0.00 12.91 537.13 Good Medium Fault Monthly Yearly
Gravel [m3] 0.00 17.54 318.63 9M S 18 0 0 0 0
Cement [T] 0.00 10.96 156.82 9M A 2 0 0 0 0
Admixture [Kg] 0.00 89.56 13158.26 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 18 0 0 2 7
Diesel [L] 0.00 120 30 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 816.54 10,033.750 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 1,024.000 14M S 0 0 0 0 1
Cold drawn wire (2.8mm) [Kg] 0.00 105.08 7,122.980 14M A 0 0 0 1 1
D-Bar (14mm) [Kg] 0.00 73.40 2,220.400 14M T 0 0 0 0 0
Tie-wire (1mm) [Kg] 0.00 0.00 500.0
EDC (KWH) Generator (300KVA) (Litters)
Daily Monthly Yearly
Daily Monthly Yearly
Hours Litters Hours Litters Hours Litters
162 1078 191420 3:05 90 81.16 1320 578.44 8900
3
Delivery Ready Mixed Concrete Delivery (M )
Items / Specification Daily Monthly Yearly
Daily Plan Monthly Yearly
Description 20-40-12 0 0 0.4
9M S 0 0 173 2366 25-15-12 0 9 61
9M A 0 0 2 328 25-21-12 0 163.5 463
9M T 0 0 0 92 Total 0 172.5 524.4
12M S 0 0 22 1692
12M A 0 0 1 215 Concrete Pipe
12M T 0 0 0 20 Type Daily Monthly Yearly Out Balance
14M S 0 0 0 109 Ø300 1 15 125 0 196
14M A 0 0 0 0 Total 1 15 125 0 196
14M T 0 0 0 0
Total 0 0 198 4822
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 0 1740 0 0 0
9m-A 121 320 0 0 0
9m-T 48 150 0 0 0
12m-S 9 101 0 0 0
12m-A 91 70 0 0 0
14m-S 5 0 0 0 0
Total 274 2381 0 0 0

Yearly Balance
10096 10096

In 2011 Out 2011


5229 4529

29

3.0833333333
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
17/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
6 3 30 3 20 2 64
Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 18 247 2048 0 0 0 18 0 76 76
9M A 2 32 375 2 0 123 0 0 81 204
9M T 2 32 143 2 0 50 0 0 10 60
12M S 18 280 1930 8 0 17 10 62 177 194
12M A 2 32 260 2 0 93 0 0 8 101
12M T 0 0 1 0 0 4 0 0 0 4
14M S 0 0 116 0 0 5 0 0 17 22
14M A 0 12 36 0 0 35 0 0 0 35
14M T 0 0 0 0 0 0 0 0 0 0
Total 42 635 4909 14 0 327 28 62 369 696
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 51.23 15.43 572.93 Good Medium Fault Monthly Yearly
Gravel [m3] 0.00 20.16 298.47 9M S 18 0 0 0 0
Cement [T] 0.00 12.23 144.59 9M A 2 0 0 0 0
Admixture [Kg] 0.00 95.12 13063.00 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 18 0 0 2 7
Diesel [L] 300.00 210 120 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 15135.00 816.54 24,352.21 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 3233.00 0.00 4,257.00 14M S 0 0 0 0 1
PC wire (9mm) [Kg] 1764.00 0.00 1,764.00 14M A 0 0 0 1 1
Cold drawn wire (2.8mm) [Kg] 0.00 105.08 7,017.900 14M T 0 0 0 0 0
D-Bar (14mm) [Kg] 0.00 73.40 2,147.000
Total 42 0 0 3 10
Tie-wire (1mm) [Kg] 0.00 0.00 500.0
Generator (300KVA) (Litters)
Daily Monthly Yearly
EDC (KWH) Hours Litters Hours Litters Hours Litters
Daily Monthly 5:05 150 86.24 1470 583.52 9050
3
163 1241 191583 Ready Mixed Concrete Delivery (M )
Delivery Specification Daily Monthly Yearly
Type Daily Plan Monthly Yearly 20-40-12 0 0 0.4
9M S 0 0 173 2366 25-15-12 0 9 61
9M A 0 0 2 328 25-21-12 4 167.5 467
9M T 0 0 0 92 Total 4 176.5 528.4
12M S 62 0 84 1754
12M A 0 0 1 215 Concrete Pipe
12M T 0 0 0 20 Type Daily Monthly Yearly Out Balance
14M S 0 0 0 109 Ø300 1 16 126 0 197
14M A 0 0 0 0 Total 1 16 126 0 197
14M T 0 0 0 0
Total 62 0 260 4884
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 0 1740 0 0 0
9m-A 123 320 0 0 0
9m-T 50 150 0 0 0
12m-S 17 101 0 0 0
12m-A 93 70 0 0 0
14m-S 5 0 0 0 0
Total 288 2381 0 0 0

Yearly Balance
10138 10138

In 2011 Out 2011


5229 4529

29

5.0833333333
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
18/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
5 3 29 4 20 2 63
Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 18 265 2066 0 0 0 18 38 56 56
9M A 2 34 377 2 0 125 0 0 81 206
9M T 2 34 145 2 0 52 0 0 10 62
12M S 18 298 1948 8 0 25 10 65 122 147
12M A 2 34 262 2 0 95 0 2 6 101
12M T 0 0 1 0 0 4 0 0 0 4
14M S 0 0 116 0 0 5 0 0 17 22
14M A 0 12 36 0 0 35 0 0 0 35
14M T 0 0 0 0 0 0 0 0 0 0
Total 42 677 4951 14 0 341 28 105 292 633
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 74.05 14.26 632.72 Good Medium Fault Monthly Yearly
Gravel [m3] 61.39 18.92 340.94 9M S 18 0 0 0 0
Cement [T] 0.00 11.59 133.00 9M A 2 0 0 0 0
Admixture [Kg] 0.00 92.12 12971.02 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 18 0 0 2 7
Diesel [L] 0.00 60 60 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 753.06 23,599.15 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 4,257.00 14M S 0 0 0 0 1
PC wire (9mm) [Kg] 0.00 0.00 1,764.00 14M A 0 0 0 1 1
Cold drawn wire (2.8mm) [Kg] 0.00 97.08 6,920.820 14M T 0 0 0 0 0
D-Bar (14mm) [Kg] 0.00 68.68 2,078.320
Total 42 0 0 3 10
Tie-wire (1mm) [Kg] 0.00 0.00 500.0
Generator (300KVA) (Litters)
Daily Monthly Yearly
EDC (KWH) Hours Litters Hours Litters Hours Litters
Daily Monthly 3:32 0 89.77 1470 587.05 9050
3
103 1344 191686 Ready Mixed Concrete Delivery (M )
Delivery Specification Daily Monthly Yearly
Type Daily Plan Monthly Yearly 20-40-12 0 0 0.4
9M S 38 0 211 2404 25-15-12 0 9 61
9M A 0 0 2 328 25-21-12 2 169.5 469
9M T 0 0 0 92 Total 2 178.5 530.4
12M S 65 0 149 1819
12M A 2 0 3 217 Concrete Pipe
12M T 0 0 0 20 Type Daily Monthly Yearly Out Balance
14M S 0 0 0 109 Ø300 1 17 127 0 198
14M A 0 0 0 0 Total 1 17 127 0 198
14M T 0 0 0 0
Total 105 0 365 4989
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 0 1740 0 0 0
9m-A 125 320 0 0 0
9m-T 52 150 0 0 0
12m-S 25 101 0 0 0
12m-A 95 70 0 0 0
14m-S 5 0 0 0 0
Total 302 2381 0 0 0

Yearly Balance
10180 10180

In 2011 Out 2011


5229 4529

29

3.5333333333
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
19/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
5 3 30 4 20 1 63
Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 18 283 2084 0 0 0 18 20 54 54
9M A 2 36 379 2 0 127 0 0 81 208
9M T 2 36 147 2 0 54 0 0 10 64
12M S 18 316 1966 8 0 33 10 13 119 152
12M A 2 36 264 2 0 97 0 2 4 101
12M T 0 0 1 0 0 4 0 0 0 4
14M S 0 0 116 0 0 5 0 0 17 22
14M A 0 12 36 0 0 35 0 0 0 35
14M T 0 0 0 0 0 0 0 0 0 0
Total 42 719 4993 14 0 355 28 35 285 640
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 73.26 53.63 652.35 Good Medium Fault Monthly Yearly
Gravel [m3] 122.00 56.76 406.18 9M S 18 0 0 0 0
Cement [T] 61.06 30.12 163.94 9M A 2 0 0 0 0
Admixture [Kg] 0.00 167.44 12803.58 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 18 0 0 2 7
Diesel [L] 300.00 210 150 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 816.54 22,782.61 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 4,257.00 14M S 0 0 0 0 1
PC wire (9mm) [Kg] 0.00 0.00 1,764.00 14M A 0 0 0 1 1
Cold drawn wire (2.8mm) [Kg] 0.00 105.08 6,815.740 14M T 0 0 0 0 0
D-Bar (14mm) [Kg] 0.00 73.40 2,004.920
Total 42 0 0 3 10
Tie-wire (1mm) [Kg] 0.00 0.00 500.0
Generator (300KVA) (Litters)
Daily Monthly Yearly
EDC (KWH) Hours Litters Hours Litters Hours Litters
Daily Monthly 7:07 150 96.88 1620 594.16 9200
3
173 1517 191859 Ready Mixed Concrete Delivery (M )
Delivery Specification Daily Monthly Yearly
Type Daily Plan Monthly Yearly 20-40-12 0 0 0.4
9M S 20 0 231 2424 25-15-12 0 9 61
9M A 0 0 2 328 25-21-12 62 231.5 531
9M T 0 0 0 92 Total 62 240.5 592.4
12M S 13 0 162 1832
12M A 2 0 5 219 Concrete Pipe
12M T 0 0 0 20 Type Daily Monthly Yearly Out Balance
14M S 0 0 0 109 Ø300 1 18 128 0 199
14M A 0 0 0 0 Total 1 18 128 0 199
14M T 0 0 0 0
Total 35 0 400 5024
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 0 1740 0 0 0
9m-A 127 320 0 0 0
9m-T 54 150 0 0 0
12m-S 33 101 0 0 0
12m-A 97 70 0 0 0
14m-S 5 0 0 0 0
Total 316 2381 0 0 0

Yearly Balance
10222 10222

In 2011 Out 2011


5229 4529

29

7.1166666667
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
20/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
0 0 27 2 15 0 44
Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 18 301 2102 0 0 0 18 0 72 72
9M A 2 38 381 2 0 129 0 0 81 210
9M T 2 38 149 2 0 56 0 0 10 66
12M S 18 334 1984 8 0 41 10 0 129 170
12M A 2 38 266 2 0 99 0 0 4 103
12M T 0 0 1 0 0 4 0 0 0 4
14M S 0 0 116 0 0 5 0 0 17 22
14M A 0 12 36 0 0 35 0 0 0 35
14M T 0 0 0 0 0 0 0 0 0 0
Total 42 761 5035 14 0 369 28 0 313 682
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 77.28 64.95 664.68 Good Medium Fault Monthly Yearly
Gravel [m3] 66.50 70.68 402.00 9M S 18 0 0 0 0
Cement [T] 0.00 36.15 127.79 9M A 2 0 0 0 0
Admixture [Kg] 0.00 194.28 12609.30 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 18 0 0 2 7
Diesel [L] 0.00 300 120 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 816.54 21,966.07 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 4,257.00 14M S 0 0 0 0 1
PC wire (9mm) [Kg] 0.00 0.00 1,764.00 14M A 0 0 0 1 1
Cold drawn wire (2.8mm) [Kg] 0.00 105.08 6,710.660 14M T 0 0 0 0 0
D-Bar (14mm) [Kg] 0.00 73.40 1,931.520
Total 42 0 0 3 10
Tie-wire (1mm) [Kg] 0.00 0.00 500.0
Generator (300KVA) (Litters)
Daily Monthly Yearly
EDC (KWH) Hours Litters Hours Litters Hours Litters
Daily Monthly 7:40 0 104.54 1620 601.82 9200
3
48 1565 191907 Ready Mixed Concrete Delivery (M )
Delivery Specification Daily Monthly Yearly
Type Daily Plan Monthly Yearly 20-40-12 0 0 0.4
9M S 0 0 231 2424 25-15-12 0 9 61
9M A 0 0 2 328 25-21-12 82 313.5 613
9M T 0 0 0 92 Total 82 322.5 674.4
12M S 0 0 162 1832
12M A 0 0 5 219 Concrete Pipe
12M T 0 0 0 20 Type Daily Monthly Yearly Out Balance
14M S 0 0 0 109 Ø300 0 17 127 0 198
14M A 0 0 0 0 Total 0 17 127 0 198
14M T 0 0 0 0
Total 0 0 400 5024
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 0 1740 0 0 0
9m-A 129 320 0 0 0
9m-T 56 150 0 0 0
12m-S 41 101 0 0 0
12m-A 99 70 0 0 0
14m-S 5 0 0 0 0
Total 330 2381 0 0 0

Yearly Balance
10264 10264

In 2011 Out 2011


5229 4529

29

7.6666666667
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
21/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
6 3 30 3 20 2 64
Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 18 319 2120 18 0 90 0 0 0 90
9M A 2 40 383 2 0 131 0 0 81 212
9M T 2 40 151 2 0 58 0 0 10 68
12M S 18 352 2002 8 0 49 10 33 106 155
12M A 2 40 268 2 0 101 0 3 1 102
12M T 0 0 1 0 0 4 0 0 0 4
14M S 0 0 116 0 0 5 0 0 17 22
14M A 0 12 36 0 0 35 0 0 0 35
14M T 0 0 0 0 0 0 0 0 0 0
Total 42 803 5077 32 0 473 10 36 215 688
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 75.46 32.17 707.97 Good Medium Fault Monthly Yearly
Gravel [m3] 38.50 34.53 405.97 9M S 2 0 0 0 0
Cement [T] 30.13 18.40 139.52 9M A 2 0 0 0 0
Admixture [Kg] 0.00 113.04 12496.26 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 18 0 0 2 7
Diesel [L] 300.00 240 180 12M A 0 0 0 0 0
PC wire (5mm) [Kg] 0.00 816.54 21,149.53 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 4,257.00 14M S 0 0 0 0 1
PC wire (9mm) [Kg] 0.00 0.00 1,764.00 14M A 0 0 0 1 1
Cold drawn wire (2.8mm) [Kg] 0.00 105.08 6,605.580 14M T 0 0 0 0 0
D-Bar (14mm) [Kg] 0.00 73.40 1,858.120
Total 24 0 0 3 10
Tie-wire (1mm) [Kg] 0.00 0.00 500.0
Generator (300KVA) (Litters)
Daily Monthly Yearly
EDC (KWH) Hours Litters Hours Litters Hours Litters
Daily Monthly 6:07 180 110.65 1800 607.93 9380
3
150 1715 192057 Ready Mixed Concrete Delivery (M )
Delivery Specification Daily Monthly Yearly
Type Daily Plan Monthly Yearly 20-40-12 0 0 0.4
9M S 0 0 231 2424 25-15-12 0 9 61
9M A 0 0 2 328 25-21-12 36 349.5 649
9M T 0 0 0 92 Total 36 358.5 710.4
12M S 33 0 195 1865
12M A 3 0 8 222 Concrete Pipe
12M T 0 0 0 20 Type Daily Monthly Yearly Out Balance
14M S 0 0 0 109 Ø300 0 17 127 0 198
14M A 0 0 0 0 Total 0 17 127 0 198
14M T 0 0 0 0
Total 36 0 436 5060
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 90 1740 0 0 0
9m-A 131 320 0 0 0
9m-T 58 150 0 0 0
12m-S 49 101 0 0 0
12m-A 101 70 0 0 0
14m-S 5 0 0 0 0
Total 434 2381 0 0 0

Yearly Balance
10306 10306

In 2011 Out 2011


5229 4529

29

6.1166666667
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
22/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
6 3 30 4 21 0 64
Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 2 321 2122 2 0 92 0 0 0 92
9M A 2 42 385 2 0 133 0 2 79 212
9M T 2 42 153 2 0 60 0 0 10 70
12M S 18 370 2020 8 0 57 10 0 116 173
12M A 0 40 268 0 0 100 0 1 1 101
12M T 0 0 1 0 0 4 0 0 0 4
14M S 0 0 116 0 0 5 0 0 17 22
14M A 0 12 36 0 0 35 0 0 0 35
14M T 0 0 0 0 0 0 0 0 0 0
Total 24 827 5101 14 0 486 10 3 223 709
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 24.96 12.64 720.29 Good Medium Fault Monthly Yearly
Gravel [m3] 0.00 17.30 388.67 9M S 18 0 0 0 0
Cement [T] 30.26 10.85 158.93 9M A 2 0 0 0 0
Admixture [Kg] 0.00 89.70 12406.56 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 18 0 0 2 7
Diesel [L] 0.00 150 30 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 560.58 20,588.95 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 4,257.00 14M S 0 0 0 0 1
PC wire (9mm) [Kg] 0.00 0.00 1,764.00 14M A 0 0 0 1 1
Cold drawn wire (2.8mm) [Kg] 0.00 67.96 6,537.620 14M T 0 0 0 0 0
D-Bar (14mm) [Kg] 0.00 47.40 1,810.720
Total 42 0 0 3 10
Tie-wire (1mm) [Kg] 0.00 0.00 500.0
Generator (300KVA) (Litters)
Daily Monthly Yearly
EDC (KWH) Hours Litters Hours Litters Hours Litters
Daily Monthly 4:38 90 115.28 1890 612.56 9470
3
143 1858 192200 Ready Mixed Concrete Delivery (M )
Delivery Specification Daily Monthly Yearly
Type Daily Plan Monthly Yearly 20-40-12 0 0 0.4
9M S 0 0 231 2424 25-15-12 0 9 61
9M A 2 0 4 330 25-21-12 0 349.5 649
9M T 0 0 0 92 Total 0 358.5 710.4
12M S 0 0 195 1865
12M A 1 0 9 223 Concrete Pipe
12M T 0 0 0 20 Type Daily Monthly Yearly Out Balance
14M S 0 0 0 109 Ø300 0 17 127 0 198
14M A 0 0 0 0 Total 0 17 127 0 198
14M T 0 0 0 0
Total 3 0 439 5063
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 92 1740 0 0 0
9m-A 133 320 0 0 0
9m-T 60 150 0 0 0
12m-S 57 101 0 0 0
12m-A 100 70 0 0 0
14m-S 5 0 0 0 0
Total 447 2381 0 0 0

Yearly Balance
10330 10330

In 2011 Out 2011


5229 4529

29

4.6333333333
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
23/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
6 3 29 4 19 3 64
Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 18 339 2140 18 0 110 0 0 0 110
9M A 2 44 387 2 0 135 0 0 79 214
9M T 2 44 155 2 0 62 0 0 10 72
12M S 18 388 2038 8 0 65 10 0 126 191
12M A 2 42 270 2 0 102 0 0 1 103
12M T 0 0 1 0 0 4 0 0 0 4
14M S 0 0 116 0 0 5 0 0 17 22
14M A 0 12 36 0 0 35 0 0 0 35
14M T 0 0 0 0 0 0 0 0 0 0
Total 42 869 5143 32 0 518 10 0 233 751
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 25.13 12.51 732.91 Good Medium Fault Monthly Yearly
Gravel [m3] 0.00 17.52 371.15 9M S 18 0 0 0 0
Cement [T] 0.00 10.95 147.98 9M A 2 0 0 0 0
Admixture [Kg] 0.00 88.60 12317.96 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 18 0 0 2 7
Diesel [L] 300.00 150 180 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 816.54 345.00 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 19,772.41 14M S 0 0 0 0 1
PC wire (9mm) [Kg] 0.00 0.00 4,257.00 14M A 0 0 0 1 1
Cold drawn wire (2.8mm) [Kg] 0.00 105.08 1,764.000 14M T 0 0 0 0 0
D-Bar (14mm) [Kg] 0.00 73.40 1,737.320
Total 42 0 0 3 10
Tie-wire (1mm) [Kg] 0.00 0.00 500.0
Generator (300KVA) (Litters)
Daily Monthly Yearly
EDC (KWH) Hours Litters Hours Litters Hours Litters
Daily Monthly Yearly 4:50 150 120.11 2040 617.39 9620
3
126 1984 192326 Ready Mixed Concrete Delivery (M )
Delivery Specification Daily Monthly Yearly
Type Daily Plan Monthly Yearly 20-40-12 0 0 0.4
9M S 0 0 231 2424 25-15-12 0 9 61
9M A 0 0 4 330 25-21-12 0 349.5 649
9M T 0 0 0 92 Total 0 358.5 710.4
12M S 0 0 195 1865
12M A 0 0 9 223 Concrete Pipe
12M T 0 0 0 20 Type Daily Monthly Yearly Out Balance
14M S 0 0 0 109 Ø300 0 17 127 0 198
14M A 0 0 0 0 Total 0 17 127 0 198
14M T 0 0 0 0
Total 0 0 439 5063
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 110 1740 0 0 0
9m-A 135 320 0 0 0
9m-T 62 150 0 0 0
12m-S 65 101 0 0 0
12m-A 102 70 0 0 0
14m-S 5 0 0 0 0
Total 479 2381 0 0 0

Yearly Balance
10372 10372

In 2011 Out 2011


5229 4529

29

4.8333333333
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
24/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
6 3 28 4 19 4 64

Items / EDC Stock Quantity Stock Quantity All


Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 18 357 2158 18 0 128 0 0 0 128
9M A 2 46 389 2 0 137 0 0 79 216
9M T 2 46 157 2 0 64 0 0 10 74
12M S 18 406 2056 8 0 73 10 0 136 209
12M A 2 44 272 2 0 104 0 0 1 105
12M T 0 0 1 0 0 4 0 0 0 4
14M S 0 0 116 0 0 5 0 0 17 22
14M A 0 12 36 0 0 35 0 0 0 35
14M T 0 0 0 0 0 0 0 0 0 0
Total 42 911 5185 32 0 550 10 0 243 793
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 0.00 12.50 720.41 Good Medium Fault Monthly Yearly
Gravel [m3] 0.00 17.63 353.52 9M S 18 0 0 0 0
Cement [T] 0.00 11.02 136.96 9M A 2 0 0 0 0
Admixture [Kg] 0.00 89.02 12228.94 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 18 0 0 2 7
Diesel [L] 0.00 60 120 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 816.54 18,955.87 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 4,257.00 14M S 0 0 0 0 1
PC wire (9mm) [Kg] 0.00 0.00 1,764.00 14M A 0 0 0 1 1
Cold drawn wire (2.8mm) [Kg] 0.00 105.08 6,327.460 14M T 0 0 0 0 0
D-Bar (14mm) [Kg] 2007.90 73.40 3,671.820
Total 42 0 0 3 10
Tie-wire (1mm) [Kg] 1000.00 0.00 1,500.0
Generator (300KVA) (Litters)
Daily Monthly Yearly
EDC (KWH) Hours Litters Hours Litters Hours Litters
Daily Monthly Yearly 4:40 0 124.77 2040 617.39 9620
3
0 1984 192326 Ready Mixed Concrete Delivery (M )
Delivery Specification Daily Monthly Yearly
Type Daily Plan Monthly Yearly 20-40-12 0 0 0.4
9M S 0 0 231 2424 25-15-12 0 9 61
9M A 0 0 4 330 25-21-12 0 349.5 649
9M T 0 0 0 92 Total 0 358.5 710.4
12M S 0 0 195 1865
12M A 0 0 9 223 Concrete Pipe
12M T 0 0 0 20 Type Daily Monthly Yearly Out Balance
14M S 0 0 0 109 Ø300 0 17 127 0 198
14M A 0 0 0 0 Total 0 17 127 0 198
14M T 0 0 0 0
Total 0 0 439 5063
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 128 1740 0 0 0
9m-A 137 320 0 0 0
9m-T 64 150 0 0 0
12m-S 73 101 0 0 0
12m-A 104 70 0 0 0
14m-S 5 0 0 0 0
Total 511 2381 0 0 0

Yearly Balance
10414 10414

In 2011 Out 2011


5229 4529

29

4.6666666667
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
25/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
6 3 29 4 19 3 64
Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 18 375 2176 18 0 146 0 0 0 146
9M A 2 48 391 2 0 139 0 0 79 218
9M T 2 48 159 2 0 66 0 0 10 76
12M S 18 424 2074 8 0 81 10 30 116 197
12M A 2 46 274 2 0 106 0 0 1 107
12M T 0 0 1 0 0 0 0 3 1 1
14M S 0 0 116 0 0 5 0 7 10 15
14M A 0 12 36 0 0 35 0 0 0 35
14M T 0 0 0 0 0 0 0 0 0 0
Total 42 953 5227 32 0 578 10 40 217 795
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 0.00 12.60 707.81 Good Medium Fault Monthly Yearly
Gravel [m3] 0.00 17.38 336.14 9M S 18 0 0 0 0
Cement [T] 30.85 10.94 156.87 9M A 2 0 0 0 0
Admixture [Kg] 0.00 88.26 12140.68 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 18 0 0 2 7
Diesel [L] 0.00 90 30 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 816.54 345.00 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 18,139.33 14M S 0 0 0 0 1
PC wire (9mm) [Kg] 0.00 0.00 4,257.00 14M A 0 0 0 1 1
Cold drawn wire (2.8mm) [Kg] 0.00 105.08 1,764.000 14M T 0 0 0 0 0
D-Bar (14mm) [Kg] 0.00 0.00 6,222.380
Total 42 0 0 3 10
Tie-wire (1mm) [Kg] 0.00 0.00 1,500.0
Generator (300KVA) (Litters)
Daily Monthly Yearly
EDC (KWH) Hours Litters Hours Litters Hours Litters
Daily Monthly Yearly 4:11 90 128.95 2130 621.57 9710
3
0 1984 192326 Ready Mixed Concrete Delivery (M )
Delivery Specification Daily Monthly Yearly
Type Daily Plan Monthly Yearly 20-40-12 0 0 0.4
9M S 0 0 231 2424 25-15-12 0 9 61
9M A 0 0 4 330 25-21-12 0 349.5 649
9M T 0 0 0 92 Total 0 358.5 710.4
12M S 30 0 225 1895
12M A 0 0 9 223 Concrete Pipe
12M T 3 0 3 23 Type Daily Monthly Yearly Out Balance
14M S 7 0 7 116 Ø300 0 17 127 0 198
14M A 0 0 0 0 Total 0 17 127 0 198
14M T 0 0 0 0
Total 40 0 479 5103
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 146 1740 0 0 0
9m-A 139 320 0 0 0
9m-T 66 150 0 0 0
12m-S 81 101 0 0 0
12m-A 106 70 0 0 0
14m-S 5 0 0 0 0
Total 543 2381 0 0 0

Yearly Balance
10456 10456

In 2011 Out 2011


5229 4529

29

4.1833333333
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
26/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
5 2 30 4 21 0 62
Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 18 393 2194 18 0 164 0 0 0 164
9M A 2 50 393 2 0 141 0 0 79 220
9M T 2 50 161 2 0 68 0 0 10 78
12M S 18 442 2092 8 0 89 10 0 126 215
12M A 2 48 276 2 0 108 0 0 1 109
12M T 0 0 1 0 0 0 0 0 1 1
14M S 0 0 116 0 0 5 0 0 10 15
14M A 0 12 36 0 0 33 0 2 0 33
14M T 0 0 0 0 0 0 0 0 0 0
Total 42 995 5269 32 0 608 10 2 227 835
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 0.00 12.53 695.28 Good Medium Fault Monthly Yearly
Gravel [m3] 0.00 17.37 318.77 9M S 18 0 0 0 0
Cement [T] 0.00 10.89 145.98 9M A 2 0 0 0 0
Admixture [Kg] 0.00 90.60 12050.08 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 18 0 0 2 7
Diesel [L] 300.00 210 120 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 680.88 17,458.45 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 4,257.00 14M S 0 0 0 0 1
PC wire (9mm) [Kg] 0.00 0.00 1,764.00 14M A 0 0 0 1 1
Cold drawn wire (2.8mm) [Kg] 0.00 86.16 6,136.220 14M T 0 0 0 0 0
D-Bar (14mm) [Kg] 0.00 60.70 3,537.720
Total 42 0 0 3 10
Tie-wire (1mm) [Kg] 0.00 0.00 1,500.0
Generator (300KVA) (Litters)
Daily Monthly Yearly
EDC (KWH) Hours Litters Hours Litters Hours Litters
Daily Monthly Yearly 2:47 150 131.73 2280 624.35 9860
3
0 1984 192326 Ready Mixed Concrete Delivery (M )
Delivery Specification Daily Monthly Yearly
Type Daily Plan Monthly Yearly 20-40-12 0 0 0.4
9M S 0 0 231 2424 25-15-12 0 9 61
9M A 0 0 4 330 25-21-12 0 349.5 649
9M T 0 0 0 92 Total 0 358.5 710.4
12M S 0 0 225 1895
12M A 0 0 9 223 Concrete Pipe
12M T 0 0 3 23 Type Daily Monthly Yearly Out Balance
14M S 0 0 7 116 Ø300 0 17 127 0 198
14M A 2 0 2 2 Total 0 17 127 0 198
14M T 0 0 0 0
Total 2 0 481 5105
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 164 1740 0 0 0
9m-A 141 320 0 0 0
9m-T 68 150 0 0 0
12m-S 89 101 0 0 0
12m-A 108 70 0 0 0
14m-S 5 0 0 0 0
Total 575 2381 0 0 0

Yearly Balance
10498 10498

In 2011 Out 2011


5229 4529

29

2.7833333333
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
27/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
0 0 26 3 17 0 46
Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 18 411 2212 18 0 182 0 0 0 182
9M A 2 52 395 2 0 143 0 0 79 222
9M T 2 52 163 2 0 70 0 0 10 80
12M S 18 460 2110 8 0 97 10 0 136 233
12M A 2 50 278 2 0 110 0 0 1 111
12M T 0 0 1 0 0 0 0 0 1 1
14M S 0 0 116 0 0 5 0 0 10 15
14M A 0 12 36 0 0 33 0 0 0 33
14M T 0 0 0 0 0 0 0 0 0 0
Total 42 1037 5311 32 0 640 10 0 237 877
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 0.00 12.65 682.63 Good Medium Fault Monthly Yearly
Gravel [m3] 0.00 17.45 301.32 9M S 18 0 0 0 0
Cement [T] 0.00 10.90 135.08 9M A 2 0 0 0 0
Admixture [Kg] 0.00 88.82 11961.26 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 18 0 0 2 7
Diesel [L] 0.00 0 120 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 952.20 16,506.25 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 4,257.00 14M S 0 0 0 0 1
PC wire (9mm) [Kg] 0.00 0.00 1,764.00 14M A 0 0 0 1 1
Cold drawn wire (2.8mm) [Kg] 0.00 124.00 6,012.220 14M T 0 0 0 0 0
D-Bar (14mm) [Kg] 0.00 86.10 3,451.620
Total 42 0 0 3 10
Tie-wire (1mm) [Kg] 0.00 0.00 1,500.0
Generator (300KVA) (Litters)
Daily Monthly Yearly
EDC (KWH) Hours Litters Hours Litters Hours Litters
Daily Monthly Yearly 3:36 0 135.33 2280 627.95 9860
3
0 1984 192326 Ready Mixed Concrete Delivery (M )
Delivery Specification Daily Monthly Yearly
Type Daily Plan Monthly Yearly 20-40-12 0 0 0.4
9M S 0 0 231 2424 25-15-12 0 9 61
9M A 0 0 4 330 25-21-12 0 349.5 649
9M T 0 0 0 92 Total 0 358.5 710.4
12M S 0 0 225 1895
12M A 0 0 9 223 Concrete Pipe
12M T 0 0 3 23 Type Daily Monthly Yearly Out Balance
14M S 0 0 7 116 Ø300 0 17 127 0 198
14M A 0 0 2 2 Total 0 17 127 0 198
14M T 0 0 0 0
Total 0 0 481 5105
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 182 1740 0 0 0
9m-A 143 320 0 0 0
9m-T 70 150 0 0 0
12m-S 97 101 0 0 0
12m-A 110 70 0 0 0
14m-S 5 0 0 0 0
Total 607 2381 0 0 0

Yearly Balance
10540 10540

In 2011 Out 2011


5229 4529

29

3.6
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
28/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
6 3 27 4 17 4 61
Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 18 429 2230 18 0 200 0 0 0 200
9M A 2 54 397 2 0 145 0 0 79 224
9M T 2 54 165 2 0 72 0 0 10 82
12M S 18 478 2128 8 0 105 10 0 146 251
12M A 2 52 280 2 0 112 0 0 1 113
12M T 0 0 1 0 0 0 0 0 1 1
14M S 0 0 116 0 0 5 0 0 10 15
14M A 0 12 36 0 0 33 0 0 0 33
14M T 0 0 0 0 0 0 0 0 0 0
Total 42 1079 5353 32 0 672 10 0 247 919
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 0.00 12.43 670.20 Good Medium Fault Monthly Yearly
Gravel [m3] 0.00 17.60 283.72 9M S 18 0 0 0 0
Cement [T] 0.00 11.05 154.49 9M A 2 0 0 0 0
Admixture [Kg] 0.00 89.20 11872.06 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 18 0 0 2 7
Diesel [L] 0.00 90 30 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 370.18 16,136.07 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 4,257.00 14M S 0 0 0 0 1
PC wire (9mm) [Kg] 0.00 0.00 1,764.00 14M A 0 0 0 1 1
Cold drawn wire (2.8mm) [Kg] 0.00 43.96 5,968.260 14M T 0 0 0 0 0
D-Bar (14mm) [Kg] 0.00 31.00 3,420.620
Total 42 0 0 3 10
Tie-wire (1mm) [Kg] 0.00 0.00 1,500.0
Generator (300KVA) (Litters)
Daily Monthly Yearly
EDC (KWH) Hours Litters Hours Litters Hours Litters
Daily Monthly Yearly 2:44 0 138.06 2280 630.68 9860
3
0 1984 192326 Ready Mixed Concrete Delivery (M )
Delivery Specification Daily Monthly Yearly
Type Daily Plan Monthly Yearly 20-40-12 0 0 0.4
9M S 0 0 231 2424 25-15-12 0 9 61
9M A 0 0 4 330 25-21-12 0 349.5 649
9M T 0 0 0 92 Total 0 358.5 710.4
12M S 0 0 225 1895
12M A 0 0 9 223 Concrete Pipe
12M T 0 0 3 23 Type Daily Monthly Yearly Out Balance
14M S 0 0 7 116 Ø300 0 17 127 0 198
14M A 0 0 2 2 Total 0 17 127 0 198
14M T 0 0 0 0
Total 0 0 481 5105
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 200 1740 0 0 0
9m-A 145 320 0 0 0
9m-T 72 150 0 0 0
12m-S 105 101 0 0 0
12m-A 112 70 0 0 0
14m-S 5 0 0 0 0
Total 639 2381 0 0 0

Yearly Balance
10582 10582

In 2011 Out 2011


5229 4529

EDC Normal
3 1

29
0

2.7333333333
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
29/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
6 3 29 4 17 2 61
Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 18 447 2248 18 0 218 0 0 0 218
9M A 2 56 399 2 0 147 0 0 79 226
9M T 2 56 167 2 0 74 0 0 10 84
12M S 18 496 2146 8 0 113 10 0 156 269
12M A 2 54 282 2 0 114 0 0 1 115
12M T 0 0 1 0 0 0 0 0 1 1
14M S 0 0 116 0 0 5 0 0 10 15
14M A 0 12 36 0 0 33 0 0 0 33
14M T 0 0 0 0 0 0 0 0 0 0
Total 42 1121 5395 32 0 704 10 0 257 961
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 0.00 12.74 657.46 Good Medium Fault Monthly Yearly
Gravel [m3] 42.40 17.31 308.81 9M S 18 0 0 0 0
Cement [T] 0.00 11.07 143.43 9M A 2 0 0 0 0
Admixture [Kg] 0.00 65.58 11806.48 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 18 0 0 2 7
Diesel [L] 300.00 180 150 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 892.72 15,243.35 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 4,257.00 14M S 0 0 0 0 1
PC wire (9mm) [Kg] 0.00 0.00 1,764.00 14M A 0 0 0 1 1
Cold drawn wire (2.8mm) [Kg] 0.00 122.24 5,846.000 14M T 0 0 0 0 0
D-Bar (14mm) [Kg] 0.00 84.80 3,335.820
Total 42 0 0 3 10
Tie-wire (1mm) [Kg] 0.00 0.00 1,500.0
Generator (300KVA) (Litters)
Daily Monthly Yearly
EDC (KWH) Hours Litters Hours Litters Hours Litters
Daily Monthly Yearly 3:02 150 141.09 2430 633.71 10010
3
0 1984 192326 Ready Mixed Concrete Delivery (M )
Delivery Specification Daily Monthly Yearly
Type Daily Plan Monthly Yearly 20-40-12 0 0 0.4
9M S 0 0 231 2424 25-15-12 0 9 61
9M A 0 0 4 330 25-21-12 0 349.5 649
9M T 0 0 0 92 Total 0 358.5 710.4
12M S 0 0 225 1895
12M A 0 0 9 223 Concrete Pipe
12M T 0 0 3 23 Type Daily Monthly Yearly Out Balance
14M S 0 0 7 116 Ø300 0 17 127 0 198
14M A 0 0 2 2 Total 0 17 127 0 198
14M T 0 0 0 0
Total 0 0 481 5105
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 218 1740 0 0 0
9m-A 147 320 0 0 0
9m-T 74 150 0 0 0
12m-S 113 101 0 0 0
12m-A 114 70 0 0 0
14m-S 5 0 0 0 0
Total 671 2381 0 0 0

Yearly Balance
10624 10624

In 2011 Out 2011


5229 4529

EDC Normal
3 1

29
0

3.0333333333
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
30/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
6 3 29 4 18 1 61
Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 18 465 2266 15 0 233 3 3 0 233
9M A 2 58 401 2 0 149 0 0 79 228
9M T 2 58 169 2 0 76 0 0 10 86
12M S 18 514 2164 8 0 121 10 0 166 287
12M A 2 56 284 2 0 116 0 0 1 117
12M T 0 0 1 0 0 0 0 0 1 1
14M S 0 0 116 0 0 5 0 0 10 15
14M A 0 12 36 0 0 33 0 0 0 33
14M T 0 0 0 0 0 0 0 0 0 0
Total 42 1163 5437 29 0 733 13 3 267 1000
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 0.00 12.43 645.03 Good Medium Fault Monthly Yearly
Gravel [m3] 0.00 17.22 291.59 9M S 18 0 0 0 0
Cement [T] 0.00 10.93 132.50 9M A 2 0 0 0 0
Admixture [Kg] 0.00 65.34 11741.14 9M T 2 0 0 0 1
Mold oil [Kg] 0.00 0 820 12M S 18 0 0 2 7
Diesel [L] 0.00 30 345 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 576.98 14,666.37 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 4,257.00 14M S 0 0 0 0 1
PC wire (9mm) [Kg] 0.00 0.00 1,764.00 14M A 0 0 0 1 1
Cold drawn wire (2.8mm) [Kg] 0.00 71.24 5,774.780 14M T 0 0 0 0 0
D-Bar (14mm) [Kg] 0.00 49.25 3,286.580
Total 42 0 0 3 10
Tie-wire (1mm) [Kg] 0.00 0.00 1,500.0
Generator (300KVA) (Litters)
Daily Monthly Yearly
EDC (KWH) Hours Litters Hours Litters Hours Litters
Daily Monthly Yearly 3:27 0 144.54 2430 637.16 10010
3
0 1984 192326 Ready Mixed Concrete Delivery (M )
Delivery Specification Daily Monthly Yearly
Type Daily Plan Monthly Yearly 20-40-12 0 0 0.4
9M S 3 0 234 2427 25-15-12 0 9 61
9M A 0 0 4 330 25-21-12 0 349.5 649
9M T 0 0 0 92 Total 0 358.5 710.4
12M S 0 0 225 1895
12M A 0 0 9 223 Concrete Pipe
12M T 0 0 3 23 Type Daily Monthly Yearly Out Balance
14M S 0 0 7 116 Ø300 0 17 127 0 198
14M A 0 0 2 2 Total 0 17 127 0 198
14M T 0 0 0 0
Total 3 0 484 5108
EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 233 1740 0 0 0
9m-A 149 320 0 0 0
9m-T 76 150 0 0 0
12m-S 121 101 0 0 0
12m-A 116 70 0 0 0
14m-S 5 0 0 0 0
Total 700 2381 0 0 0

Yearly Balance
10666 10666

In 2011 Out 2011


5229 4529

EDC Normal
3 1

29
0

3.45
AJU Industry (Cambodia) Co., Ltd.

Date Production QC Sale Administation General Manager Director


Charger
31/May/2012

GENERAL REPORT
Administation
Admin & Acc Marketing Production QC Daily worker Absent Total
6 3 29 4 17 2 61
Production
Items / EDC Stock Quantity Stock Quantity All
Daily Monthly Yearly
Description In Out Balance In Out Balance Balance
9M S 18 483 2284 6 0 239 12 12 0 239
9M A 2 60 403 2 170 -19 0 0 79 60
9M T 2 60 171 2 100 -23 0 0 10 -13
12M S 18 532 2182 8 0 129 10 50 126 255
12M A 2 58 286 2 70 48 0 0 1 49
12M T 0 0 1 0 0 0 0 0 1 1
14M S 0 0 116 0 0 5 0 0 10 15
14M A 0 12 36 0 0 33 0 0 0 33
14M T 0 0 0 0 0 0 0 0 0 0
Total 42 1205 5479 20 340 412 22 62 227 639
Material Concrete Pole Classification
Stock Quantity Broken
Items / Description Classification
In Out Balance Items Tested Pole
3
Sand [m ] 0.00 238.85 406.18 Good Medium Fault Monthly Yearly
Gravel [m3] 0.00 242.08 49.51 9M S 18 0 0 0 0
Cement [T] 31.08 117.95 45.63 9M A 2 0 0 0 0
Admixture [Kg] 0.00 504.48 11236.66 9M T 2 0 0 1 2
Mold oil [Kg] 0.00 0 820 12M S 18 0 0 2 7
Diesel [L] 0.00 30 90 12M A 2 0 0 0 0
PC wire (5mm) [Kg] 0.00 1426.28 13,240.09 12M T 0 0 0 0 0
PC wire (7mm) [Kg] 0.00 0.00 4,257.00 14M S 0 0 0 0 1
PC wire (9mm) [Kg] 0.00 0.00 1,764.00 14M A 0 0 0 1 1
Cold drawn wire (2.8mm) [Kg] 0.00 182.88 5,591.900 14M T 0 0 0 0 0
D-Bar (14mm) [Kg] 0.00 128.56 3,158.020
Total 42 0 0 4 11
Tie-wire (1mm) [Kg] 0.00 550.00 950.0
Generator (300KVA) (Litters)
Daily Monthly Yearly
EDC (KWH) Hours Litters Hours Litters Hours Litters
Daily Monthly Yearly 2:43 0 147.25 2430 639.87 9980
3
0 1984 192326 Ready Mixed Concrete Delivery (M )
Delivery Specification Daily Monthly Yearly
Type Daily Plan Monthly Yearly 20-40-12 0 0 0.4
9M S 12 0 246 2439 25-15-12 0 9 61
9M A 170 0 174 500 25-21-12 0 349.5 649
9M T 100 0 100 192 Total 0 358.5 710.4
12M S 50 0 275 1945
12M A 70 0 79 293 Concrete Pipe
12M T 0 0 3 23 Type Daily Monthly Yearly Out Balance
14M S 0 0 7 116 Ø300 0 18 128 0 199
14M A 0 0 2 2 Total 0 18 128 0 199
14M T 0 0 0 0
Total 402 0 886 5510
,

EDC GOAL

POLE Current Stock Goal Remain Out Delivery Remain


9m-S 239 1740 0 0 0
9m-A -19 320 0 0 0
9m-T -23 150 0 0 0
12m-S 129 101 0 0 0
12m-A 48 70 0 0 0
14m-S 5 0 0 0 0
Total 379 2381 0 0 0

Yearly Balance
10708 10708

In 2011 Out 2011


5229 4529

12m-S
EDC Normal
3 1

30

2.7166666667